Which of the following establishes key dates throughout the life of a project that
must be met for the project to finish on time?
Select one:
a. Critical path
b. Ballpark estimate
c. Pert diagram
d. Slack chart
e. Milestone schedule
must be met for the project to finish on time?
Select one:
a. Critical path
b. Ballpark estimate
c. Pert diagram
d. Slack chart
e. Milestone schedule