Which of the following activity is not the part of project planning?

A. project estimation

B. project scheduling

C. project monitoring

D. risk management

1 Answer

Answer :

C. project monitoring

Related questions

Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation

Last Answer : B. Project Monitoring and Control

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description : Software safety is a ................... activity that focuses on the identification and assessment of potential hazards that may affect software negatively and cause an entire ... monitoring and management (B) Software quality assurance (C) Software cost estimation (D) Defect removal efficiency

Last Answer : (B) Software quality assurance

Description : Which one of the following statements about the project risk register is false? a. It facilitates the review and monitoring of risks. b. It facilitates the risk appetite. c. It facilitates the recording of risk responses. d. It facilitates the recording of risks.

Last Answer : b. It facilitates the risk appetite.

Description : Which one of the following statements about the project risk register is false?  a. It facilitates the review and monitoring of risks.  b. It facilitates the risk appetite.  c. It facilitates the recording of risk responses.  d. It facilitates the recording of risks

Last Answer : b. It facilitates the risk appetite

Description : Different activity of a project management is A. project planning B. project monitoring C. project control D. All of the above

Last Answer : B. project monitoring

Description : Which of the following is not the part of Risk Control  A. Execution of the risk response strategy  B. Monitoring of triggering events  C. Initiating contingency plans  D. Not watching for new risks

Last Answer : D. Not watching for new risks

Description : Which of the following is NOT a part of project management? (A) initiating (B) monitoring (C) closing (D) All above are parts

Last Answer : (D) All above are parts

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : In estimation of cost functions, variations in a single activity level represents the A. related total costs B. related fixed cost C. related variable cost D. related per unit cost

Last Answer : A. related total costs

Description : Relationship based on unrelated level of activity and past data of cost is measured with help of A. cost estimation B. price estimation C. unit estimation D. production estimation

Last Answer : A. cost estimation

Description : Which of the following serves as project estimation technique? A. Empirical estimation B. Heuristic technique C. Analytical estimation D. All of the above

Last Answer : D. All of the above

Description : Which of the following serves as metrics for project size estimation? A. Lines of codes B. function point C. Number of persons D. Only A & B

Last Answer : D. Only A & B

Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above

Last Answer : D. all of the above

Description : A is developed using historical cost information that relates  some metric to the project cost. a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : a) Algorithmic cost modelling

Description : Which stage of project management life cycle requires the maximum time of  completion  A.Conceptualization  B.Planning  C.Execution  D.Estimation

Last Answer : C.Execution

Description : When using a function point estimation worksheet, there are 14 factors that impact the complexity of a project. These factors include _____.  a. data communications, time tradeoffs, and ... programming language  d. reports printed and PCA  e. x-rays, extensibility, and operational conversion

Last Answer : b. end-user efficiency, data communications, and reusability

Description : The process of assigning values for the time and effort needed to perform a system  project is called _____.  a. analysis  b. estimation  c. identifying  d. planning

Last Answer : b. estimation

Description : _____ is the process of planning and controlling the development of a system within a  specified time frame at a minimum cost with the right functionality.  a. Project management  b. Symantic timeline  c. Task identification  d. Time estimation  e. Work plan

Last Answer : a. Project management

Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.

Last Answer : a. overall project duration.

Description : In project scheduling, resources are allocated so that project objectives are attained within a ……… a. sensible time span b. lavish time c. excessive d. undue

Last Answer : a. sensible time span

Description : According to leading experts in software development, the margin of error when  estimating project costs is 100% and the margin of error in project scheduling time is  25%.

Last Answer : Ans: True

Description : Scheduling can best be defined as the process used to determine:  a. overall project duration.  b. project cost estimating.  c. the project management plan.

Last Answer : a. overall project duration.

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : )Which of the following is NOT one of the primary needs for good project scheduling? 1. Cutting costs and reducing time  2. Decreasing the time required for decision making  3. Eliminating idle time  4. Developing better trouble shooting procedures.

Last Answer : 4. Developing better trouble shooting procedures.

Description : What Should The Project Manager Look For In A Scheduling System?

Last Answer : The three basic elements that the project scheduling systems should provide are; a common basis for communication at all operational levels of the project, a basis for regular status reporting, the use of the management by exception technique.

Description : The system of monitoring and control is more effective when, along with the time- frame, there is the linkage between the physical work to be performed in each activity and  the financial expenditure to be incurred. (True/False)

Last Answer : Ans. True

Description : The phases of a project life cycle are: a. starting, planning, control and closing. b. concept, definition, development, handover and closure. c. initiation, definition, planning, monitoring and operations. d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing

Description : What are the 5 major processes of project management?  A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)  B. Starting, Closing, Managing, Planning, ... Finishing, Monitoring and Controlling, Executing, Planning D. Starting, Finishing, Executing, Managing, Closing

Last Answer : A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)

Description : The phases of a project life cycle are:  a. starting, planning, control and closing.  b. concept, definition, development, handover and closure.  c. initiation, definition, planning, monitoring and operations.  d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : Quality control in the final analysis is : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements  2. a production system  3. an inspection system  4. fitness for purpose

Last Answer : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : A mean for monitoring and controlling organization's strategic projects is A. Project Monitoring process B. Project Portfolio Process C. Project Portfolio Plan D. Project Portfolio Phase

Last Answer : B. Project Portfolio Process

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : Which of the following is not a Configuration Management  Activity? a) Configuration item identification b) Risk management c) Release management d) Branch management

Last Answer : b) Risk management

Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.

Last Answer : a. identify project risks and then manage them appropriately.

Description : Who has ultimate responsibility for project risk? a. Steering group. b. Risk owner. c. Project sponsor. d. Project manager.

Last Answer : c. Project sponsor.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : An Expected Monetary Value (EMV) of $100000 on a potential project event in the  project means which of the following? Select one: a. A number that can be ignored b. An opportunity that ... Actual investment returns on the event e. A threat that must be considered to minimize the project risk

Last Answer : b. An opportunity that must be explored

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.