Which of the following statement(s) is/are true about a Project?

I. It brings change

II. It has risk

III. The outcome is certain

(A) I only

(B) II only

(C) I and II only

(D) I, II, and III

1 Answer

Answer :

(C) I and II only

Related questions

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : The main outcome of risk identification, in a risk management process, is to:  a. identify and determine the relative importance of the project risks.  b. identify and describe all risks that ... to the project risks.  d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : Which from the following statement(s) is/are NOT true? I. Projects have defined objectives II. Programs have a larger scope than projects III. The projects and programs in a portfolio must be directly related (A) I only (B) II only (C) III only (D) II and III only

Last Answer : (C) III only

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.

Last Answer : a. All variance to the project scope is evaluated.

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Which one of the following does project change control primarily seek to ensure?  a. All variance to the project scope is evaluated.  b. No reduction in the perceived quality of the project outcome ... project do not increase.  d. Any decrease in the scoped deliverable of the project is rejected

Last Answer : a. All variance to the project scope is evaluated.

Description : Which one of the following best describes a project stakeholder? a. A party who is concerned about the project going ahead. b. A party with an interest or role in the project or is impacted by ... of the project. d. A party who has a financial stake in the organization managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : Which one of the following best describes a project stakeholder?  a. A party who is concerned about the project going ahead.  b. A party with an interest or role in the project or is impacted by ... of the project.  d. A party who has a financial stake in the organisation managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : Normally a performance bond, depending upon the state, only stipulates that the contractor will guarantee the work for a certain period of time.  Answer: D  (8)Which contract type places the most risk on ... fee  3. Cost plus fixed fee  4. Fixed price plus incentive fee  5. Firm fixed price

Last Answer : 5. Firm fixed price

Description : All of the following statements are true regarding risks except for which one? Choose the least correct answer.  A. Risks might be threats to the objectives of the project.  B. Risks are ... Risks might be opportunities to the objectives of the project.  D. Risks have causes and consequences.

Last Answer : B. Risks are certain events that may be threats or opportunities to the objectives of  the project

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Which of the following is/are true if a firm has a required rate of return equal to the ROE? I. The amount of earnings retained by the firm does not affect market price or the P/E. II. The firm can increase market ... (III) above D. Both (II) and (III) above E. All (I), (II) and (III) above

Last Answer : E. All (I), (II) and (III) above

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : Who has ultimate responsibility for project risk? a. Steering group. b. Risk owner. c. Project sponsor. d. Project manager.

Last Answer : c. Project sponsor.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which one of the following statements about the project risk register is false? a. It facilitates the review and monitoring of risks. b. It facilitates the risk appetite. c. It facilitates the recording of risk responses. d. It facilitates the recording of risks.

Last Answer : b. It facilitates the risk appetite.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management

Last Answer : C. project monitoring

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : An Expected Monetary Value (EMV) of $100000 on a potential project event in the  project means which of the following? Select one: a. A number that can be ignored b. An opportunity that ... Actual investment returns on the event e. A threat that must be considered to minimize the project risk

Last Answer : b. An opportunity that must be explored

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Fill in the blank. There is _______ correlation between project complexity  and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general

Last Answer : b. a positive

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above

Last Answer : c. Track progress

Description : Which of the following is not considered as a risk in project management? a. Specification delays b. Product competition c. Testing d. Staff turnover

Last Answer : c. Testing

Description : Which risk is connected to the circumstance outside the project that may influence the  scope of work and the performance of the organization?  A.Operational Risk  B.Financial Risk  C.Strategic Risk  D.Contextual Risk

Last Answer : D.Contextual Risk

Description : Risk Event Graph is having following on X axis  A.Gantt Chart  B.Work Break Down Structure  C.Project Life Cycle  D.Splitting

Last Answer : C.Project Life Cycle