Which of the following should be the FIRST step in removing a generator from parallel operation? A. Trip the generator off the switchboard. B. Turn off all electrical equipment. C. Remove the load from the 'off going' generator. D. Increase the cycles of the generator staying on the line.

1 Answer

Answer :

Answer: C

Related questions

Description : Undervoltage trips are frequently installed on switchboard circuit breakers to trip ____________. A. out generators in the event of severe arcing or sparking B. out generators when there is reversal of power ... , but continues to run D. out generators when there is low voltage in the main circuit

Last Answer : Answer: D

Description : Which of the following statements is true concerning the operation of two alternators in parallel? A. The cycles per second of each alternator are the same. B. Both alternator governors must be set ... be the same on each alternator. D. The load must always be divided equally between alternators.

Last Answer : Answer: A

Description : A ground is indicated by the ground-detecting system on the main electrical switchboard. The FIRST step in locating the actual ground is to _____________. A. close all circuit breakers in ... ground detection system indicates normal C. change over generators D. check each circuit with a megohmmeter

Last Answer : Answer: B

Description : The electrical energy necessary to power a sound-powered telephone's small vibrating bell is obtained from _________. A. the emergency batteries for the general alarm B. each station's hand-cranked generator C. the emergency switchboard D. normal 115 volt DC supplies

Last Answer : Answer: B

Description : Coast Guard Regulations (46 CFR) require that each alternating current generator arranged for parallel operation shall be provided with _____________. A. more than one means of excitation B. individual circuit fuses C. a high back-pressure trip D. a reverse-power trip

Last Answer : Answer: D

Description : Before any work on electrical or electronic equipment is performed, which of the following precautions should be carried out? A. De-energize the applicable switchboard bus. B. Bypass the interlocks. C. ... supply circuit breaker in the open position. D. Station a man at the circuit supply switch.

Last Answer : Answer: C

Description : Automatic voltage regulators provided on switchboards function to _____________. A. regulate the AC load on the generator B. protect the switchboard from high voltage C. govern prime mover speed to control voltage D. vary the field excitation to the generators

Last Answer : Answer: D

Description : A loss of field excitation to an AC generator while operating in parallel will cause it to ____________. A. absorb more and more load due to decreased armature reaction B. lose its load due to ... polarity D. lose its load, begin to motorize, trip out on reverse power relay, and possibly overspeed

Last Answer : Answer: D

Description : A vessel is equipped with two ship's service generators. Generator #1 is rated at 900 kw and generator #2 is rated at 600 kw. During parallel operation, with a hotel load of 1,000 kw, what should be the kw load on generator #2? A. 100 kw B. 400 kw C. 500 kw D. 600 kw

Last Answer : Answer: B

Description : The purpose of a main switchboard circuit breaker's reverse-power trip is to _____________. A. prevent main circuit overload B. protect the circuit breaker blowout coil C. prevent alternator motorization D. prevent low voltage tripout

Last Answer : Answer: C

Description : An AC generator produces 60 Hz at 1800 RPM. If the generator speed is increased to 1830 RPM, the cycles will _____________. A. remain at 60 Hz B. increase to 61 Hz C. decrease to 59 Hz D. increase to 63 Hz

Last Answer : Answer: B

Description : To remove an alternator operating in parallel with another unit from the main electrical bus, you must FIRST _________. A. adjust the power factor on both units B. set the desired voltage on ... C. open the circuit breaker on the outgoing alternator D. remove the load from the outgoing alternator

Last Answer : Answer: D

Description : When paralleling two AC generators, the frequency (cycles) of the incoming generator, just prior to closing the circuit breaker, should be _____________. A. slightly less than the frequency of the generator on ... C. slightly more than the frequency of the generator on the line D. all of the above

Last Answer : Answer: C

Description : Which of the following represents the accepted method of cleaning dust and foreign particles from electrical equipment while limiting damage to electric components? A. Carefully wiping off the components ... the components. D. Using carbon tetrachloride as a cleaning solvent to clean the components.

Last Answer : Answer: C

Description : A diesel driven emergency generator is prevented from being paralleled with the ship's service generators by __________. A. an electrical interlock system B. an automatic paralleling trip switch C. the synchronizing oscilloscope D. the reverse current relay

Last Answer : Answer: A

Description : The source of emergency lighting and power at loss of normal ship's power on a cargo vessel should be obtained from the ______________. A. emergency generator supply to the emergency ... switchboard C. battery supply to the main switchboard D. turbogenerator supply to the emergency switchboard

Last Answer : Answer: A

Description : In the illustration, the component labeled 'EXC' is _______. EL-0003 A. a separate class II regulated DC generator for critical direct current loads B. a generator feeding the FLD ... to drive the governor for turbogenerator speed. D. the electronic driver for the switchboard metering circuits

Last Answer : Answer: B

Description : Which of the listed sections of an emergency switchboard is used to supply power for alarm signals under emergency conditions? A. The generator and bus transfer section B. The 450 volt, 60 cycle, 3 phase bus C. The 120 volt, 3 phase, 60 cycle bus D. The 24 volt DC bus

Last Answer : Answer: D

Description : Attempting to parallel an AC generator which is out of phase with the bus will result in which of the following problems? A. The breaker should trip. B. The KVA will decrease. C. The synchronizing lamps will burn out. D. The power factor will be unitized.

Last Answer : Answer: A

Description : Diesel generators #1 and #2 are operating in parallel at near full load capacity. Diesel generator #1 suddenly trips out mechanically due to low lube oil pressure. The reverse power relay functions ... all nonvital circuits. D. Secure alarms, reset reverse power relay, and restart #1 engine.

Last Answer : Answer: C

Description : In accordance with Coast Guard Regulations (46 CFR), a steering gear feeder circuit from the emergency switchboard or alternate power supply must have the capacity for continuous operation of the rudder 15° side to side in not more than 60 seconds for a A. 1/4 hour B. 1/2 hour C. 1 hour D. 2 hours

Last Answer : Answer: B

Description : A current-carrying conductor making electrical contact with a wiring conduit will be indicated by a _____________. A. high switchboard wattmeter reading B. totally dark switchboard ground detecting light C. low switchboard wattmeter reading D. all of the above

Last Answer : Answer: B

Description : A current carrying conductor making an electrical contact with a wiring metal conduit is indicated by a _____________. A. low switchboard wattmeter reading B. reading of 1.0 on the power factor meter C. high switchboard voltmeter reading D. totally darkened switchboard ground-detecting light

Last Answer : Answer: D

Description : A ground in an electrical circuit outside the engine room _____________. A. cannot be detected under normal conditions B. is of no consequence to engineering personnel C. is indicated at the branch circuit breaker panel D. is indicated by the ground detecting lamps on the main switchboard

Last Answer : Answer: D

Description : A switchboard, for a AC electrical distribution system, will be provided with which of the following components? A. Frequency meter. B. Ammeter C. Voltmeter D. All of the above

Last Answer : Answer: D

Description : A switchboard for an AC electrical system requires the use of which of the following devices? A. Frequency meter. B. Ohmmeter. C. Induction voltage regulator. D. Current transformer governor.

Last Answer : Answer: A

Description : The part of the shipboard electrical system used to control the distribution of power to the branch circuits, is the _____________. A. bridge control panel B. disconnect links C. governor relay box D. main switchboard

Last Answer : Answer: D

Description : The electrical energy necessary to transmit a person's voice over a sound-powered telephone circuit is obtained from _____________. A. dry cell batteries B. the ship's service switchboard C. the emergency switchboard D. the speaker's voice

Last Answer : Answer: D

Description : Normally, the FIRST step in troubleshooting a transistor circuit card is to _____________. A. carefully remove the transistors from the card B. give the circuit an initial test with a signal generator C. test for continuity with a low voltage DC supply D. visually inspect the card

Last Answer : Answer: D

Description : When troubleshooting electronic equipment, the FIRST step to be taken before testing the circuit voltage is to _________. A. set the meter to the lowest range B. check the voltage supply from the power source C. remove the suspected component D. check the current flow through the circuit

Last Answer : Answer: B

Description : Which of the following statements is correct concerning the motor performance curves and data table shown in the illustration? EL-0006 A. The motor RPM at full load is 1737 RPM. B. The motor draws 12.62 kw ... If the motor was developing 10 HP its power factor would be 0.92. D. All of the above.

Last Answer : Answer: D

Description : If the energy input is significantly reduced to the prime mover of one shipboard alternator operating in parallel with others, that alternator will _____________. A. continue to operate at no load B. lose ... overspeed C. begin to motorize and then trip out D. slow down and operate at reduced load

Last Answer : Answer: C

Description : You are attempting to parallel two AC generators and the synchroscope pointer stops at a position other than 0°. If you close the circuit breaker at this moment _____________. A. the incoming ... hazardous condition will be created by the incoming machine being at a higher frequency than the bus

Last Answer : Answer: C

Description : In the illustration, the contacts between terminals 26 and 27 should be closed when _________. EL-0046 A. using one generator in isochronous mode only B. using two or more generators in ... through varying loads in parallel or single operation D. the circuit breaker is closed for that generator

Last Answer : Answer: C

Description : In replacing a defective transformer with a new one, which of the following actions must be carried out to insure proper operation of the equipment it serves? A. The secondary leads must be grounded ... magnetize it. D. The iron core must be grounded for 10 minutes to remove any residual magnetism.

Last Answer : Answer: B

Description : When shipboard electrical distribution circuits are connected in parallel, additional parallel circuits will cause the total circuit resistance to _____________. A. increase, causing a drop in the line current B ... an increase in the line voltage D. decrease, causing an increase in the line current

Last Answer : Answer: D

Description : A generator has been exposed to water and is being checked for its safe operation. Therefore, it is necessary to _______________. A. check for shorted coils with a growler B. take moisture readings with a ... a megger D. ground the commutator, or slip rings and run it at half load for 12 hours

Last Answer : Answer: C

Description : If deck machinery is expected to be idle for an extended period of time you should____________. A. have electrical safety gloves available in case of electrical shock before running B. perform ... run at regular intervals to inusre correct operation and to renew the internal coating of lubrication

Last Answer : Answer: D

Description : A three-phase alternator is operating at 450 volts with the switchboard ammeter indicating 300 amps. The kw meter currently indicates 163.6 KW, with a power factor of 0.7. If the power factor increases to 0.8, the KW meter reading would increase by ___ A. 17.8 KW B. 23.2 KW C. 30.6 KW D. 37.8 KW

Last Answer : Answer: B

Description : Regarding an AC generator connected to the main electrical bus; as the electric load and power factor vary, a corresponding change is reflected in the generator armature reaction. These changes in ... . governor speed droop setting B. voltage regulator C. balance coil D. phase-balance relay

Last Answer : Answer: B

Description : In steam and other vapour cycles, the process of removing noncondensable is called [GATE-1992] (a) Scavenging process (b) Deaeration process (c) Exhaust process (d) Condensation process  

Last Answer : (b) Deaeration process  

Description : After closing the circuit breaker to place two similar alternators in parallel, the NEXT step is to balance the _____________. A. power factor B. voltage load C. kilowatt load D. ampere load

Last Answer : Answer: C

Description : The emergency electrical power source on tank vessels over 500 GT on an international voyage, should be capable of continuous operation under emergency load for _____________. A. 6 hours B. 12 hours C. 18 hours D. 24 hours

Last Answer : Answer: C