Complete the following statement. In a weak matrix environment, the
project manager, Eric, has to constantly make an effort to influence his
project team and stakeholders to ensure project success. This is because:
Select one:
a. Eric has a lot of authority.
b. Eric has no or little authority.
c. Eric is controlled by his functional managers.
d. there are no functional managers.
e. Eric has flexibility on authority.