CV = $70,000; AC = 90,000; Budget = $200,000. What percent of the
project is complete?
Select one: a. 80% b. 53% c. 45% d. 35% e. 75%
Answer – a. 80%
39. As a project manager, John was finally relieved because a major project
led by him was just announced a success. According to the PMBOK, which
of the following has likely happened in order to consider John’s project a
success?
Select one:
a. John’s project has met all of the stakeholders’ expectations.
b. The phase completion of John’s project has been approved.
c. John’s client has paid off the project.
d. John’s boss is happy.
e. John and his team are promoted and get salary increases.
project is complete?
Select one: a. 80% b. 53% c. 45% d. 35% e. 75%
Answer – a. 80%
39. As a project manager, John was finally relieved because a major project
led by him was just announced a success. According to the PMBOK, which
of the following has likely happened in order to consider John’s project a
success?
Select one:
a. John’s project has met all of the stakeholders’ expectations.
b. The phase completion of John’s project has been approved.
c. John’s client has paid off the project.
d. John’s boss is happy.
e. John and his team are promoted and get salary increases.