The PM distributed a document to the stakeholders, which described the software to be
developed, the functionality, the users it would serve and the installation timeline. The document
was an example of:
1. Product scope
2. Project scope
3. A combination of project and product scope
4. It was not complete enough to be either a product or a project scope document
developed, the functionality, the users it would serve and the installation timeline. The document
was an example of:
1. Product scope
2. Project scope
3. A combination of project and product scope
4. It was not complete enough to be either a product or a project scope document