Project Scope:
1. is of concern only at the start of the project
2. is mainly a problem to be handled by the change control procedures during the project
execution phase.
3. Should be managed and controlled from the project concept through close-out
4. is usually not a problem after the contract or other document authorizing the project has been
approved.
1. is of concern only at the start of the project
2. is mainly a problem to be handled by the change control procedures during the project
execution phase.
3. Should be managed and controlled from the project concept through close-out
4. is usually not a problem after the contract or other document authorizing the project has been
approved.