During a new project planning process to sequence activities, the project
manager, Nate, decides to use the precedence diagraming method to show the
identified activity dependencies. Which of the following logical relationships is
Nate’s least favorite choice?
Select one:
a. Finish-to-start
b. Start-to-finish
c. Finish-to-finish
d. Start-to-start
e. All of these answers