You are a project manager for Move It Now trucking company. Your company
specializes in moving household goods across the city or across the country. Your project
involves upgrading the nationwide computer network for the company. Your lead
engineer has given you the following estimates for a critical path activity: 60 days most
likely, 72 days pessimistic, 48 days optimistic. What is the weighted average or expected
value?
A. 54
B. 66
C. 60
D. 30