The depth of 19.81 mlong service girder is about………
 a)1.67 m  
b)1.16 m*  
c)0.95 m  
d)1.52 m

1 Answer

Answer :

b)1.16 m*

Related questions

Description : The discharge through a channel of circular section will be maximum when the depth of water is __________ the diameter of the circular channel. (A) 0.34 times (B) 0.67 times (C) 0.81 times (D) 0.95 times

Last Answer : Answer: Option D

Description : The velocity through a channel of circular section will be maximum when the depth of water is __________ the diameter of the circular channel. (A) 0.34 times (B) 0.67 times (C) 0.81 times (D) 0.95 times

Last Answer : Answer: Option C

Description : Depth of construction in a girder bridge means the depth from a) RL to HFL b) RL to top of bed block * c) RL to bottom of bed block d) RL to Bed level

Last Answer : b) RL to top of bed block *

Description : What is the width of Head of 52 kg Rail section a. 70 mm b. 75 mm c. 67 mm* d. 60 mm

Last Answer : c. 67 mm*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Minimum vertical clearance (VC) for a slab/ girder bridges with discharge of 0-30 cumecs is a) 300 mm b) 1500 mm c) 1800 mm d) 600 mm*

Last Answer : d) 600 mm*

Description : What is the difference between rail flange of 60 kg & 52 rail section a. 20 mm b. 18 mm c. 14 mm* d. 16 mm

Last Answer : c. 14 mm

Description : Formation width for bank for M.G. double line section is (a) 8.50 m (b) 8.84 m (c) 9.65 m (d) 9.81 m*

Last Answer : (d) 9.81 m*

Description : How many joules of work is the equivalent of 15000 cal of heat?  a) 62850 joules  b) 3579.95 joules  c) 14995.81 joules  d) 15004.19 joules Formula: J =Work/Heat J = mechanical equivalent of heat whose value is 4.19 joules/calorie

Last Answer : 62850 joules

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : Metallising is the process of spraying of …. on the surface prepared girder.

Last Answer : Zinc.. or ..Aluminium.

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : Piano wire is used for measuring the a) Distortion b)Camber in PSC girder c)Both a & b* d)None of above

Last Answer : c)Both a & b*

Description : Shallow type girder can be used in a) ROBs b) RUBs* c) FOBs

Last Answer : b) RUBs*

Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level

Last Answer : b) commencing from bottom of girder towards bed level*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : When as small area of girder bridge should be painted when requiring immediate painting; known as a) patch painting* b) periodical through painting c) Any of the above d) None of the above

Last Answer : a) patch painting*

Description : Entire steel work of girder bridge should be painted at regular interval; known as a) patch painting b) periodical through painting* c) Any of the above d) None of the above

Last Answer : b) periodical through painting*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be removed a) after hardening of concrete b) before hardening of concrete c) during concreting d) after stressing the cables

Last Answer : d) after stressing the cables

Description : The load transferred from rails to web of girders is in a) deck type girder b) through type girder c) semi-through type girder* d) plate girder

Last Answer : c) semi-through type girder*

Description : The load transferred from rails to bottom flanges is in a) deck type girder b) through type girder* c) semi-through type girder d) plate girder

Last Answer : b) through type girder*

Description : In shallow type girders, the rail level shall be a) 25mm above the top flange of girder* b) near the bottom of the girder c) near the middle of the girder d) below the girder

Last Answer : a) 25mm above the top flange of girder*

Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block

Last Answer : a) Girder/Slab*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : Camber in steel triangulated girder is provided to compensate for deflection a) Under live load and dead load* b) Under live load c) Under dead load d) None of the above

Last Answer : a) Under live load and dead load*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : Two trains, both 50m long, moving in opposite directions cross each other in 4 seconds. If one is moving thrice as fast the other, then the speed of the faster train is. A) 45km/hr B) 19 km/hr C) 95 km/hr D) 67.5 km/hr

Last Answer : ANSWER:D Explanation:  Let the speed of the slower train be x' m/sec  The speed of the sfaster train = 3x m/s  Relative speed = (x +3x)m/sec  = 4x m/sec  50 + 50 / 4 = 4x  100 / 4 = 4x  100 = 16x  x = 100 ... the faster train = 3 * 25 / 4  = 75 / 4 m/s = (75/4 *18 /5)km/hr  = 67.5 km/hr

Description : Service life of CMS crossing ( 52 Kg rail) is:- (a) 400 GMT. (b) 300 GMT. (c) 200 GMT. (d) 150 GMT.*

Last Answer : (d) 150 GMT.*

Description : Service life in terms of total GMT carried for 52 kg. 90 UTS rail is:- (a) 425 GMT (b) 475 GMT (c) 525 GMT* (d) 545 GMT

Last Answer : (c) 525 GMT*

Description : What is the assessed GMT service life of 52 kg 90 UTS rail. a. 650 GMT b. 600 GMT c. 525 GMT* d. 500 GMT

Last Answer : c. 525 GMT*

Description : ormal size of brick used in India is a) 22 x 11.2 x 7 cm* b) 25 x 16 x 8 cm c) 19 x 12 x 9 cm d) 20 x 10 x 5 cm

Last Answer : a) 22 x 11.2 x 7 cm*

Description : Effective depth of septic tank of 10 users is about (a) 1.0 m () 1.2 m* (c) 1.7 m (d) 2.0 m

Last Answer : b) 1.2 m*

Description : A 2 kg object weighs 1.8 kgf on a spring balance. The value of 'g' at that location in m/sec2is (A) 8.82 (B) 9.81 (C) 10.88 (D) 0.95

Last Answer : (A) 8.82

Description : RBG loading caters for maaaaximum axle load of…….tones for locomotive with trailing loadof…… tonnes/metre of track with maximum axle load of…….tonnes for wagons a)22.9,7.67,25 b)22.5,7.67,22.9* c)25,7.67,22.9, d)None of above

Last Answer : b)22.5,7.67,22.9*

Description : GML loading caters for maaaaximum axle load of…….tonnes for locomotive with trailing load of………tonnes/metre. a)22.9,7.67* b)22.5,7.67 c)25,7.67 d)None of above

Last Answer : a)22.9,7.67*

Description : Minimum clearance between toe of Open switch and stock rail for new works a. 115 mm* b. 120 mm c. 95 mm d. 110 mm

Last Answer : a. 115 mm*

Description : What is the app. Weight of 52 kg portion? (i) 10 kg (ii) 11 kg* (iii) 12 kg (iv) None of the above

Last Answer : (ii) 11 kg*

Description : Standard bag of cement in ……… kg a) 52 kg b) 30.5kg c) 10.7kg d) 50 kg*

Last Answer : d) 50 kg*

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : Minimum rail section recommended for section having traffic more than 20 GMT is (a) 90 UTS (b) 52 Kg. (c) 60 Kg.* (d) None of the above.

Last Answer : (c) 60 Kg.

Description : Minimum permissible vertical wear on nose of a 52 kg CMS crossing on Rajdhani route is i) 6mm ii) 8mm* iii) 10mm iv) 12 mm

Last Answer : ii) 8mm*