All activities lying on critical path have slack time equal to
 (A) 0 (B) 1
(C) 2 (D) None of above

1 Answer

Answer :

(A) 0

Related questions

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : In time-cost optimization of a project, crashing is done. (A) On all the activities (B) On all the activities lying on the critical path (C) Only on activities lying on the ... critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Last Answer : D

Description : Activities lying on critical path are called ............................ a. Critical activities b. Non-critical activities c. Dummy activities d. None of these

Last Answer : a. Critical activities

Description : Software project planning entails what activities? What are the difficulties faced in measuring the Software Costs?

Last Answer : Ans. Software project planning entails the following activities: Estimation: o -Effort, cost, resource, and project duration Project scheduling: Staff organization: o -staffing ... actual specifications of the system hence cost estimations based on uncertain information cannot be accurate.

Description : What are the three activities of risk assessment?

Last Answer : Ans: The three activities are identifying, analyzing and giving priorities. Risks can be identified by a check list or looking at previously identified risks. Risk analysis involves examining how ... with modification of risk input variables. Risk prioritization helps in focus on most severe risks.

Description : Explain a. the activities of software maintenance. b. key process areas of CMM.

Last Answer : Ans: a) Software maintenance is a broad activity that includes error correction, enhancement of capabilities, deletion of obsolete capabilities and optimization. b) Key process areas of CMM ... management which establishes and maintains the integrity of the products throughout the life cycle.

Description : FP-based estimation techniques require problem decomposition based on (A) information domain values (B) project schedule (C) software functions (D) process activities

Last Answer : (C) software functions

Description : What is the normal order of activities in which software testing is organized? (A) unit, integration, system, validation (B) system, integration, unit, validation (C) unit, integration, validation, system (D) none of the above

Last Answer : (A) unit, integration, system, validation

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : What are the assumptions of the execution-time component model? Compare the execution-time component for basic model and the logarithmic Poisson model.

Last Answer : Ans. The execution-time component is based on the following assumptions: (1) Tests represent the environment in which the program will be used. (2) All failures are observed. (3) ... constant for basic model while the decrement per failure decreases exponentially as shown in the following graph.

Description : Software feasibility is based on which of the following (A) business and marketing concerns (B) scope, constraints, market (C) technology, finance, time, resources (D) technical prowess of the developers

Last Answer : (C) technology, finance, time, resources

Description : A key concept of quality control is that all work products (A) are delivered on time and under budget (B) have complete documentation (C) have measurable specification for process outputs (D) are thoroughly tested before delivery to the customer

Last Answer : (C) have measurable specification for process outputs

Description : The model that assumes that effort and development time are functions of product size alone is (A) Basic COCOMO model (B) Intermediate COCOMO model (C) Detailed COCOMO model (D) All the three COCOMO models

Last Answer : (A) Basic COCOMO model

Description : Each time a defect gets detected and fixed, the reliability of a software product (A) increases. (B) decreases. (C) remains constant. (D) cannot say anything.

Last Answer : (A) increases.

Description : Draw the flow chart of Risk Management-Activity and explain various Software risks.

Last Answer : Ans RISK is a problem that could cause some loss or threatens the success of the project, but which has not happened yet. Typical Software Risks:- 1. Dependencies: -Many ... Inadequate application domain experience. New technologies. Ineffective, poorly documented, or neglected processes.

Description : What specific languages can be used in SRS? What are the advantages of using these specific languages of SRS?

Last Answer : Ans. Requirement specification necessitates the use of some specification language. The language should support the desired qualities of the SRS- modifiability, understandability, unambiguous, and so forth. ... formally specify the behavior of a system on different combination of input or settings.

Description : What is Data Dictionary? Explain each component?

Last Answer : Ans Data dictionary is a storehouse of data giving information about data. It is a list of terms and their definition for all data items and data files of a system. A data dictionary contains ... Data Stores- data Flows are data structures in motion whereas data stores are data structures at rest.

Description : Explain incremental model? Define core product and detailed plan.

Last Answer : Ans. The incremental model is proposed by D.L PARNAS. It is basically implemented by combining elements of linear sequential model and iterative prototyping model. Incremental development refer to the process ... . Risk of failure of product is decreased as user start using the product early.

Description : Explain various types of static and dynamic testing tools.

Last Answer : Ans. Static testing tools: 1. Static analysers A static analyser operates from a pre-computed database of descriptive information derived from the source text of the program. The idea of a static ... for documenting that the tests have been done and that no defects were found during the process.

Description : How is cyclomatic complexity useful in program test? What is sequence of testing? What is testability?

Last Answer : Ans. Cyclomatic complexity measures the amount of decision logic in a single software module. It is used for two related purposes in the structured testing methodology. First, it gives the number of ... a lack of testability may hinder testing parts of the software or software requirements at all.

Description : Design black box test suits for a function that checks whether a character or string upto ten characters in a palindrome?

Last Answer : Ans Following may be the test cases: - Try with Even number of characters (MALAYALAM) - Try with Odd number of characters (ADDA) - Try with maximum length of string The following are negative test ... come for the following) - Try with empty string - Try with numbers - Try with special characters

Description : Compare and contrast reliability and availability?

Last Answer : Ans. Reliability:The probability of failure-free system operation over a specified time in a given environment for a given purpose is called reliability Availability:The probability that a system, at ... damage data, low reliability may not be a problem. Availability takes repair time into account.

Description : Explain various Object Oriented concepts used in Software Engineering. Give an example.

Last Answer : Ans .Various concepts of Object Oriented concepts used in Software Engineering: Object:- An object is something which is capable of being seen, touched or sensed. Each object has certain distinctions ... . A message can be sent between two objects only if they have an association between them.

Description : Define cohesion & coupling? Give suitable examples.

Last Answer : Ans Coupling:Coupling refers to the strength of the relationship between modules in a system. Coupling represents how strongly different modules are interconnected with each other. Cohesion: Cohesion ... Cohesion represents how strongly the internal elements of a module are bound to each other.

Description : What is Data Binding?

Last Answer : Ans.The matrix that attempts to capture the module-level concept of coupling is data binding. Data binding are a measure that captures the data interaction across portions of a software system. In ... words, data binding try to specify how strongly coupled different modules in a software system are.

Description : What is function point? Explain its importance. What is function-oriented metrics?

Last Answer : Ans. Function point measures the functionality from the user point of view, that is, on the basis of what the user request and receives in return. Therefore, it deals with ... empirical relationship based on countable measures of software's information domain and assessments of software complexity.

Description : Spiral model is a realistic approach to the development of large-scale systems & software. Justify & explain the model?

Last Answer : Ans. There are several advantages of Spiral model that makes it a realistic approach to development of large-scale systems and software, viz: 1) The spiral model promotes quality assurance ... , which can help in identifying and resolving potential problems or errors in the software development.

Description : What is CMM? Describe its levels & compare it with ISO 9001?

Last Answer : Ans. CAPABILITY MATURITY MODEL (CMM): CMM is a strategy for improving the software process, irrespective of the actual life cycle model used. Software Engineering Institute (SEI) of Carnegie- ... in the CMM are called out in the auditing practices of the verifying implementation common feature.

Description : Explain acceptance testing and beta testing.

Last Answer : Ans. Acceptance Testing and Beta testing:System tests are designed to validate a fully developed system to assure that it meets its requirements. Acceptance and beta testing are form of system ... testing performed by the cutomer to determine whether he should accept the delivery of the system.

Description : Discuss the problems faced during software maintenance

Last Answer : Ans. Problems During Maintenance The most important problem during maintenance is that before correcting or modifying a program, the programmer must first understand it. Then, the programmer ... be very difficult. Therefore approach of development should be the production of maintainable software.

Description : Explain the concept of bottom-up, top-down and hybrid design.

Last Answer : Ans: Bottom up design:This approach leads to a style of design where we decide how to combine these modules to provide larger ones; to combine those to provide even larger ones, ... approaches are often not practical therefore hybrid approach which combines the above two approaches is often used.

Description : Why is good design important for a product?

Last Answer : Ans: A good design is the key to successful product. Almost 2000 years ago a Roman Architect recorded the following attributes of a good design:  Durability  Utility and  Charm A well-designed system is easy to implement, understandable and reliable and allows for smooth evolution.

Description : Define the following terms: (i) Product metrics (ii) Live variables (iii) FAN IN

Last Answer : Ans: (i) Product metrics: describe the characteristics of the product such as size, complexity, design features, performance, efficiency, reliability, portability, etc. (ii) A variable is live from its first ... count of the number of other Components that can call, or pass control, to Component A.

Description : List any three characteristics of a good SRS.

Last Answer : Ans:The SRS should be: Correct , Unambiguous, Complete 1. Correct: An SRS is correct iff every requirement stated therein is one that the software shall meet . 2. Unambiguous: An SRS is ... full labels and references to all figures and diagram and definition of all terms and units of measures

Description : Explain any two requirement elicitation methods.

Last Answer : Ans. Interviews: After receiving the problem statement from the customer, the first step is to arrange a meeting with the customer. During the meeting or interview, both the parties would like to ... -Board, flip chart, worksheets, wall stickiest, etc. Participants should not criticize or debate.

Description : Explain the software life cycle model that incorporates risk factor.

Last Answer : Ans. The problem with traditional software process models is that they do not deal sufficiently with the uncertainty, which is inherent to software projects. Important software projects failed ... . The risk analysis and validation steps eliminate errors in the early phases of development

Description : Discuss any two software characteristics.

Last Answer : Ans.Software is not manufactured: The life of a software is from concept exploration to the retirement of the software product. It is one time development effort and continuous maintenance effort in order ... this characteristic may be the best and may help us to accommodate any kind of change.

Description : What is structured programming and why is it important?

Last Answer : Ans. Structured programming is a term which was coined in the late 1960's to mean programming without using go to statements, programming using only while loops and if statements as ... Structured programming means programs can be read sequentially and are therefore easier to understand and inspect.

Description : What is reverse engineering?

Last Answer : Ans. It is a process of analysing software with a view to understanding its design and specification. - In reverse engineering, source code and executable code are the input. - It may be part of a ... to : - Serves as input to SRS for program replacement. - Be available to help program maintenance.

Description : What are dynamic testing tools? Explain the functions that they must support.

Last Answer : Ans. Dynamic testing tools: 1: coverage analyzers (execution verifiers): A coverage analyzer is the most common and important tool for testing. It is often relatively simple. One of the common ... tester to plan tests so they are both efficient and also effective at forcing discovery of defects.

Description : Define graph matrix and connection matrix.

Last Answer : Ans: Graph matrix: A graph matrix is a square matrix whose size(i.e., number of rows and columns) is equal to the number of nodes on the flow graph. Each row and column corresponds to ... letter has been replaced with a 1, indicating that a connection exists (zeros have been excluded for clarity).

Description : Describe system testing.

Last Answer : Ans. System testing: System test are designed to validate a fully developed systems with a view to assuring that it meets its requirements. There are three types of system testing: Alpha testing: This ... is performed by the customer to determine whether or not to accept the delivery of the system.

Description : Why does the software design improve when we use object-oriented concepts?

Last Answer : Ans. The software design improves when we use object-oriented concepts because 1.Object-orientation works at higher level of abstraction. The development can proceed at the object level and ... good programming techniques. 4.Object-oriented programming design and programming promote code re-use.

Description : Explain the development phases of the detailed COCOMO model.

Last Answer : Ans A software development is carried out in four successive phases, which are as follows: 1: plan/requirements: this is the first phase of the development cycle. The requirement is analyzed, the product ... product. This requires 16% to 34% of normal effort and 18% to 34% of the development time.

Description : Explain the development phases of the detailed COCOMO model.

Last Answer : Ans A software development is carried out in four successive phases, which are as follows: 1: plan/requirements: this is the first phase of the development cycle. The requirement is analyzed, the product ... product. This requires 16% to 34% of normal effort and 18% to 34% of the development time.

Description : Differentiate between structured analysis and structured design.

Last Answer : Ans. The aim of structured analysis is to transform the textual description of a problem into a graphic model. During structured analysis, functional decomposition of the system takes place, i ... define the structure of the solution that is suitable for implementation in some programming language.