Description : Upper CASE tools are used to create diagrams and generate code for database tables system functionality during the design phase.
Last Answer : Ans: False
Description : Integrated CASE tools are used to support tasks that happen throughout the SDLC.
Last Answer : Ans: True
Description : Benefits to using computer-aided software engineering (CASE) include faster task completion and alteration, centralized development information, and illustration of information through diagrams.
Description : Which model is used to compute the effort required to integrate reusable components or program code that is automatically generated by design or program translation tools? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model
Last Answer : c) A reuse model
Description : According to the Project Management Institute (PMI), project management is defined as the application of knowledge, _____, _____, and techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories
Last Answer : d. skills, tools
Description : Monte Carlo analysis can help predict the impact of risks on project deliverables. This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis
Last Answer : B. Quantitative Risk Analysis
Description : Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system? a) System building b) Release management c) Change management d) Version management
Last Answer : a) System building
Description : Project Integration Management ensures that various elements of a project are properly integrated and coordinated for smooth flow of information and resources. (True/False)
Last Answer : Ans. True
Description : An example of the risk involved in development is a) Key personnel may resign before the product is complete b) The manufacturer of critical components (e.g. the hardware associated with a ... a fully functional lower-cost equivalent package e) All of these are risks involved in development.
Last Answer : e) All of these are risks involved in development.
Description : For the best model suitable for the project, in which of the phase the developers decide a roadmap for project plan? a. Design b. System Analysis c. Coding d. Testing
Last Answer : b. System Analysis
Description : Which of the following items should not be included in the project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development organisation, project responsibilities, managerial objectives and priorities e) None of the above.
Last Answer : c) The life cycle model to be used
Description : Which of the following states that work expands to fill the time available. a) CASE tools b) Pricing to win c) Parkinson’s Law d) Expert judgement
Last Answer : c) Parkinson’s Law
Description : Which of the following activity is undertaken immediately after feasibility study and before the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling
Last Answer : A. Project Planning
Description : Complete the following statement. As the project progresses into the execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have been avoided.
Last Answer : a. risks need to be checked off on activities that have been performed.
Description : Once the project is approved and moves into the planning stage, what happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis
Last Answer : d. Risks are identified with each major group of activities.
Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis
Last Answer : e) Risk analysis
Description : Using typical industry standards for estimating project time schedules, the estimated analysis phase would be 10 person-months for a systems project where the planning phase was completed in 7.5 person-months.
Description : Using typical industry standards for estimating project time schedules, the estimated analysis phase would be 25 person-months for a systems project where the planning phase was completed in 30 person-months.
Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the project life cycle. b. The business case is ... is owned by the project manager and is created during the definition phase of the project life cycle.
Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the project life cycle.
Description : The business case and the justification for the project is determined during the _____ phase. (A) initiation (B) planning (C) execution (D) closure
Last Answer : (A) initiation
Description : Which phase of the RUP is used to establish a business case for the system? a) Transition b) Elaboration c) Construction d) Inception
Last Answer : d) Inception
Description : Which of the following statement(s) is/are FALSE in the context of Relational DBMS ? I. Views in a database system are important because they help with access control by allowing users to see only a particular subset of the data ... (B) III and IV only (C) I, II and III only (D) II, III and IV only
Last Answer : (D) II, III and IV only
Description : Evaluating testability of the requirements and system are a part of which phase:- a) Test Analysis and Design b) Test Planning and control c) Test Implementation and execution d) Evaluating ... text box which accepts alphabets in lower or upper case. Identify the invalid Equivalence class value.
Last Answer : a) Test Analysis and Design
Description : What is the most accurate method of obtaining project information that can reduce the amount of risk? 1. Observations on the current project 2. Determining the risk by using brainstorming ... from previous projects that were similar in nature 4. Sensitivity analysis 5. Delphi technique.
Last Answer : 3. The use of historical data from previous projects that were similar in nature
Description : What combines procedures and tools to manage different versions of configuration objects that are created during the process? a) Change control b) Version control c) SCIs d) None of the mentioned
Last Answer : b) Version control
Description : Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer store. Which type of contract will get signed in this case? A. Purchase Order B. Cost plus Fee C. Fixed cost D. Time and Material
Last Answer : A. Purchase Order
Description : .Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer store. Which type of contract will get signed in this case? A. Purchase Order B. Cost plus Fee C. Fixed cost D. Time and Material
Description : What Are The Tools Needed For A Project Management System?
Last Answer : A work definition policy and format, a scheduling procedure, a resource budgeting methodology and format, a real time data collection/reporting system, a material control and accountability subsystem, a ... control subsystem, and a monthly formal status review format to be used by senior management.
Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis
Last Answer : c. Perform Qualitative risk analysis
Description : All of the following are true regarding the Qualitative Risk Analysis process except which one? A. Probability and impact and expert interview are used to help correct biases that occur in the data ... of this process used to determine which risks need near-term response plans.
Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and impact that usually takes a good deal of time to perform.
Description : A kiosk a) is data organised and presented in a manner that has additional value beyond t he value of the data itself b) combines microscopic electronic components on a single integrated circuit that ... and service d) describes a computer's type, processor, and operating system e) None of these
Last Answer : c) is a computer station that provides the public with specific and useful information and service
Description : Which of the following statements is true regarding contracts? Select one: a. They are the filters through which project members screen information that is shared. b. They do not lend ... information-rich environment will suffer. e. Contracts promote the growth of a trusting project culture.
Last Answer : b. They do not lend themselves to create an environment of trust.
Description : The project scope statement furnishes the basis for: 1. Provides links to the clients functional management groups 2. Allowing the project to move to the next phase . A way to provide updated information to the accounting department
Last Answer : 1. Provides links to the clients functional management groups
Description : Nature of interrelationships between components in a system defines the A. Function of system B. Structure of system C. Environment of system D. Platform of system
Last Answer : B. Structure of system
Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.
Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.
Description : Project management includes the tools, techniques, and essential to deal with the growth of products a. Knowledge b. Skill c. Attitude d. Confidence
Last Answer : a. Knowledge
Description : The most significant challenge to project managers is _____. a. lack of project management training b. no one really understands how to manage a complex systems development project ... tools that can assist in controlling project progress d. unrealistic schedule demands by project sponsors
Last Answer : d. unrealistic schedule demands by project sponsors
Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of ... endeavour undertaken to achieve a desired outcome. d. A project is a method of planning work.
Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.
Description : What Are The Different Project Management Tools?
Last Answer : The different Project Management tools are MS Project, Templates, eBooks, flowcharts Compliant with PMBOK 4th Edition, EPOs (Electronic Project Offices) etc.
Description : Which of the following is a quality management system that gives titles to specialists and requires a cost-benefit analysis? Select one: a. Lean accounting b. Business process re-engineering c. Kaizen d. Six Sigma e. Total Quality Management
Last Answer : d. Six Sigma
Description : The process of assigning values for the time and effort needed to perform a system project is called _____. a. analysis b. estimation c. identifying d. planning
Last Answer : b. estimation
Description : Quality control in the final analysis is : 1. using the technical procedures of monitoring project results to decide if the outputs meet the requirements 2. a production system 3. an inspection system 4. fitness for purpose
Last Answer : 1. using the technical procedures of monitoring project results to decide if the outputs meet the requirements
Description : One of the reasons a project life cycle is split into phases is to: a. facilitate formal go/no-go decision making during the project. b. balance the costs of work in each phase of ... the major deployments of resources throughout the project. d. chunk work into time periods of similar durations.
Last Answer : a. facilitate formal go/no-go decision making during the project.
Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.
Last Answer : a. The cost associated at the beginning of the project is highest.
Description : Fill in the blanks. It is during the ______________ phase that the decision should be made regarding whether the project should continue. During this phase, ____________ must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk
Last Answer : e. initiation, risk
Description : One of the reasons a project life cycle is split into phases is to: a. facilitate formal go/no-go decision making during the project. b. balance the costs of work in each phase ... the major deployments of resources throughout the project. d. chunk work into time periods of similar durations.
Description : Project Scope: 1. is of concern only at the start of the project 2. is mainly a problem to be handled by the change control procedures during the project execution phase. 3. Should ... . is usually not a problem after the contract or other document authorizing the project has been approved.
Last Answer : 3. Should be managed and controlled from the project concept through close-out