Which of the following processes assesses the likelihood of risk occurrences and their

consequences using a numerical rating?

A. Qualitative Risk Analysis

B. Risk Identification

C. Quantitative Risk Analysis

D. Risk Response Planning

1 Answer

Answer :

C. Quantitative Risk Analysis

Related questions

Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning

Last Answer : C. Qualitative Risk Analysis

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : The third stage of Resource Planning involves ? (a) Identification and inventory of resources. (b) Matching the resource development plan with overall National Development plan. (c) ... with appropriate technology. (d) Qualitative and quantitative estimation and measurement of the resources.

Last Answer : (b) Matching the resource development plan with overall National Development plan.

Description : An approach to location anal on analysis that include includes both qualitative and quantitative considerations is a. locational cost-volume b. factor rating c. transportation model d. assignment assignment method e. make or buy analysis

Last Answer : b. factor rating

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : What is a Research Design? (A) A way of conducting research that is not grounded in theory. (B) The choice between using qualitative or quantitative methods. (C) The style in which you present your research ... e.g. a graph. (D) A framework for every stage of the collection and analysis of data. 

Last Answer : (D) A framework for every stage of the collection and analysis of data.

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : Each of the following statements is true regarding the risk management plan except  for which one?  A. The risk management plan is an output of the Risk Management Planning process. B. The risk ... and budgets. D. The risk management plan is an input to all the remaining risk-planning processes.

Last Answer : B. The risk management plan includes a description of the responses to risks and  triggers.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.

Last Answer : c. Identify potential project risks.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Researchers use both open-ended and closed-ended questions to collect data. Which of the following statements is true? a. Open-ended questions directly provide quantitative data based on the ... own words d. Closed-ended questions directly provide qualitative data in the participants' own words

Last Answer : c. Open-ended questions provide qualitative data in the participant’s own words

Description : Which of the following statements is incorrect about materiality? a. The concept of materiality recognizes that some matters are important for fair presentation of financial statements in conformity with ... s perception of the needs of a reasonable person who will rely on the financial statements

Last Answer : An auditor considers materiality for planning purposes in terms of the largest aggregate level of misstatements that could be material to any one of the financial statements

Description : Quantitative data refers to (i) Graphs and tables (ii) Any data you present in your report (iii) Statistical analysis (iv) Numerical data that could be useful to answer your research question(s) and to meet your Objectives

Last Answer : (iv) Numerical data that could be useful to answer your research question(s) and to meet your Objectives

Description : The primary components of the quality management function are : 1. quality planning  2. quality control and assurance  3. quantitative measurement  4. quantitative assessment of the project

Last Answer : 5. a and b

Description : Answer: b Metabolic response to injury results in increased energy expenditure. If energy intake is less than expenditure, oxidation of body fat stores and erosion of lean body mass will occur ... requirements, caloric requirements should be distributed at a ratio of 70% as glucose and 30% as fat

Last Answer : Which of the following statement(s) is/are true concerning body fuel reserves? a. The largest fuel reserve in the body is skeletal muscle b. Fat provides about 9 calories/gram c. Free glucose and glycogen stores are a trivial fuel reserve d. Body protein is a valuable storage form of energy

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk

Last Answer : d. There are no risk-free projects.

Description : Which of the following is not a Configuration Management  Activity? a) Configuration item identification b) Risk management c) Release management d) Branch management

Last Answer : b) Risk management

Description : The main outcome of risk identification, in a risk management process, is to:  a. identify and determine the relative importance of the project risks.  b. identify and describe all risks that ... to the project risks.  d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : The main product is……….. a. project proposal b. Problem Identification c. Problem Definition d. Project Planning

Last Answer : a. project proposal

Description : _____ is the process of planning and controlling the development of a system within a  specified time frame at a minimum cost with the right functionality.  a. Project management  b. Symantic timeline  c. Task identification  d. Time estimation  e. Work plan

Last Answer : a. Project management

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : Using typical industry standards for estimating project time schedules, the estimated  analysis phase would be 10 person-months for a systems project where the planning phase was completed in 7.5 person-months.

Last Answer : Ans: True

Description : Using typical industry standards for estimating project time schedules, the estimated  analysis phase would be 25 person-months for a systems project where the planning phase was completed in 30 person-months.

Last Answer : Ans: False

Description : When estimating project time schedules using industry standards for a systems project,  the following values are acceptable: 15% for planning, 25% for analysis, 50% for design,  and 10% for implementation.

Last Answer : Ans: False

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Role clarification facilitates the development of all of the following, EXCEPT: Select one: a. communication planning. b. key milestones. c. work flow organization. d. approval processes. e. role boundary spanning processes.

Last Answer : b. key milestones.

Description : Project planning involves three processes:____ review, and __

Last Answer : Ans. Identification, analysis

Description : Following are the characteristics of Project Mindset. (A) Time, Responsiveness, Information sharing, Processes, structured planning (B) Time, Project management, Information sharing, Processes ... , structured planning (D) Time, Responsiveness, Information sharing, Processes, project planning

Last Answer : (A) Time, Responsiveness, Information sharing, Processes, structured planning

Description : Which of the following processes serve as inputs to each other?  A. Executing, and Monitoring and Controlling B. Executing and Closing C. Planning, and Monitoring and Controlling D. Executing and Initiation

Last Answer : A. Executing, and Monitoring and Controlling

Description : According to the PMBOK Guide, the project manager is identified and assigned  during which process?  A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process

Last Answer : C. Prior to beginning the Planning processes

Description : What are the 5 major processes of project management?  A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)  B. Starting, Closing, Managing, Planning, ... Finishing, Monitoring and Controlling, Executing, Planning D. Starting, Finishing, Executing, Managing, Closing

Last Answer : A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Which of the following is not the part of Risk Control  A. Execution of the risk response strategy  B. Monitoring of triggering events  C. Initiating contingency plans  D. Not watching for new risks

Last Answer : D. Not watching for new risks

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis

Last Answer : e) Risk analysis

Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.

Last Answer : d. minimising threats and maximising opportunities.

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk