A function point is a measure of program size based on the number and complexity of 

inputs, outputs, queries, files and program interfaces.

1 Answer

Answer :

Ans: True

Related questions

Description : A(n) ____________ is a measure of program size based on the number and  complexity of inputs, outputs, queries, files, and program interfaces.  a. function point  b. line of code  c. project plan  d. standard module  e. workplan

Last Answer : a. function point

Description : Consider a project with the following functional units : Number of user inputs = 50 Number of user outputs = 40 Number of user enquiries = 35 Number of user files = 06 Number of external interfaces = 04 ... average, the function points for the project will be (A) 135 (B) 722 (C) 675 (D) 672

Last Answer : (D) 672

Description : Function points are used to measure the estimated _____ of a project.  a. complexity  b. effort required  c. program size  d. time required

Last Answer : c. program size

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : ____ and ____ refer to the mechanism applied to the inputs to create the desired outputs.

Last Answer : Ans. Tools and techniques

Description : Which one of the following statements best defines procurement?  a. A technique to establish the best approach for obtaining the resources for the project.  b. A group of interrelated resources and ... product.  d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : When using a function point estimation worksheet, there are 14 factors that impact the complexity of a project. These factors include _____.  a. data communications, time tradeoffs, and ... programming language  d. reports printed and PCA  e. x-rays, extensibility, and operational conversion

Last Answer : b. end-user efficiency, data communications, and reusability

Description : A measure A measure of the success of an success of an operation in converting operation in converting inputs to inputs to outputs is outputs is a. Efficiency b. Effectiveness Effectiveness c. Quality d. Profitability

Last Answer : a. Efficiency

Description : The contract administration function includes: 1. funding management  2. managing relationships and interfaces  3. performance control  4. all of the above

Last Answer : 4. all of the above

Description : Political unrest, budget overruns, size and complexity of the project  Answer: B  (8)Decision trees are best used for : 1. Determining the interaction of the amount at stake and the expected ... and the associated events  4. A flow chart which determines the standard deviation of the risk event

Last Answer : 3. An illustration of how to see the interactions between decisions and the associated events

Description : )Which of the following fit the category of external risks? 1. Project delays, budget under-runs, movement of city utilities  2. Regulatory, currency changes, taxation  3. Natural disasters, ... , design, social impact  5. Political unrest, budget overruns, size and complexity of the project

Last Answer : 2. Regulatory, currency changes, taxation

Description : Using the shortcut method to determine the complexity of a systems project, a very  complex system having 300 unadjusted function points would have 405 adjust function  points.

Last Answer : Ans: True

Description : . A normal system with 400 unadjusted function points would have _____ adjusted  function points when the shortcut method is use to determine the complexity of the  project.

Last Answer : c. 400

Description : Kathryn has little experience estimating the time it will take to complete a systems  project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points  c. industry standards  d. Microsoft Project  e. more complex approach

Last Answer : c. industry standards

Description : Where does the Bayes rule can be used? a) Solving queries b) Increasing complexity c) Decreasing complexity d) Answering probabilistic query

Last Answer : d) Answering probabilistic query

Description : Production Function relates to: (1) costs to outputs (2) costs to inputs (3) inputs to outputs (4) wage level to profits

Last Answer : (3) inputs to outputs Explanation: In microeconomics and macroeconomics, a production function is a function that specifies the out-put of a firm, an industry, or an entire economy for all ... in the use of factor inputs in production and the resulting distribution of income to those factors.

Description : What is the name of the function in the following statement “A perceptron adds up all the weighted inputs it receives, and if it exceeds a certain value, it outputs a 1, otherwise it just outputs a 0”? a) Step function b) Heaviside function c) Logistic function d) Perceptron function

Last Answer : b) Heaviside function

Description : Science bases its estimation of the size of a product on a) Files (Fi), Flows (Fl) and Processes (Pr) b) Lines of Code (kLOC) c) Function Points (FP) d) operands and operators e) Feature Points (FeP).

Last Answer : d) operands and operators

Description : Which one of the following best describes users? a. Providers of both strategic and tactical direction to the project. b. Those intended to receive benefits or operate outputs. c. Facilitators of an appropriate issue resolution procedure. d. Those providing full-time commitment to the project.

Last Answer : b. Those intended to receive benefits or operate outputs.

Description : The outputs of the Close Project process include all of the following except for which one?  A. Administrative closure procedure B. Formal acceptance C. Lessons learned D. Closed contracts

Last Answer : C. Lessons learned

Description : Which one of the following best describes users?  a. Providers of both strategic and tactical direction to the project.  b. Those intended to receive benefits or operate outputs.  c. ... of an appropriate issue resolution procedure.  d. Those providing full-time commitment to the project.

Last Answer : b. Those intended to receive benefits or operate outputs.

Description : Quality control in the final analysis is : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements  2. a production system  3. an inspection system  4. fitness for purpose

Last Answer : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : What is the most critical aspect in developing a project plan that meets project  specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project

Last Answer : e. Developing a project execution plan that matches the complexity level of the project

Description : Fill in the blank. There is _______ correlation between project complexity  and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general

Last Answer : b. a positive

Description : Algorithmic cost estimation in different organisations may be different for the same application development, because a) Different organisations consider complexity factors differently b) Different organisations may use ... measurement of productivity may vary e) All of the above may be true.

Last Answer : e) All of the above may be true.

Description : Michelle has decided to use a shortcut to determine the complexity of the project she  is currently managing. She has assigned the adjusted project complexity (PCA) a value  of .65. She has determined that ... _____.  a. bi-lateral  b. complex c. microconvergent  d. normal  e. very simple

Last Answer : e. very simple

Description : Which is not a size metric? (A) LOC (B) Function count (C) Program length (D) Cyclomatic complexity

Last Answer : (D) Cyclomatic complexity

Description : How many inputs and how many outputs of NOT gate ?

Last Answer : NOT Gate has one input and one output.

Description : What are the inputs and outputs of a toaster?

Last Answer : Need answer

Description : What is a mapping between a set of inputs and a set of outputs?

Last Answer : It is simply a mapping. It could be a function but there areseveral conditions that need to be met before the mapping canbecome a function and there is no basis for assuming that thoseconditions are met.

Description : Transformation of physical inputs into physical outputs is termed as

Last Answer : Ans. Production

Description : Gross National Product means - (1) gross value of finished goods (2) money values of the total national production for any given period (3) gross value of raw materials and semifinished products (4) money value of inputs and outputs

Last Answer : (2) money values of the total national production for any given period Explanation: Gross national product (GNP) is the market/monetary value of all products and services produced in one year by labour and property supplied by the residents of a country.

Description : One feature of the operational amplifier is that it can have ____________. A. up to ten outputs B. binary coded decimal inputs C. several hundred amps at the output D. inverting and non-inverting inputs

Last Answer : Answer: D

Description : A perceptron adds up all the weighted inputs it receives, and if it exceeds a certain value, it outputs a 1, otherwise it just outputs a 0. a) True b) False c) Sometimes – it can also output intermediate values as well d) Can’t say

Last Answer : a) True

Description : . In an Unsupervised learning ____________ a) Specific output values are given b) Specific output values are not given c) No specific Inputs are given d) Both inputs and outputs are given

Last Answer : b) Specific output values are not given

Description : Which were built in such a way that humans had to supply the inputs and interpret the outputs? a) Agents b) AI system c) Sensor d) Actuators

Last Answer : b) AI system

Description : Value added is: a) the cost saving through production and marketing efforts within the firm. b) the value that a firm adds through the development of dynamic capabilities. c) the value that a ... through outsourcing. d) the difference between the cost of inputs and the market value of outputs

Last Answer : the difference between the cost of inputs and the market value of outputs

Description : Various Organizational routines & processes that determines how efficiently and effectively the Organization transforms it’s inputs into outputs is called: A. Strength B. Core Competencies C. Capabilities D. Customer Value

Last Answer : Core Competencies

Description : What is a firm? a. A president, some vice presidents, and some employees b. Any organization that wants to make a profit. c. Any accumulation of productive assets. d. Any organization that turns inputs into outputs

Last Answer : d. Any organization that turns inputs into outputs

Description : How many inputs and outputs are possible with a differential amplifier?

Last Answer : Two inputs, two outputs.

Description : In an Unsupervised learning a) Specific output values are given b) Specific output values are not given c) No specific Inputs are given d) Both inputs and outputs are given e) Neither inputs nor outputs are given

Last Answer : b) Specific output values are not given

Description : Plant P Plant Producti roductivity is: vity is: a)Productivity = Inputs/Outputs b)Productivity = lnputs*Outputs c)Productivity = Outputs//lnputs d) None of the above

Last Answer : c)Productivity = Outputs//lnputs

Description : …………………. is a group of interested components working together towards a common goal by accepting inputs and producing outputs in an organized transformation process. A) System B) Network C) Team D) System Unit

Last Answer : A) System

Description : A full adder logic circuit will have (A) Two inputs and one output. (B) Three inputs and three outputs. (C) Two inputs and two outputs. (D) Three inputs and two outputs.

Last Answer : Ans: D A full adder circuit will add two bits and it will also accounts the carry input generated in the previous stage. Thus three inputs and two outputs (Sum and Carry) are there.

Description : Gross National Product means (1) gross value of finished goods (2) money values of the total national production for any given period (3) gross value of raw materials and semi-finished products (4) money value of inputs and outputs

Last Answer : money values of the total national production for any given period

Description : List typical inputs and outputs for PLC (four input and any four output).

Last Answer : Typical PLC inputs  Push Button  Selector Switch  Proximity switch  FOOT switch, level switch  Analog input  Typical PLC outputs  Contactor Coil, solenoid, relay  Indicating Lamp  Buzzer  Alaram annunciator

Description : Which of the following processes serve as inputs to each other?  A. Executing, and Monitoring and Controlling B. Executing and Closing C. Planning, and Monitoring and Controlling D. Executing and Initiation

Last Answer : A. Executing, and Monitoring and Controlling

Description : Which of the following serves as metrics for project size estimation? A. Lines of codes B. function point C. Number of persons D. Only A & B

Last Answer : D. Only A & B