Earned value management integrates scope, cost, and schedule measures to:
A. assess project performance and progress.
B. develop a preliminary budget.
C. assess communication effectiveness among project team members.
D. assess whether all requirements were met.
A. assess project performance and progress.
B. develop a preliminary budget.
C. assess communication effectiveness among project team members.
D. assess whether all requirements were met.