Which one of the following best describes a project stakeholder?

a. A party who is concerned about the project going ahead.

b. A party with an interest or role in the project or is impacted by the project.

c. A party who has a vested interest in the outcome of the project.

d. A party who has a financial stake in the organization managing the project.

1 Answer

Answer :

b. A party with an interest or role in the project or is impacted by the project.

Related questions

Description : Which one of the following best describes a project stakeholder?  a. A party who is concerned about the project going ahead.  b. A party with an interest or role in the project or is impacted by ... of the project.  d. A party who has a financial stake in the organisation managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : To successfully manage a project, the PM must play both a manager and leadership role. In the manager role the PM will do all but which of the following: 1. Develop procedures  2. Align people  3. Produce results for stakeholder  4. Focus on the organization and its structure 5. Both b and d

Last Answer : 2. Align people

Description : Which of the following best describes a project environment? a. The type of organization concerned with implementation. b. The structured method used to control the project. c. The context within which a project is undertaken. d. An understanding of the risks involved in the project.

Last Answer : c. The context within which a project is undertaken.

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : As a PMP, you will be required to comply with the PMP Code of Professional  Conduct. This code refers to all of the following except which one?  A. Reporting conflicts of interest ... C. Complying with the stakeholder requirements D. Complying with the rules and standards of foreign countries

Last Answer : C. Complying with the stakeholder requirements

Description : In the context of strategic management, stakeholders can be defined as: a) An individual or group with a financial stake in the organization b) An external individual or group that is able to ... individual or group with an interest in the organization's activities and who seeks to influence them

Last Answer : An individual or group with an interest in the organization's activities and who seeks to influence them

Description : In the context of strategic management, stakeholders can be defined as: A. An individual or group with a financial stake in the organization B. An external individual or group that is able to ... individual or group with an interest in the organization's activities and who seeks to influence them

Last Answer : Internal groups or individuals that are able to influence strategic direction of the organization

Description : In the context of strategic management, stakeholders can be defined as: A. An individual or group with a financial stake in the organization B. An external individual or group that is able to ... individual or group with an interest in the organization's activities and who seeks to influence them

Last Answer : Internal groups or individuals that are able to influence strategic direction of the organization

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Which one of the following best defines a benefit? a. A positive result of stakeholder management. b. The successful management of a project. c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : Project reporting can best be defined as: a. informing stakeholders about the project. b. storing and archiving of project information. c. gathering stakeholder feedback. d. collecting project information.

Last Answer : a. informing stakeholders about the project.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : Which of the following is/are considered stakeholder in the process? a. Customers b. End-users c. Project managers d. All of the above.

Last Answer : d. All of the above.

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Which one of the following best defines a benefit?  a. A positive result of stakeholder management.  b. The successful management of a project.  c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : Project reporting can best be defined as:  a. informing stakeholders about the project.  b. storing and archiving of project information. c. gathering stakeholder feedback.  d. collecting project information.

Last Answer : a. informing stakeholders about the project

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : )The engineer of the project in the planning phase and makes a significant contribution to the  technical scope. This is an example of what type of skill and knowledge? 1. Inherent  2. Stakeholder  3. Technical evaluation  4. Convergent thinking

Last Answer : 2. Stakeholder

Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : Which of the following best describes a project environment? a. The type of organisation concerned with implementation.  b. The structured method used to control the project.  c. The context within which a project is undertaken.  d. An understanding of the risks involved in the project.

Last Answer : c. The context within which a project is undertaken.

Description : Political unrest, budget overruns, size and complexity of the project  Answer: B  (8)Decision trees are best used for : 1. Determining the interaction of the amount at stake and the expected ... and the associated events  4. A flow chart which determines the standard deviation of the risk event

Last Answer : 3. An illustration of how to see the interactions between decisions and the associated events

Description : The Three attributes of project risk are _________, ___________ and ___________. 1. What might happen, who it happens to, and how much will it cost  2. Notification, frequency of relevant events, ... planning, total number of risk events 5. Risk event, probability occurrence, the amount at stake

Last Answer : 5. Risk event, probability occurrence, the amount at stake

Description : Which risk is connected to the circumstance outside the project that may influence the  scope of work and the performance of the organization?  A.Operational Risk  B.Financial Risk  C.Strategic Risk  D.Contextual Risk

Last Answer : D.Contextual Risk

Description : . A key aspect of managing a project involves: a. defining which operational systems to put in place. b. identifying routine tasks. c. ensuring ongoing operations are maintained. d. planning to achieve defined objectives

Last Answer : d. planning to achieve defined objectives.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : The project you are managing has nine stakeholders. How many channel of communications are there between these stakeholders? a. 9 b. 8 c. 45 d. 36

Last Answer : d. 36

Description : Marco is an investor, and Jon is a project team member. Both have  intensive technical background for the project that you are managing.  However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company

Last Answer : c. The project team

Description : Michelle has decided to use a shortcut to determine the complexity of the project she  is currently managing. She has assigned the adjusted project complexity (PCA) a value  of .65. She has determined that ... _____.  a. bi-lateral  b. complex c. microconvergent  d. normal  e. very simple

Last Answer : e. very simple

Description : What are the 5 major processes of project management?  A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)  B. Starting, Closing, Managing, Planning, ... Finishing, Monitoring and Controlling, Executing, Planning D. Starting, Finishing, Executing, Managing, Closing

Last Answer : A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)

Description : The project you are managing has nine stakeholders. How many channel of communications  are there between these stakeholders? a. 9 b. 8 c. 45 d. 36

Last Answer : 36

Description : A key aspect of managing a project involves:  a. defining which operational systems to put in place. b. identifying routine tasks.  c. ensuring ongoing operations are maintained.  d. planning to achieve defined objectives.

Last Answer : d. planning to achieve defined objectives.

Description : Project risk management is best described as:  a. managing responses to threats.  b. identifying and acknowledging threats and opportunities.  c. planning responses to threats.  d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Why does a company choose to have an independent auditor report on its financial statements? a. Independent auditors will always detect management fraud. b. Independent auditors guarantee the accuracy ... . An independent audit is designed to search for deficiencies in the company's internal control

Last Answer : The company preparing the statements may have a vested interest in reporting certain results.

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : The document that identifies what information needs to be shared, to whom, why, when and  how is called the: a. communication management plan.  b. stakeholder mapping grid.  c. document distribution schedule.  d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Who Is A Stakeholder ?

Last Answer : Project stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They may ... possible, manage their influence in relation to the requirements to ensure a successful project.

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.

Last Answer : a. All variance to the project scope is evaluated.