Which one of the following statements best defines the purpose of a Product Breakdown

Structure (PBS)?

a. To define the hierarchy of deliverables that are required to be produced on the project.

b. To define how the products are produced by identifying derivations and dependencies.

c. To establish the extent of work required prior to project commissioning and the handover.

d. To identify the health and safety strategies and procedures to be used on the project

1 Answer

Answer :

a. To define the hierarchy of deliverables that are required to be produced on the project.

Related questions

Description : Which one of the following statements best defines the purpose of a Product Breakdown  Structure(PBS)?  a. To define the hierarchy of deliverables that are required to be produced on the project.  b. ... .  d. To identify the health and safety strategies and procedures to be used on the project.

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : When a project has completed the handover and closure phase: a. the project deliverables are ready for commissioning. b. the project deliverables are ready for handing over to the users. c. the project ... must be disposed of. d. the capability is now in place for the benefits to be realized.

Last Answer : d. the capability is now in place for the benefits to be realized.

Description : When a project has completed the handover and closure phase:  a. the project deliverables are ready for commissioning.  b. the project deliverables are ready for handing over to the users.  c. the ... must be disposed of.  d. the capability is now in place for the benefits to be realised.

Last Answer : d. the capability is now in place for the benefits to be realised.

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which one of the following statements best defines procurement?  a. A technique to establish the best approach for obtaining the resources for the project.  b. A group of interrelated resources and ... product.  d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : Which one of the following best defines a benefit? a. A positive result of stakeholder management. b. The successful management of a project. c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : Which one of the following best defines a benefit?  a. A positive result of stakeholder management.  b. The successful management of a project.  c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : WBS is produced by identifying the key elements, breaking each element down into  component parts and continuing to breakdown until manageable work packages have been identified. (True/False)

Last Answer : Ans. True

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : Auditors perform analytical procedures in the planning stage of an audit for the purpose of: a. Determining which of the financial statement assertions are the most important for the client's ... matters to cover in an engagement. d. Identifying unusual conditions that deserve more auditing effort

Last Answer : Identifying unusual conditions that deserve more auditing effort

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : An Organisational Breakdown Structure (OBS) is used to identify:  a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : Which one of the following statements best defines teamwork? a. People working collaboratively towards a common goal. b. Developing skills that will enhance project performance. c. Gathering the ... together to work on a project. d. Establishing vision and direction towards a common purpose.

Last Answer : a. People working collaboratively towards a common goal.

Description : Which one of the following statements best defines teamwork?  a. People working collaboratively towards a common goal .b. Developing skills that will enhance project performance.  c. Gathering the ... together to work on a project.  d. Establishing vision and direction towards a common purpose

Last Answer : a. People working collaboratively towards a common goal.

Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.

Last Answer : b. Organizational Breakdown Structure.

Description : Which structure shows the reporting relationships and communications channels for a  project?  a. Work Breakdown Structure.  b. Organisational Breakdown Structure.  c. Product Breakdown Structure.  d. Responsibility assignment structure.

Last Answer : b. Organisational Breakdown Structure.

Description : Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name  of this identifier? 1. Product ID number  2. Code of accounts  3. Quality inspection identifier  4. Project activity code

Last Answer : 2. Code of accounts

Description : . In project management, the term quality is best defined as: a. inspection, testing and measurement. b. reviews and audits. c. fitness for purpose of deliverables. d. professionally-bound project reports.

Last Answer : c. fitness for purpose of deliverables.

Description : In project management, the term quality is best defined as:  a. inspection, testing and measurement.  b. reviews and audits.  c. fitness for purpose of deliverables.  d. professionally-bound project reports.

Last Answer : c. fitness for purpose of deliverables.

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : The following procedures relate to Skills and Competence, except a. Identify criteria which will be considered in evaluating individual performance and expected proficiency. b. Provide procedures for ... to fill the firm's needs for personnel with expertise in specialized and industries.

Last Answer : Provide procedures for maintaining the firm's standards of quality for the work performed.

Description : The phases of a project life cycle are: a. starting, planning, control and closing. b. concept, definition, development, handover and closure. c. initiation, definition, planning, monitoring and operations. d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : The phases of a project life cycle are:  a. starting, planning, control and closing.  b. concept, definition, development, handover and closure.  c. initiation, definition, planning, monitoring and operations.  d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : The entire process of a project may be considered to be made upon a number of sub- processes placed in different stages called the Work Breakdown Structure. (True/False)

Last Answer : Ans. True

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : The evolutionary Work Breakdown Structure makes it easy to compare the current  project with past project

Last Answer : Ans: True

Description : The traditional Work Breakdown Structure makes it easy to compare the current  project with past projects.

Last Answer : Ans: False

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract

Description : The work plan records and keeps track of all of the tasks that need to be accomplished  over the life of the project, listing each task, along with important information about it,  such as when it needs to be completed, the person assigned to do the work, and any  deliverables that will result.

Last Answer : Ans: True

Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan  b. creating the work plan, staffing the project, and controlling ... the deliverables  e. setting the start date, estimating the time, and reading the actual time

Last Answer : b. creating the work plan, staffing the project, and controlling and directing the  project

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.