You are a project manager for Move It Now trucking company. Your company

specializes in moving household goods across the city or across the country. Your project

involves upgrading the nationwide computer network for the company. Your lead

engineer has given you the following estimates for a critical path activity: 60 days most

likely, 72 days pessimistic, 48 days optimistic. What is the weighted average or expected

value?

A. 54

B. 66

C. 60

D. 30

1 Answer

Answer :

C. 60

Related questions

Description : For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is (A) 8 days (B) 9 days (C) 10 days (D) 15 days

Last Answer : (B) 9 days

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is (A) (a + m + b)/6 (B) (a + 2m + b)/6 (C) (a + 4m + b)/6 (D) (a + 5m + b)/6

Last Answer : (C) (a + 4m + b)/6

Description : If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively (A) 3.5 and 5/6 (B) 5 and 25/36 (C) 3.5 and 25/36 (D) 4 and 5/6

Last Answer : (C) 3.5 and 25/36

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : The area under the Beta distribution curve is divided into two equal parts by (A) Most likely time (B) Optimistic time (C) Pessimistic time (D) Expected time

Last Answer : (D) Expected time

Description : You are a project manager for Cinema Snicker Productions. Your company  specializes in producing comedy films for the big screen. Your latest project has just been  cancelled because of budget cuts ... elsewhere. D. This project ended due to integration because the funding was cut off.

Last Answer : A. This project ended due to starvation because the funding was cut off.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above

Last Answer : D. all of the above

Description : Pick up the correct statement from the following: (A) Optimistic time estimate refers to activities (B) Pessimistic time estimate refers to activities (C) Most likely time estimate refers to activities (D) All the above

Last Answer : (D) All the above

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : Are you pessimistic or optimistic for the economic future of your country?

Last Answer : answer:I agree with David Suzuki that economics is a mental illness. From inside that illness, I think that things may go up or down but that it will eventually get worse and worse, unless/until many things change that are outside the mental box of that illness.

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing

Description : . A project leader or manager is expected to be completely accountable for his team  members and meeting the team’s targets. (True/False)

Last Answer : Ans. True

Description : How does a project differ from an ongoing work effort?  A. It is unique B. It involves more than one person C. It has a project manager D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Last Answer : D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : What would be the critical path if the duration of activity C increased to 10? A. ABCF B. ABCEF C. ABGHIF D. ABGHIF & ABDEF

Last Answer : A. ABCF

Description : The population of a city in 2000 is 50,000. The average increase in population over last 8 decades is  7500 and average incremental increase during 8 decades is 750. The population of the city based  on incremental method, in ... (A) 55,000  (B) 60,500  (C) 66,500  (D) 72,500 

Last Answer : (C) 66,500

Description : )The critical element in a project's communication system is the: 1. Progress report * 2. Project directive  3. Project manager  4. Customer

Last Answer : 3. Project manager

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time D. between normal time and crash time

Last Answer : D. between normal time and crash time

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time

Last Answer : D. between normal time and crash time

Description : When planning a systems project, overly optimistic timetables are the cause of project  completion delays.

Last Answer : Ans: True

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : Are humans naturally optimistic or pessimistic?

Last Answer : neither, we are neutral at birth and the effects of life change us to think one way or the other.

Description : Are you optimistic or pessimistic about our future? (Immediate and Long-term)

Last Answer : Well, lloydbird honey, I don't know how much of a future we have since I'm a happily married woman . . . Oh, wait, us? Humanity? I think the future looks bright. While I don't ... the importance of saving our planet and its resources. Fluther gives me hope, especially the posts of the young people.

Description : What situation best describes a difference in interpretation A.One painter's life work shows an optimistic outlook while another painter's life work shows a deeply pessimistic outlook. B.One noveli?

Last Answer : What is the answer ?

Description : The maximise criteria is ........................... a. Optimistic b. Pessimistic c. Neutral d. None of these

Last Answer : b. Pessimistic

Description : The average weight of four boys A, B, C, and D is 75 kg. The fifth boy E is included and the average weight decreases by 4 kg. A is replaced by F. The weight of F is 6 kg more than E. Average weight decreases because of ... . Find the weight of A. 1) 57 kg 2) 54 kg 3) 56 kg 4) 60 kg 5) 58 kg

Last Answer : 3) 56 kg

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is the critical path through the network above? A. ABGHIF B. ABDEF C. ABGHIF& ABDEF D. AB CEF

Last Answer : B. ABDEF

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : The critical angle for two media with permittivities of 16 and 9 respectively is a) 48.59 b) 54.34 c) 60 d) 45

Last Answer : a) 48.59

Description : Which method is not included in seven Project Selection Methods?  A. Financial Analysis B. Strategic Alignment C. Weighted Scoring Model D. Straight line Model (Ans.)

Last Answer : D. Straight line Model (Ans.)