Which one of the following is captured in the Work Breakdown Structure (WBS)?
a. The life cycle phases.
b. The logical order of tasks.
c. The scope of the project.
d. Project costs.
a. The life cycle phases.
b. The logical order of tasks.
c. The scope of the project.
d. Project costs.