A Cost Breakdown Structure (CBS) shows costs assigned to:

a. individual work packages using the Work Breakdown Structure (WBS).

b. individual resources using the Work Breakdown Structure (WBS).

c. individual resources using the Responsibility Assignment Matrix (RAM).

d. individual deliverables using the Responsibility Assignment Matrix (RAM)

1 Answer

Answer :

a. individual work packages using the Work Breakdown Structure (WBS).

Related questions

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following types of Organizational Charts can be BEST used to track project costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : Which of the following types of Organizational Charts can be BEST used to track project  costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.

Last Answer : b. Organizational Breakdown Structure.

Description : Which structure shows the reporting relationships and communications channels for a  project?  a. Work Breakdown Structure.  b. Organisational Breakdown Structure.  c. Product Breakdown Structure.  d. Responsibility assignment structure.

Last Answer : b. Organisational Breakdown Structure.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : WBS is produced by identifying the key elements, breaking each element down into  component parts and continuing to breakdown until manageable work packages have been identified. (True/False)

Last Answer : Ans. True

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : What Is A Work Breakdown Structure (wbs)?

Last Answer : The work breakdown structure defines the total project. A work breakdown structure is a product oriented, family tree composed of hardware elements, software elements, and service elements. The work ... the end product. The work breakdown structure is not an organization chart of company personnel.

Description : Which one of the following statements best defines the purpose of a Product Breakdown Structure (PBS)? a. To define the hierarchy of deliverables that are required to be produced on the project. ... . d. To identify the health and safety strategies and procedures to be used on the project

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : Which one of the following statements best defines the purpose of a Product Breakdown  Structure(PBS)?  a. To define the hierarchy of deliverables that are required to be produced on the project.  b. ... .  d. To identify the health and safety strategies and procedures to be used on the project.

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : An Organisational Breakdown Structure (OBS) is used to identify:  a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : The document that identifies what information needs to be shared, to whom, why, when and  how is called the: a. communication management plan.  b. stakeholder mapping grid.  c. document distribution schedule.  d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description : The justification for the investment to be made in a project is documented in the: a. Cost Breakdown Structure. b. procurement strategy. c. business case. d. Project Management Plan.

Last Answer : c. business case.

Description : The justification for the investment to be made in a project is documented in the:  a. Cost Breakdown Structure.  b. procurement strategy.  c. business case.  d. Project Management Plan

Last Answer : c. business case.

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______  level of the WBS 1. Highest  2. Lowest  3. Major work effort  4. Third

Last Answer : 2. Lowest

Description : When developing a project's scope statement, which of the following should not be  included? 1. Project justification.  2. Cost/benefit analysis  3. Project deliverables  4. Measurable objectives

Last Answer : 1. Project justification.

Description : Following is(are) the responsibility(ies) of the project manager. (A) Budgeting and cost control (B) Allocating resources (C) Tracking project expenditure

Last Answer : (C) Tracking project expenditure

Description : Following is(are) the responsibility(ies) of the project manager. (A)Budgeting and cost control (B)Allocating resources (C)Tracking project expenditure (D)All of the above

Last Answer : (D)All of the above

Description : The strategy used to correct resource over-allocations by balancing demand for resources and  the available supply is known as (A) resource assignment (B) resource leveling (C) resource splitting (D) resource scheduling

Last Answer : (B) resource leveling

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : The entire process of a project may be considered to be made upon a number of sub- processes placed in different stages called the Work Breakdown Structure. (True/False)

Last Answer : Ans. True

Description : The evolutionary Work Breakdown Structure makes it easy to compare the current  project with past project

Last Answer : Ans: True

Description : The traditional Work Breakdown Structure makes it easy to compare the current  project with past projects.

Last Answer : Ans: False

Description : The evolutionary Work Breakdown Structure approach is very useful when the  requirements of the system are not well understood.

Last Answer : Ans: True

Description : The traditional Work Breakdown Structure approach is very useful when the  requirements of the system are not well understood.

Last Answer : Ans: False

Description : Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name  of this identifier? 1. Product ID number  2. Code of accounts  3. Quality inspection identifier  4. Project activity code

Last Answer : 2. Code of accounts

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract