)The fixed price contract is advantageous to the buyer because it:

1. requires extremely well defined specifications 

2. requires formal procedures for scope changes 

3. contractor assumes financial and technical risk 

4. has a known cost

1 Answer

Answer :

3. contractor assumes financial and technical risk

Related questions

Description : Normally a performance bond, depending upon the state, only stipulates that the contractor will guarantee the work for a certain period of time.  Answer: D  (8)Which contract type places the most risk on ... fee  3. Cost plus fixed fee  4. Fixed price plus incentive fee  5. Firm fixed price

Last Answer : 5. Firm fixed price

Description : )A new project was initiated that involves new technology and subsequently has never been  done before. What type of contract would to owner want to issue to reduce or eliminate as much  risk as possible. 1. Firm ... 2. Cost plus fix fee  3. Cost plus incentive fee  4. Lump sum  5. A and D

Last Answer : 5. A and D

Description : Your company has asked you to be the project manager for the product introduction  of its new DeskTop Rock media system. You recently published the project scope  statement. Which ... . Constraints  B. Project specifications  C. Requested changes D. Project configuration management requirements

Last Answer : C. Requested changes

Description : Project Scope: 1. is of concern only at the start of the project  2. is mainly a problem to be handled by the change control procedures during the project  execution phase.  3. Should ... . is usually not a problem after the contract or other document authorizing the project has been  approved.

Last Answer : 3. Should be managed and controlled from the project concept through close-out

Description : A risk is defined as what might happened to the ____________ of the project 1. assessment  2. detriment  3. schedule  4. cost  5. scope

Last Answer : 2. detriment

Description : Which of the following type of contracts is most preferable to the contractor doing the project  work? 1. Cost plus fixed fee  2. Fixed price  3. Fixed price plus incentive free 4. B and C

Last Answer : 1. Cost plus fixed fee

Description : Which risk is connected to the circumstance outside the project that may influence the  scope of work and the performance of the organization?  A.Operational Risk  B.Financial Risk  C.Strategic Risk  D.Contextual Risk

Last Answer : D.Contextual Risk

Description : What are the signs that a project is in trouble? a. The product scope is poorly defined. b. Deadlines are unrealistic. c. Changes are managed poorly. d. All of the above.

Last Answer : d. All of the above.

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : A Unit Price (UP) contract provides: 1. a reimbursement of allowable costs plus a fixed fee which is paid proportionately as the  contract progresses  2. a reimbursement of allowable cost of services ... unit rates and the  final price is dependent on the quantities needed to carry out the work.

Last Answer : 4. a fixed price where the supplier agrees to furnish goods and services at unit rates and the  final price is dependent on the quantities needed to carry out the work

Description : Contract documentation is an input to both the Close Project and Contract Closure  processes. Contract documentation might include all of the following except for which  one?  A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents

Last Answer : D. Procurement audit documents

Description : Which of the following statements about independent financial statement audit is incorrect? a. The term "scope of the audit" refers to audit procedures deemed necessary in the circumstances ... uncover material misstatement is eliminated when the auditor conducts the audit in accordance with PSAs.

Last Answer : The risk that the auditor will fail to uncover material misstatement is eliminated when the auditor conducts the audit in accordance with PSAs.

Description : Which of the following is true?  A. Discounted cash flow analysis is the least precise of the cash flow techniques, because  it does not consider the time value of money. B. NPV is ... least precise of the cash flow analysis techniques, because it assumes  reinvestment at the cost of capital.

Last Answer : C. Payback period is the least precise of the cash flow analysis techniques, because it  does not consider the time value of money.

Description : . A project is typically defined in terms of scope, time, cost and which other parameter? a. Benefits. b. Quality. c. Tolerance. d. Controls.

Last Answer : b. Quality.

Description : A project is typically defined in terms of scope, time, cost and which other parameter?  a. Benefits. b. Quality.  c. Tolerance.  d. Controls.

Last Answer : b. Quality.

Description : )The engineer of the project in the planning phase and makes a significant contribution to the  technical scope. This is an example of what type of skill and knowledge? 1. Inherent  2. Stakeholder  3. Technical evaluation  4. Convergent thinking

Last Answer : 2. Stakeholder

Description : The contractor provides the financing and is paid an agreed fraction of actual savings  achieved. This payment is used to pay down the debt costs of equipment and/or services.  ... contract b) extended technical guarantee/service c) performance Contract d) shared savings performance contrac

Last Answer : d) shared savings performance contrac

Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project  management arena.

Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers,  supplementing that experience

Description : Which of the following auditor concerns most likely could be so serious that the auditor concludes that a financial statement audit cannot be conducted? a. The entity has no formal written ... subject to management override d. Management fails to modify prescribed controls for changes in conditions

Last Answer : The integrity of the entity’s management is suspect

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : Controlling the changes in the project may affect (A)The progress of the project (B)Stage cost (C)Project scope (D)All of the abov

Last Answer : (D)All of the abov

Description :  Which of the following processes are performed in the Closing process group and in  what order?  A. Contract Closure and then Close Project B. Scope Verification and then Close Project C. Contract Closure and then Scope Verification D. Close Project and then Contract Closure

Last Answer : A. Contract Closure and then Close Project

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract

Description : Quality control in the final analysis is : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements  2. a production system  3. an inspection system  4. fitness for purpose

Last Answer : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements

Description : Which of the following is not an example of formal communication? a. Contract b. email c. Project status report d. Status meeting

Last Answer : b. email

Description : Which of the following is not an example of formal communication? a. Contract b. email c. Project status report d. Status meeting

Last Answer : b. email

Description : Which one of the following best describes a project issue? a. A major problem that requires formal escalation. b. A problem that the project manager has to deal with on a day-to-day basis. c. An uncertain event that may or may not occur. d. An opportunity that occurs through change control.

Last Answer : a. A major problem that requires formal escalation.

Description : Which one of the following best describes a project issue?  a. A major problem that requires formal escalation.  b. A problem that the project manager has to deal with on a day-to-day basis.  c. An uncertain event that may or may not occur.  d. An opportunity that occurs through change control.

Last Answer : a. A major problem that requires formal escalation.

Description : Experience has shown that certain conditions in an organization are symptoms of possible management fraud. Which of the following conditions would not be considered an indicator of possible fraud? ... their profit center's scope d. Managers are not complying with corporate directives and procedures

Last Answer : Managers are subject to formal performance reviews on a regular basis.

Description :  The scope of the work is defined in which phase of the project management? (A) Initiating (B) Planning (C) Executing (D) Closing

Last Answer : (A) Initiating

Description : Which from the following statement(s) is/are NOT true? I. Projects have defined objectives II. Programs have a larger scope than projects III. The projects and programs in a portfolio must be directly related (A) I only (B) II only (C) III only (D) II and III only

Last Answer : (C) III only

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer store. Which type of contract will get signed in this case? A. Purchase Order B. Cost plus Fee C. Fixed cost D. Time and Material

Last Answer : A. Purchase Order

Description : .Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer  store. Which type of contract will get signed in this case? A. Purchase Order B. Cost plus Fee C. Fixed cost D. Time and Material

Last Answer : A. Purchase Order

Description : Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero.

Last Answer : D. IRR is the discount rate when NPV is equal to zero.

Description : Which of the following is true regarding NPV?  A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all the selections.  C. NPV assumes reinvestment at the prevailing rate.  D. NPV assumes reinvestment at the NPV rate.

Last Answer : A. NPV assumes reinvestment at the cost of capital.

Description : Change X requires a higher level of authority than Change Y in which of the following pairs? Change X Change Y A. Code in development Code in production B. Specifications during requirements ... Documents requested by customers D. A product distributed to several sites A product with a single user

Last Answer : D. A product distributed to several sites A product with a single user

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description : Scope creep is only a minor factor in projects running over schedule, and every effort  should be made to incorporate any changes into the present system if they would truly be  beneficial.

Last Answer : Ans: False

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : The internal auditing profession has advanced primarily as a result of a. Increased interest by Bachelor of Science in Accountancy (BSA) graduates and experienced auditors. b. The ... emphasis on background knowledge and skills. d. Increased complexity and sophistication of business operations.

Last Answer : Increased complexity and sophistication of business operations.

Description : An example of the risk involved in development is a) Key personnel may resign before the product is complete b) The manufacturer of critical components (e.g. the hardware  associated with a ... a fully functional lower-cost  equivalent package e) All of these are risks involved in development.

Last Answer : e) All of these are risks involved in development.

Description : When the purchasing manager for ABBA seat covers buys material and thread, he considers a variety of factors. Which one of the following is LEAST likely to concern the buyer in the purchase ... )does the supplier also sell to my competitors D)does the price meet the company budget requirements

Last Answer : C)does the supplier also sell to my competitors

Description : Which model assumes that systems are created fromreusable  components, scripting or database programming? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model

Last Answer : a) An application-composition model

Description : The individual or organisation who wants a product to be  developed is known as the: a) Developer (b) User (c)Contractor (d) Initiator (e) Client

Last Answer : (e) Client.

Description : Which of the following matters would an auditor most likely consider when establishing the scope of the audit? a. Audit areas where there is a higher risk of material misstatement. ... status of audit work throughout the engagement and the expected deliverables resulting from the audit procedures.