Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set in between the head and the plate. c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

1 Answer

Answer :

d) All the above*

Related questions

Description : In flange splices when the number of hammer and hand loose rivets is 30% or more of the total rivets on any side of the splice location, a) Need no be renewed b) wait for 100% loose rivets c) all the rivets should be renewed.* d) None of the above

Last Answer : c) all the rivets should be renewed.*

Description : Renewal of loose rivet shall be taken up in end bearing stiffener when the % of hammer loose rivet is

Last Answer : 30%

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : Minimum vertical clearance (VC) for a slab/ girder bridges with discharge of 0-30 cumecs is a) 300 mm b) 1500 mm c) 1800 mm d) 600 mm*

Last Answer : d) 600 mm*

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : The minimum pitch of rivets of diameter ‘d’ in steel plates shall be a) 2 x d b) 3 x d c) 1.75 x d d) 2.5 x d*

Last Answer : d) 2.5 x d*

Description : The minimum edge distance for rivets of diameter ‘d’ in steel plates shall be a) 2 x d b) 3 x d c) 1.5 x d* d) 2.5 x d

Last Answer : c) 1.5 x d*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : The load transferred from rails to web of girders is in a) deck type girder b) through type girder c) semi-through type girder* d) plate girder

Last Answer : c) semi-through type girder*

Description : The load transferred from rails to bottom flanges is in a) deck type girder b) through type girder* c) semi-through type girder d) plate girder

Last Answer : b) through type girder*

Description : Entire steel work of girder bridge should be painted at regular interval; known as a) patch painting b) periodical through painting* c) Any of the above d) None of the above

Last Answer : b) periodical through painting*

Description : Camber in steel triangulated girder is provided to compensate for deflection a) Under live load and dead load* b) Under live load c) Under dead load d) None of the above

Last Answer : a) Under live load and dead load*

Description : Which of the following are made out of the carbon steel having carbon content of 0.9 to 1%? (A) Small punches, broaches reamers and springs (B) Cutlery, screws, rivets and files (C) ... lathe tools and razors (D) Forgings like can shaft, structural steel plate, threading dies and drawing dies

Last Answer : (A) Small punches, broaches reamers and springs

Description : Minimum speed restriction to be imposed for Track renewal is:- (a) Stop dead & 10 Kmph (b) 10 Kmph (c) 15 Kmph (d) 20 Kmph*

Last Answer : (d) 20 Kmph*

Description : Lowest level of staff/supervisor competent for Renewal/recoupment of fastenings requiring lifting in LWR/CWR. a. PWS b. Gangmate* c. Keyman d. Gangman

Last Answer : b. Gangmate*

Description : Lowest level of staff/supervisor competent of Renewal of fastenings not requiring lifting in LWR/CWR. a. PWS b. Gangmate c. Keyman* d. Gangman

Last Answer : c. Keyman

Description : Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR. a. PWI b. Keyman c. Gangmate* d. PWS

Last Answer : c. Gangmate*

Description : What is the full form of PQRS used for Track renewal works. a. Plasser quick Relaying system* b. Please quick return services c. Poor Quality renewal system d. None of above

Last Answer : a. Plasser quick Relaying system*

Description : Metallising is the process of spraying of …. on the surface prepared girder.

Last Answer : Zinc.. or ..Aluminium.

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : Piano wire is used for measuring the a) Distortion b)Camber in PSC girder c)Both a & b* d)None of above

Last Answer : c)Both a & b*

Description : The depth of 19.81 mlong service girder is about……… a)1.67 m b)1.16 m* c)0.95 m d)1.52 m

Last Answer : b)1.16 m*

Description : Shallow type girder can be used in a) ROBs b) RUBs* c) FOBs

Last Answer : b) RUBs*

Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level

Last Answer : b) commencing from bottom of girder towards bed level*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : When as small area of girder bridge should be painted when requiring immediate painting; known as a) patch painting* b) periodical through painting c) Any of the above d) None of the above

Last Answer : a) patch painting*

Description : Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be removed a) after hardening of concrete b) before hardening of concrete c) during concreting d) after stressing the cables

Last Answer : d) after stressing the cables

Description : In shallow type girders, the rail level shall be a) 25mm above the top flange of girder* b) near the bottom of the girder c) near the middle of the girder d) below the girder

Last Answer : a) 25mm above the top flange of girder*

Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block

Last Answer : a) Girder/Slab*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : Depth of construction in a girder bridge means the depth from a) RL to HFL b) RL to top of bed block * c) RL to bottom of bed block d) RL to Bed level

Last Answer : b) RL to top of bed block *

Description : The most effective method of locating a loose commutator bar in a D.C. motor is by _____________. A. visual inspection B. jiggling each by hand C. sounding each bar with a light weight hammer D. checking with a calibrated torque wrench

Last Answer : Answer: C

Description : The allowable shear stress in stiffened webs of mild steel beams decreases with (a) Decrease in the spacing of the stiffeners (b) Increase in the spacing of the stiffeners (c) Decrease in the effective depth (d) Increase in the effective depth

Last Answer : (b) Increase in the spacing of the stiffeners

Description : How do engineer determine the number of cells for concrete box girder bridges?

Last Answer : If the depth of a box girder bridge exceeds 1/6 or 1/5 of the bridge width, then it is recommended to be designed as a single cell box girder bridge. However, if the bridge depth is ... improvement in transverse load distribution when the number of cells of box girder is increased to three or more.

Description : Are diaphragms necessary in the design of concrete box girder bridges?

Last Answer : Diaphragms are adopted in concrete box girder bridges to transfer loads from bridge decks to bearings. Since the depth of diaphragms normally exceeds the width by two times, they are usually designed ... In fact, diaphragms also contribute to the provision of torsional restraint to the bridge deck.

Description : In Case If Concrete Box Girder Bridges How Is The Number Of Cells Determined?

Last Answer : Answer : When the depth of a box girder bridge exceed 1/6th or 1/5th of the bridge width then the design recommended is that of a single cell box girder bridge. But in case the depth of ... the transverse load distribution when the number of cells of the box girder is higher than three or more.

Description : The weight of rivet testing hammer is

Last Answer : 110 gm

Description : Rebound hammer is used for a) To find the strength of concrete* b) To form rivet heads c) To break the concrete structures d) None of the above

Last Answer : a) To find the strength of concrete*

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : bridge foundation having less then 2M depth below bed level in case of arch bridges and 1.2M depth below bed level in case of other bridges is termed as

Last Answer : …Shallow foundation..

Description : If the SSE/SE/JE/ Br. working in the section is not readily available, another SSE/SE/JE may be authorised by …………….. to witness payment on the section. a) DEN b) SSE/SE/JE/ c) AEN (Bridges)* d) Office clerk

Last Answer : c) AEN (Bridges)

Description : Investigation for important bridges may be carried out in which stage a) Technical feasibility study (reconnaissance survey) b) Techno-economic feasibility study (preliminary engineering survey) c) Detailed survey and project report stage (final location survey) d) All the above *

Last Answer : d) All the above