What do leaders do? 

A. Inspire, trust, and challenge the status quo. 

B. Dictate the team

C. Direct people and behavior.

D. Control people

1 Answer

Answer :

A. Inspire, trust, and challenge the status quo.

Related questions

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Determining the policies that are needed for the smooth execution of a project  relates to which of the following agenda items of alignment sessions? Select one: a. Developing a common ... role clarification on projects e. Agreeing on the means and methods for accomplishing the purpose

Last Answer : d. Developing role clarification on projects

Description : Leaders who inspire followers to transcend their own self-interests for the good of the organization, and are capable of having a profound and extraordinary effect on followers are _____ leaders. (a) Transactional ; (b) Transformational ; (c) Democratic ; (d) Autocratic

Last Answer :  (b) Transformational ;

Description : Is the East Coast getting battered to the quick every season of the year getting to be status quo?

Last Answer : answer:As one who lived in New England for a few decades, I don't see it as any worse there than it was back in the late-70s. Well, aside from those places that couldn't be rebuilt, like ... So regardless of which coast gets hit worse by nature, the West Coast will be the one that gets devastated.

Description : Suppose you won the lotto. Would you maintain the status quo?

Last Answer : answer:Seriously, I would start a charity helping young people pay off student loans. I would totally let them refinance through me, at absurdly easy terms. 1) I would feel like I was helping the community 2) I would be exposed to attractive people way too young for me as I settle into old age.

Description : Do you believe in a status quo in regards to gender roles?

Last Answer : answer:Such roles are ridiculous to me, and where I live and work we've certainly moved a great deal past that. I am not saying there is full gender equality, but things have certainly ... , they may just not know better from cultural restrictions. The culture itself may be sexist by definition.

Description : How can one be more content with the status quo when needs be?

Last Answer : It's about being comfortable with your choice. If you make the choice based on a careful consideration of all the factors, then you are more likely to be comfortable with it. If you keep second-guessing ... of yet. You have to figure out what that is so you can include it in your calculation.

Description : What will happen if I challange the status quo (relationships)

Last Answer : 1. How old are you? 2. Do your friends every ask why you don't date? 3. Why don't you date? Your role in society is not to be the guy who doesn't date. Who is that benefiting? What are ... Why does that worry you? I have never met a person who is completely comfortable with dating. Go for it. :)

Description : pricing strategy aimed at paying current or past due bills is 1. Survival pricing 2. Brand pricing 3. Status quo pricing 4. Due bill pricing 5. None of these

Last Answer : Survival pricing

Description : A firm establishes which of the following pricing objectives to maintain or increase its product's sales in relation to total industry sales? A)Cash flow B)Sales potential C)Product quality D)Market share E)Status quo

Last Answer : D)Market share

Description : Which pricing objective de -emphasises price and can lead to a climate of nonprice competition in an industry? A)Status quo B)Return on investment C)Market share D)Survival E)Cash flow

Last Answer : A)Status quo

Description : What type of pricing objective might an organisation set if it was already in a favourable financial position and desired nothing more? A)Return on investment B)Cash flow C)Profit D)Status quo E)Survival

Last Answer : D)Status quo

Description : Which characteristic was found by Raudsepp among creative managers? (a) They had few hobbies or interests outside work. (b) They focused intensely on immediate needs. (c) They were irritated by the status quo. (d) They had little energy to spare.

Last Answer : (c) They were irritated by the status quo.

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : A Communications Management Plan does the following:  A. Coordinates an effort to communicate in meetings effectively B. Lays out a plan on how to communicate with your Project ... and  efficiently. D. Coordinates the communication between project leaders and uninterested project  members

Last Answer : C. Lays out the approach and method for delivering information effectively and  efficiently.

Description : A planning phase for an engineering component generated 80 engineering drawings. The QA team randomly selected 8 drawings for inspection. This exercise can BEST be described as example of: A. Inspection B. Statistical Sampling C. Flowcharting D. Control Charting

Last Answer : B. Statistical Sampling

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : .A planning phase for an engineering component generated 80 engineering drawings. The QA  team randomly selected 8 drawings for inspection. This exercise can BEST be described as  example of: A. Inspection B. Statistical Sampling C. Flowcharting D. Control Charting

Last Answer : B. Statistical Sampling

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : Which of the following is a form of trust that is built on the examination of the  person’s motives and the conclusion that he or she is not hostile? Select one: a. Objective credibility b. Attribution of benevolence c. Non-manipulative trust d. Unequivocal liberality e. High cost of lying

Last Answer : b. Attribution of benevolence

Description : Which of the following statements is true regarding contracts? Select one: a. They are the filters through which project members screen information that is shared. b. They do not lend ... information-rich  environment will suffer. e. Contracts promote the growth of a trusting project culture.

Last Answer : b. They do not lend themselves to create an environment of trust.

Description : Which of the following is a personal characteristic that reflects the  truthfulness of an individual that can be checked against observable facts? Select one: a. Objective credibility b. Attribution ... c. Non-manipulative trust d. High cost of lying e. Acknowledgment of munificence

Last Answer : a. Objective credibility

Description : Which one of the following statements best describes the use of an issue log? a. A summary of all possible alternative resolutions of an issue. b. A summary of all the project issues, their ... for capturing all issues. d. A tool to ensure that the issue management process is adhered to.

Last Answer : b. A summary of all the project issues, their analysis and status.

Description : Which of the following is not an example of formal communication? a. Contract b. email c. Project status report d. Status meeting

Last Answer : b. email

Description : As a PMP, you will be required to comply with the PMP Code of Professional  Conduct. This code refers to all of the following except which one?  A. Reporting conflicts of interest ... C. Complying with the stakeholder requirements D. Complying with the rules and standards of foreign countries

Last Answer : C. Complying with the stakeholder requirements

Description : Which of the following is not an example of formal communication? a. Contract b. email c. Project status report d. Status meeting

Last Answer : b. email

Description : Which one of the following statements best describes the use of an issue log?  a. A summary of all possible alternative resolutions of an issue.  b. A summary of all the project issues, their ... for capturing all issues.  d. A tool to ensure that the issue management process is adhered to.

Last Answer : b. A summary of all the project issues, their analysis and status.

Description : What criticisms were made of business leaders and trust?

Last Answer : Need answer

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : The project charter describes the qualifications of the people who will work on a  project and the reporting structure of the project team.

Last Answer : Ans: False

Description : Sergei, the project manager, is worried about completing the project on time. To  increase the productivity of his 15-person team he should create subteams with no more  than 10 people on a sub team.

Last Answer : Ans: True

Description : Adding people to a project team in order to speed up total development time _____.  a. is a standard task in timeboxing  b. is a useful way to meet a tight deadline  c. may actually increase total development time  d. simplifies communication within the team  e. none of the above

Last Answer : c. may actually increase total development time

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers

Last Answer : (B) stakeholders

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.

Description : Which one of the following best describes project success criteria? a. Actively seeking some senior management support. b. Measures by which the success of the project is judged. c. Achievement of milestones. d. A motivated project team.

Last Answer : b. Measures by which the success of the project is judged.

Description : Which one of the following is a responsibility of the project steering group/board? a. To identify potential problems for the project team to solve. b. To provide strategic direction and guidance ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.

Last Answer : c. The project manager.

Description : A communication management plan identifies the relevant information that should be communicated to: a. the project team. b. the project stakeholders. c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : Which of the following is not project management goal? a) Keeping overall costs within budget b) Delivering the software to the customer at the agreed time c) Maintaining a happy and well-functioning development team

Last Answer : d) Avoiding customer complaints

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : This set of Software Engineering Multiple Choice Questions & Answers (MCQs) focuses on Project  Management . 1. Which of the following is not project management goal? a) Keeping overall ... agreed time c) Maintaining a happy and well-functioning development team d) Avoiding customer complaints

Last Answer : d) Avoiding customer complaints