Minimum vertical clearance (VC) for a slab/ girder bridges with discharge of 0-30  cumecs is
a) 300 mm
b) 1500 mm
c) 1800 mm
d) 600 mm*

1 Answer

Answer :

d) 600 mm*

Related questions

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Vertical Clearance (VC) in water way bridges is the level difference between a) HFL and Formation level b) Bed level and bottom of superstructure c) HFL and bottom of superstructure* d) Rail level and Formation level

Last Answer : c) HFL and bottom of superstructure*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : .Minimum earth cushion required over RCC Box is a) 300 mm b) 600 mm c) 0* d) 1000 mm

Last Answer : c) 0*

Description : The minimum vertical clearance in RUB in urban area shall be a) 5870 mm b) 6525 mm c) 5000 mm d) 5500 mm*

Last Answer : d) 5500 mm*

Description : The minimum vertical clearance in RUB in rural area shall be a) 5870 mm b) 6525 mm c) 5000 mm* d) 5500 mm

Last Answer : c) 5000 mm*

Description : The minimum vertical clearance above R.L. to bottom of ROB near the yard shall be a) 6525 mm* b) 5870 mm c) 2360 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : The minimum vertical clearance of foot over bridge gangway is a) 2100 mm b) 3660 mm c) 6525 mm d) 2710 mm

Last Answer : d) 2710 mm

Description : Minimum Free Board required in a bridge is a) 1 m* b) 1.20 m c) 600 mm d) 300 mm

Last Answer : a) 1 m*

Description : Clear distance between consecutive sleepers not to exceed on bridges in BG is a) 450 mm* b) 600 mm c) 510 mm d) 500 mm

Last Answer : a) 450 mm*

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block

Last Answer : a) Girder/Slab*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : The vertical clearance of bottom most foot over bridge structure above rail level is a) 6525 mm* b) 3660 mm c) 5330 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : Facia boards of platform shelters shall have a minimum horizontal clearance of ……. from C.L. of track at a minimum height of 4.61m above RL. a) 2360 mm b) 3660 mm c) 3000 mm d) 1600 mm*

Last Answer : d) 1600 mm*

Description : .Minimum wing rail clearance opposing nose of crossing on Fan shaped turnout a. 45 mm b. 40 mm c. 41 mm* d. 44 mm

Last Answer : c. 41 mm*

Description : Minimum clearance between toe of Open switch and stock rail for new works a. 115 mm* b. 120 mm c. 95 mm d. 110 mm

Last Answer : a. 115 mm*

Description : .Minimum check rail clearance at Level crossing a. 45 mm b. 51 mm* c. 50 mm d. 57 mm

Last Answer : b. 51 mm*

Description : The recommended maximum gradient in the year for B.G is- (a) 1 in 1000 (b) 1 in 1200* ( c) 1 in 1500 (d) 1 in 1800

Last Answer : (b) 1 in 1200*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : Given: True track 215; mountain elevation 11,600 ft; local airfield gives qnh as 1035 mb; Required terrain clearance 1500 ft; temparute ISA-15C Which of the following is the minimum flight level considering the temperature?

Last Answer : FL140

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : Minimum permissible vertical wear on nose of a 52 kg CMS crossing on Rajdhani route is i) 6mm ii) 8mm* iii) 10mm iv) 12 mm

Last Answer : ii) 8mm*

Description : For protection of level crossing gate in an emergency on BG double line the Gateman should place one detonator at one place and 3 detonators at a subsequent place at a distance of ------- a) and------ ... c) 500 meters and 1000 meters d) 600 meters and 1200 meters* e) 800 meters in 1500 meters

Last Answer : d) 600 meters and 1200 meters*

Description : The level of guard rail in bridges shall not be lower than that of running rail by more than a) 25 mm* b) 55 mm c) 75 mm d) 65 mm

Last Answer : a) 25 mm*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : The horizontal clearance of edge of foot over bridge structure from face of platform is a) 6525 mm b) 3660 mm* c) 5330 mm d) 5300 mm

Last Answer : b) 3660 mm*

Description : For A class ODC, the gross clearance over maximum moving dimension of B.G is (a) 150mm (b) 175mm (c) 225 mm* (d) (d) 250mm

Last Answer : (c) 225 mm*

Description : The daily water allowance for normal adult (60 kg) is about (A) 200–600 ml (B) 500–800 ml (C) 800–1500 ml (D) 1800–2500 ml

Last Answer : Answer : D

Description : What is Pre Heating Temperature of rail ends in AT Welding? (i) 300 ± 20oC (ii) 400 ± 20oC (iii) 500 ± 20oC (iv) 600 ± 20oC *

Last Answer : (iv) 600 ± 20oC *

Description : The size of a plane table is (a) 750mm x 900 mm (b) 600mm x 750 mm* (c) 450mm x 600 mm

Last Answer : (b) 600mm x 750 mm*

Description : For a continuous slab of 3 m × 3.5 m size, the minimum overall depth of slab to satisfy vertical deflection limits is (A) 50 mm (B) 75 mm (C) 100 mm (D) 120 mm

Last Answer : (B) 75 mm

Description : For a continuous slab of 3 m x 35 m size, the minimum overall depth of slab to satisfy vertical deflection limits is (a) 120 mm (b) 100 mm (c) 75 mm (d) 50 mm

Last Answer : (a) 120 mm

Description : In new Rail as well as second hand rails how much end bends of the rails in vertical are permitted when checked with one meter straight edge before welding? (i) +0.5mm, -0 mm in vertical * (ii) +0.2mm, -.3 mm in vertical (iii) +0.3mm, -2 mm in vertical (iv) 0 mm, +.5 mm in vertical

Last Answer : (i) +0.5mm, -0 mm in vertical *

Description : The depth of 19.81 mlong service girder is about……… a)1.67 m b)1.16 m* c)0.95 m d)1.52 m

Last Answer : b)1.16 m*

Description : If 20 kg of coarse aggregate is sieved through 80 mm, 40 mm, 20 mm, 10 mm, 4.75 mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron and 150 micron standard sieves and the weights retained are 0 kg, 2 kg, 8 kg, ... , the fineness modulus of the aggregate, is (A) 7.30 (B) 7.35 (C) 7.40 (D) 7.45

Last Answer : Answer: Option C

Description : For railway bridges with spans in excess of 30.5m, generally provided with a) deck type girders b) open web through girders* c) semi through girders d) shallow type girders

Last Answer : b) open web through girders*

Description : Minimum clearance of check rails for B.G. at level crossing should be (a) 48mm (b) 57mm (c) 51mm* (d) 44mm

Last Answer : (c) 51mm*

Description : A contractor wishes to determine a suitable combination of manual labour and machine work for the excavation of a multistory construction. For every cum of excavation, 3 man-hours are needed; or 0.2 machine-hour. Costs ... total cost will be (a) 1500 cum (b) 1800 cum (c) 2250 cum (d) 2500 cum

Last Answer : (d) 2500 cum

Description : For a simply supported beam of span 15 m, the minimum effective depth to satisfy the vertical deflection limits should be (A) 600 mm (B) 750 mm (C) 900 mm (D) More than 1 m

Last Answer : Answer: Option B

Description : Free board given in septic tank is about (a) 100 mm (b) 200 mm (c) 300 mm* (d) 500 mm

Last Answer : (c) 300 mm*

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*