Once the logic of a network is laid out, the project manager will conduct a forward
pass and a backward pass through the network. This will provide information regarding
______ and will identify the________.
A. The total duration of the project, critical path
B. The slack for each activity, high risk activities
C. Resource shortages, high risk activities
D. The high risk activities, non-critical path