According to the PMBOK guide, which of the following statements is 

right in terms of using reserve analysis to determine a project budget?

Select one:

A. Reserve analysis always plans contingency reserves for unexpected project scope and 

project costs, which are part of your project budget.

B. Reserves should not be included in the project budget.

C. If you only have limited resources, you may completely ignore reserve analysis when 

you try to determine your project budget.

D. Planning contingency reserves for a project is not practical.

E. Contingency reserves have never been a concern when planning a project budget.

1 Answer

Answer :

A. Reserve analysis always plans contingency reserves for unexpected project scope and 

project costs, which are part of your project budget.

Related questions

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : According to the PMBOK Guide, the project manager is identified and assigned  during which process?  A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process

Last Answer : C. Prior to beginning the Planning processes

Description : As a new project manager, Karen was worried about a statement from  her client: your project deliverable is in low quality with low grade .  According to PMBOK, how can you help Karen ... quality with high grade is always desirable to your client. e. High quality always  represents high grade.

Last Answer : c. Low quality represents a true problem, but low grade might not be the case.

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : When developing a project's scope statement, which of the following should not be  included? 1. Project justification.  2. Cost/benefit analysis  3. Project deliverables  4. Measurable objectives

Last Answer : 1. Project justification.

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : Which of these is not one of the constraints of a project? A. Scope B. Resources C. Team D. Budget

Last Answer : C. Team

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : Project Scope: 1. is of concern only at the start of the project  2. is mainly a problem to be handled by the change control procedures during the project  execution phase.  3. Should ... . is usually not a problem after the contract or other document authorizing the project has been  approved.

Last Answer : 3. Should be managed and controlled from the project concept through close-out

Description : Complete the following statement. As a project manager, Darrell is  excited that he is assigned to be in charge of the most important project  this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.

Last Answer : b. start to define and develop the stakeholder needs and requirements

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term  can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : _____________ is used to accomplish the project economically in the minimum available time with limited resources A. Project Scheduling. B. Network Analysis. C. Budget Analysis. D. Critical Planning.

Last Answer : A. Project Scheduling.

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description : According to the Project Management Institute (PMI), the scope statement should  address all of the following issues EXCEPT: Select one: a. project constraints. b. project assumptions c. project ... d. code of conduct for the team members working on the project. e. project deliverables.

Last Answer : d. code of conduct for the team members working on the project.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description : You are a project manager for Cinema Snicker Productions. Your company  specializes in producing comedy films for the big screen. Your latest project has just been  cancelled because of budget cuts ... elsewhere. D. This project ended due to integration because the funding was cut off.

Last Answer : A. This project ended due to starvation because the funding was cut off.

Description : Which of the following is not the part of Risk Control  A. Execution of the risk response strategy  B. Monitoring of triggering events  C. Initiating contingency plans  D. Not watching for new risks

Last Answer : D. Not watching for new risks

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : According to the Project Management Institute (PMI), project  management is defined as the application of knowledge, _____, _____, and  techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories

Last Answer : d. skills, tools

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : )In a program or project plan, there are always revisions to account for new or missing data.  Which one of the following provides the best reason for performing a revision of the plan? 1. ... 4. Historical data on a similar project suggests that risk events are not included in the current  plan.

Last Answer : 2. Project tasks are crashed to meet their end dates

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : A project charter does not include ____ of the project. (A) scope (B) objectives (C) team (D) all above are included

Last Answer : (D) all above are included

Description : Which of these characteristics are used to determine the scope of a project? a. Only performance. b. Only context. c. Information objectives, function, performance d. None of the above.

Last Answer : c. Information objectives, function, performance

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.

Last Answer : a. All variance to the project scope is evaluated.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : Which one of the following does project change control primarily seek to ensure?  a. All variance to the project scope is evaluated.  b. No reduction in the perceived quality of the project outcome ... project do not increase.  d. Any decrease in the scoped deliverable of the project is rejected

Last Answer : a. All variance to the project scope is evaluated.

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Fill in the blank. During the _________ of a project, the project manager focuses on  developing the project infrastructure needed to execute the project and developing  clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement