8 men and 4 women-together can complete a piece of work in 6 days. Work done by a man in one day is double the work done by a woman in one day. If 8 men and 4 women started working and after 2 days, 4 men left and 4 new women joined, in how many more days will the work be completed? a) 7 days b) 6 days c) 5 days d) 8 days e) 4 days 

1 Answer

Answer :

1 man = 2 women

8 men + 4 women = 20 women

2 day's work of 20 women = 20 × 6/1

= 20 × 2/x

x =1/3

Remaining work = 1 – 1/3 = 2/3

Total number of females = 16

20 × 6/1 = 16 × x ÷2/ 3

x = 5 days

Short Cut

M1D1=M2D2+M3D3

10x6 =10x2 + 8 x

60-20= 8x

x= 5 days

Answer: c)

Related questions

Description : P,Q, & R can complete a piece of job together in 20 days. All the 3 started working at it together and after 8 days P left. Then Q & R together completed a job in 20 more days. P alone could complete the work in. a) 60 b) 50 c) 40 d) 30

Last Answer : B Work done by P,Q & R in 8 days = 1/20 * 8 =2/5 Remaining work = (1 - 2/5) = 3/5 Now 3/5 work is done by Q & R in 20 days Whole work will be done by Q & R in(20*5/3) =100/3 days (P+Q+R ... (Q+R)'s 1 day work =1/20 - 3/100 =5-3/100 =2/100 =1/50 P alone could complete the work in 50 days..

Description : A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 4/7 of the work completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? a) 79 b) 80 c) 81 d) 82 e) 83

Last Answer : work finished by 33 days = 33 117 8 = 30888 man hours 4/7th of the job is finished. remaining work = 1-(4/7) = 3/7 if 4/7th of the work is 30888 hours, then 3/7th of the work = [30888 ... 9 number of men = 198 since, 117 men are already working, additional men required = 198 - 117 = 81 Answer: c)

Description : Ram, Suresh and Shilpa, working together, can do a piece of work in 1 day. Ram is thrice as efficient as Suresh, and Suresh takes twice the number of days as Shilpa takes to do it alone. What is the difference between ... and Shilpa, each working alone, to complete the work? a) 1 b) 2 c) 3 d) 4 e) 5

Last Answer : Let the time taken by Ram, Suresh and Shilpa to finish the work alone be A, B and C respectively Therefore, 1/A + 1/B + 1/C = 1 Also it is given that, A = B/3 and C =B/2 3/B + 1/B + ... between the number of days taken by Ram and Shilpa, each working alone, to complete the work = 3-2 = 1 Answer: a)

Description : Kathir and Anand can do a work in 20 days and 30 days respectively. Kathir started the work and left after 4 days. Anand took over and completed the work. In how many days was the total work completed? a) 28 days b) 20 days c) 23 days d) 25 days e) 26 days 

Last Answer : a Kathir’s one day’s work= 1/20 Kathir’s 4 day’s work =4* (1/20) = 1/5 Work left= 1-1/5 = 4 /5 Anand’s one day’s work= 1/30 Anand can do work in = (4/5) *(30/ 1) = 24 days So total days = 24+4 = 28 days

Description : 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days. a) 4 days b) 6 days c) 2 days d) 8 days e) 7 days

Last Answer : Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b Work done by 6 men and 8 women in 1 day = 1/10 => 6m + 8b = 1/10 => 60m + 80b = 1 --- (1) Work done by 26 men and 48 ... 1 day = 15/100 + 20/200 =1/4 => Time taken by 15 men and 20 women in doing the work = 4 days Answer: a)

Description : A task was assigned to P, Q and R to be completed by not more than seven days. P alone can complete the task in ten days. Q alone can complete the task in twelve days and R alone can complete the task in fifteen days. ... will remain after four days? a) 3/10 b) 1/15 c) 1/9 d) 5/16 e) None of these

Last Answer : 1day's work of (P + Q+ R) = 1/10 + 1/12 +1/15 = 15/60 2 day's work of (P + Q+ R) = 15/60 × 2 = 1/2 1 day's work of (P+Q) = 1/10 +1/12 = 11/60 2 day's work of (P+Q) = 11/60 × 2 = 11/30 Rem. work of 4 days = 1- 1/2 + 11/30 = 2/15 Answer: e)

Description : A,B and C can do piece of work in 11 days,20 days and 55 days respectively, working alone. How soon can the work be done if a is assisted by B and C on alternate days/ a) 6 b) 7 c) 8 d) 9 e) 10

Last Answer : Work done by A and B in one day = 1/11 + 1/20 =31/220 Work done by A and C in one day = 1/11 + 1/55 =6/55 Work done in 2 days = 31 /220+6/55=55/220 = ¼ Hence, 1/4 of the work is done in 2 days Hence, it takes 8 days to finish the work Answer : c

Description : A,B and C can do piece of work in 11 days,20 days and 55 days respectively, working alone. How soon can the work be done if a is assisted by B and C on alternate days/ a) 6 b) 7 c) 8 d) 9 e) 10

Last Answer : Work done by A and B in one day = 1/11 + 1/20 =31/220 Work done by A and C in one day = 1/11 + 1/55 =6/55 Work done in 2 days = 31 /220+6/55=55/220 = ¼ Hence, 1/4 of the work is done in 2 days Hence, it takes 8 days to finish the work Answer : c

Description : 8 men and 8 boys can finish a piece of work in 10 days. 9 women and 7 boys can finish the same work in 10 days. Also 7 men and 6 women can finish the same work in 10 days. In how many days 1man, ... boy can finish the work, at their double efficiency? a) 25 days b) 20 days c) 15 days d) 10 days

Last Answer : A Efficiency of 8 men and 8 boys = 10% Efficiency of 9 women and 7boys = 10% Efficiency of 7 men and 6 women = 10% So, Efficiency of 15 men, 15women and 15boys = 30% So, efficiency of 1 man ... efficiency Efficiency of 1 man, 1 woman and 1 boy = 4% Required number of days = 100/4=25 days

Description : Francis and George started a business with investments of Rs.7000 and Rs.10000. After x months, Francis left. After two more months David joined the business with an investment of Rs.10000. If the annual profit is shared among David, ... which they stayed that year. a)5:5:12 b)1:1:3 c)1:1:4 d)1:1:2

Last Answer : a)5:5:12

Description : P, Q and R can do a piece of work in 18,24 and 36 days on the second day and P on the third day, again R on the fourth day and so on. Then in how, many days will the work be completed? 1. 25 2. 24 3. 22 4. 20 5. 26

Last Answer : 2;

Description : Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, wo

Last Answer : Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are ... work in 25 days, working 6 hours per day ?

Description : 8 male can finish a work in 6 days.12 female can complete the same work in 9 days. 6 male and 4 female started working and after 4 days 3 more female joined them. How many days will they now take to complete the remaining work? a) 76/41 days b) 25/62days c) 3/31days d) 4/77days

Last Answer : A 1 male's 1 day work = 1/48 1 female's 1 day work = 1/108 Work done in 4 days = 4 (6/48 +4/108) =4(1/8+1/27) =1/2+4/27 =(27+8)/54 =35/54 Remaining work = (1 - 35/54) = 19/ ... (27+14)/216 =41/216 Now 41/216 work is done by them in 1 day Therefore time taken = 216/41 * 19/54 = 76/41 days

Description : Rakchita can do a piece of work in 28 days, while Shreya can do the same work in 42 days.They started the work together but 6 days before the completion of the work, Rakchita left the work. The total number of days to complete the work is a) 3 b) 4 c) 5 d) 6 

Last Answer : D 6 days before the completion of the work Rakchita left the work means in last 6 days only Shreya has worked alone So, in last 6 days worked done by Shreya = 6*1/42=6/42=1/7 So, the rest = 1-1/7 =6/7 So 6/7work was done by Rakchita and Shreya worked together=6/7*70/10 =420/70=6 days

Description : 20 workers working 5hours a day can finish the work in 20 days.If the workers went to work for 4hours a day.How many more workers are required to complete the work in same 20days? 1)7 2)4 3)5 4)6

Last Answer : 3)5 Exp: workers required for 4h=>(5/4)×20=25. 25-20=5.

Description : A started a business with Rs. 21,000 and is joined afterwars by B with Rs. 36,000. After how many months did B join if the profits at the end of the year are divided equally? A.8 months B.2 months C.5 months D.7 months

Last Answer : Answer – C (5 months) Explanation – let B joined after x months Then, 21000 x 12 = 36000 x (12 – x)36 = 180x = 5Hence, B joined after 5 months

Description : P and Q started a partnership business investing some amount in the ratio of 3:5. R joined them after six months with an amount equal to that of Q. In what proportion should the profit at the end of one year be distributed among P, Qand R? A.5 : 8 : 10 B.6 : 10 : 5 C.6 : 4 : 10 D.10 : 6 : 3

Last Answer : Answer – B (6 : 10 : 5) Explanation – Let the initial investments of P and Q be 3a amd 5a. P : Q : R = (3a x 12) : (5a x 12) : (5a x 6) = 36 : 60 : 30 = 6 : 10 : 5.

Description : A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall? a) 13/3 days b) 22/3 days c) 7/4 days d) 7 days e) None of these

Last Answer : Amount of work done by A in one day = 1/8th of the total work B can break 1/3rd of the work in one day Therefore, if both of them are working together then the work done in one day = 1/8 - 1/3 = -5/24 ... = 11/12 Time taken by A to finish 11/12th of the work = 11/12 8 = 22/3 days Answer: b)

Description : Arun started a business with Rs. 40,000 and is joined afterwards by Arul with Rs.60, 000. After how many months did Arul join if the profits at the end of the year are divided equally? a) 3 b) 4 c) 5 d) 6 e) 2

Last Answer : b Suppose, Arul joined after x months.  Then, 40000 * 12 = 60000 * (12 – x) => 48 = 72 - 6x => 6x = 24 → x = 4

Description : 90 persons can complete a job in 32 days. 12 days after they started working, 60 more persons joined them. How many days will they now take to complete the remaining work? a) 10 days b) 12 days c) 14 days d) 16 days

Last Answer : B (90 * 32) persons can complete the work in 1 day. 1 person 1 day's work = 1/(90 *32) i.e., 1/2880 90 person's 12 day's work = 1/32 * 12 = 3/8 Remaining work =(1- 3/8) = 5/8 150 persons 1 ... 5/96 work is done by them in 1 day . Therefore 5/8 work is done by them, = (96/5*5/8) =12 days.

Description : Out of 5 women and 4 men, a committee of three members is to be formed in such a way that at least one member is woman. In how many different ways can this be done? 1) 60 2) 100 3) 120 4) 90 5) 80

Last Answer : 5) 80

Description : Sai and Ram working together completed a job in 10 days. If sai worked twice as efficiently as he actually did and ram worked 2/3 as efficiently as he actually did, the work would have been completed in 6 days. Sai alone could complete the work in. a) 40/3 days b) 42/4 days c) 44/6 days d) 43/3 days

Last Answer : A Let sai's 1 day work = x Ram's 1 day work = y Then x+y = 1/10 ===>1 and 2x +2y /3 = 1/6 (6x+2y )/3 = 1/6 6x + 2y =1/2 ====>2 Multiply 1 by 6 =>6x+6y = 6/10 2 = ... /10 - 1/40 = 4-1/10 =3/40 Sai's 1 day work = 3/40 So sai alone could complete the work in 40/3 days.

Description : A man can do a piece of work in 10 days. With the help of a boy he can do the same piece of work in 8 days. If they get Rs. 11115 for the work then what will be the share of boys? a) Rs.2223 b) Rs.2784 c) Rs.3163 d) Rs.3312 e) None of these

Last Answer : In one day boys can do = (1/8) – (1/10) = (5-4)/10 = 1/40 part so, boys can finish the work in 40 days. Now, Men’s share : Boy’s share = 40 : 10 = 4 : 1 Boys share = (11115 / 5) × 1 = Rs. 2223 Answer is: a)

Description : The capacities of A,B and C to complete a piece of work is `1:2:3`. By working together, the thre of them can complete the work in 24 days. In how man

Last Answer : The capacities of A,B and C to complete a piece of work is `1:2:3`. By working together, the ... days. In how many days can C alone complete it ?

Description : Hanisha can do a work in 25 days, while sudha can do the same work in 50 days. They started the work jointly.Few days sughana also joined them and thus all of them completed the whole work in 12 days. All of them were paid total Rs.900. What is the Share of sughana? a) 252 b) 346 c) 454 d).359

Last Answer : A Efficiency of Hanisha = 1/100*25 =25/100=1/4=>4% Efficiency of sudha = 2% Thus, in 12 days working together they will complete only 72% of the work. [(4+2)*12] =72 Hence, the remaining work will ... which is =(100-72)=28% Thus, sughana will get 28% of Rs. 900, =28/100*900 which is Rs.252

Description : A committee of 5 members is to be formed from 8 men and 5 women. How many committees can be formed if at least 2 women and 1 man have to present in the committee? a) 800 b) 840 c) 880 d) 920 e) 996

Last Answer : The various possible cases are: i. 2 women and 3 men = 5C2 × 8C3 = 10 × 56 = 560 ii. 3 women and 2 men = 5C3 × 8C2 = 10 × 28 = 280 iii. 4 women and 1 men = 5C4 × 8C1 = 5 × 8 = 40 Total = 560 + 280 + 40 = 880 Answer: c)

Description : Three pipes A, B and C can fill a tank in 6 hours. After working at it together for 2 hours, C is closed and A and B can fill the remaining part in 7 hours. The number of hours taken by C alone to fill the tank is: a) 10 b) 14 c) 12 d) 13 e) 15

Last Answer : (A+B+C) - (A+B) (A+B+C) =1/6 and (A+B+C) in 2hrs=2/6 and remaining part 1-2/6=2/3. So (A+B) in 7 hrs is 2/ (3*7) =2/21. 1/6-2/21=1/14 so answer is 14. Answer: b)

Description : If six men working 8 hours a day earn Rs.840 per week, then 9 men working 6 hours per day will earn per week a) Rs. 940 b) Rs. 945 c) Rs. 1620 d) Rs. 1680 e) Rs. 1245

Last Answer : b) Rs. 945

Description : Twenty workers can complete a piece of work in 30 days. After how many days should 5 workers leave the job so that the work is completed in 35 days? a) 5 days b) 10 days c) 15 days d) 20 days

Last Answer : c) 15 days

Description : A boy and his mother together can do a piece of work in 24 days while the day, working with his father, can complete it in 18 days. If the mother and

Last Answer : A boy and his mother together can do a piece of work in 24 days while the day, working with ... take to complete the job, if they work individually.

Description : A and B working alone can finish a job in 5 days and 7 days respectively. They work at it alternately for a day. If A starts the work, find in how many days the job will be finished? a) 29/5 b) 11/5 c) 24/5 d) 21/5 e) None of these

Last Answer : Work done by A in one day = 1/5 and work done by B in one day = 1/7 They are working alternately. Therefore, Work done in first two day = (1/5 + 1/7) = 12/35 Work done in first four day = 24/35 Work done in ... = 4/35/1/7 = 4/5 of the day. Therefore Total days taken = 5 + 4/5 = 29/5 days Answer: b)

Description : 4 women and 3 men can do a piece of work in 2 days while 6 women and 2 men can also finish it in 2 days. Now find the time taken by one woman to compl

Last Answer : 4 women and 3 men can do a piece of work in 2 days while 6 women and 2 men can also ... time one man takes to complete the same job working alone.

Description : 6 men and 10 women can finish making pots in 8 days, while the 4 men and 6 women can finish it in 12 days. Find the time taken by the one man alone from that of one woman alone to finish the work. -Maths 9th

Last Answer : Given: 6 men and 10 women can finish making pots in 8 days 4 men and 6 women can finish it in 12 days To find: Time taken by the one man alone from that of one woman alone to finish the work ... = 48Then time taken by the one man alone from that of one woman alone to finish the work is 48 days

Description : Mr. Sachin spent 20% of his monthly income on food and 15% on children's education. 40% of the remaining he spent on entertainment and transport together and 30% on the medical. He is left with an amount of Rs.8, 775/- after ... 000/- b) Rs.46,000/- c) Rs.36, 000/- d) Rs.29,000/- e) None of these

Last Answer : Let the total income of Mr.Sachin be 100 According to question, 100 – 20 –15 = 65 × 60/100 × 70/100 = 27.3. 27.3 = 100 8775 = 100/27.3 × 8775 = Rs. 32142. Answer: e)

Description : X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………

Last Answer : X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………

Description : A sum of money is divided among Suresh, Ganesh, Vignesh and Mahesh in the ratio of 3 : 4 : 9 : 10 respectively. If the share of Vignesh is Rs.2,580/-more than the share of Ganesh, then what is the total amount of money of Suresh ... ,985/- b) Rs. 6,487/- c) Rs. 6,708/- d) Rs. 7,156/- e) Rs. 8,457/-

Last Answer : According to the question, difference of ratio of Ganesh and Vignesh is 5 so, 1 ratio = 2580/5 = 516 Now, total ratio of Suresh + Mahesh = 13 So, total money = 13 × 516 = Rs. 6708 Answer: c)

Description : If 40 men complete a piece of work in 5 days, then 80 man can complete the same piece of work in _____.

Last Answer : If 40 men complete a piece of work in 5 days, then 80 man can complete the same piece of work in _____.

Description : Pipe A can fill a water tank in 8 hours, Pipe B can fill the same tank in 12 hours and Pipe C can empty the tank in 24 hours. If all three pipes are opened together, in how many hours will the tank be completely filled or empty? a) 4.8 hours b) 5 hours c) 5.4 hours d) 6 hours e) 7.2 hours

Last Answer : If all the three pipes are opened together, in one hour they will fill 1/8 + 1/12 – 1/24 = (3+2-1)/24 = 1/6 part of tank. So, to fill it completely it will take 6 hours. Answer is: d)

Description : Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job? (a) 8 hrs (b) 7 1/2 hrs (c) 7 hrs (d) 9 hrs

Last Answer : (b) 7 1/2 hrs

Description : An amount becomes 160% of itself in 5 years through simple interest. At the same rate of interest, how long will it take for the amount to more than double itself if we use compound interest? a) 7 b) 8 c) 9 d) 10 e) cannot be determined

Last Answer : Answer: a)

Description : Among 4 persons A, B, C and D. A takes twice as much time as B to complete a piece of work. B takes twice as much time as C and C takes twice as much time as D to complete the same work. One group of three of the ... is the group that takes 11 days? a) A.B.C b) A,B,D c) B,C,D d) None of the above

Last Answer : B From the given information B is twice as efficient as A. C is twice as efficient as B. D is twice efficient as C. If work done by A in a day is 'n' units, the work done in a day by B, ... of times taken to complete the work by the former and later groups is 11:7 A, B and D take 11 days.

Description : Seven men, five women and eight children were given as assignment of distributing 2000 books to students in a school over a period of three days. All of them distributed books on the first day. One of the second ... distributed on the second day? a) 1000 b) 800 c) 650 d) 900 e) Cannot be determined

Last Answer : Answer: C Sol. Let the books distributed by man, a woman and a child be 5x, 4x and 2x respectively. ∴ No. of books distributed in 1st day = 7 5x+5 4x+8 2x=71x No. of books distributed in 2nd day =7 ... 2x=46x 71x + 57x + 46x = 2000, x = 2000/174 57x=2000/174 57= 655 650 (Approx)

Description : A man can row 15 km/hr in still water. It takes him twice as long to row upstream as to row downstream. Find the rate of stream? a) 5 km/hr b) 10 km/hr c) 7.5 km/hr d) 6 km/hr e) 8 km/hr

Last Answer : Let the man’s upstream speed be x km/hour and downstream speed will be 2x km/hour Speed in still water = 1/2 (2x + x) = 3x/2 km/hour 3x/2 = 15 X = 10 Hence, his downstream speed = 20km/hour Rate of stream = 1/2 (20-10) = 5km/hour Answer: a)

Description : There are 20 pieces of bread to divide among 20 people. A man eats 3 pieces, woman eats 2 pieces and a child eats half piece of bread. Tell the correct combination of men, women and children so that ... the bread. You have to tell there are how may are men, women and children in those 20 people.

Last Answer : There are 5 women, 1 man and 14 children.

Description : There are 20 pieces of bread to divide among 20 people. A man eats 3 pieces, woman eats 2 pieces and a child eats half piece of bread. Tell the correct combination of men, women and children so that ... the bread. You have to tell there are how may are men, women and children in those 20 people.

Last Answer : There are 5 women, 1 man and 14 children.

Description : In a unit time, the work done by 3 men is equal to the work done by 6 women. The ratio of work done by a man to that of a woman is ………………

Last Answer : In a unit time, the work done by 3 men is equal to the work done by 6 women. The ratio of work done by a man to that of a woman is ………………

Description : M & N do a certain work in 40 days and 24 days respectively. M started the work alone and then after 8 days N joined him till the completion of the work. How long did the work last? a) 16days b) 18days c) 20 days d) 22 days

Last Answer : C Work done by M in 8 days = 1/40*8 =1/5 Remaining work = 1-1/5 = 4/5 (M+N)’s 1 day work = 1/40 + 1/24 =(3+5)/120 =8/120 =1/15 Now 1/15 work is done by M & N in 1 day. So 4/5 work will be done by X and Y is, =15 / 1 * 4/5 =12 days Hence total time taken = 12+8 = 20 days

Description : Rishwi can finish a work in 6 days working 4 hours a day. Dhiviksha can complete the same work in 4 days working 5 hrs a day. If both rishwi and dhiviksha work together, working 4 hrs a day, in how many days can they finished the work? a) 30/11 b) 11/120 c) 11/30 d) 30/13

Last Answer : A Rishwi can complete the work in (6*4) = 24 hrs Dhiviksha can complete the work in (4*5) = 20 hrs Rishwi's 1 hr work = 1/24 Dhiviksh's 1 hr work = 1/20(Rishwi and dhivikasha)'s 1 hr work = (1/24 ... fininsh the work in (120/11)hrs Number of days of 4 hrs each = 120/11*1/4 =120/44 =30/11 days

Description : A this usual rowing rate, Mohit can travel 12 miles downstream in a certain river in 6 hours less than it takes him to travel the same distance upstream. But if he could double his usual rowing rate for his 24 miles round trip, ... current in miles per hour? A.2.5m/hr B.4 m/hr C.8/3 m/hr D. 5/3m/hr

Last Answer : Answer-C Basic Formula: Speed of the stream = ½ (a-b) km/hr Explanation: Let the speed in still water be x m/hr Speed of stream be y m/hr Then, speed upstream = x-y m/hr and Speed downstream = x+y m/hr 12/x-y - ... 1] 3y^2 = 8 y so, y = 8/3 speed of the current = 8/3 m/hr = 2 (2/3) m/hr

Description : Is X divisible by 12? a. X leaves a remainder 2 when divided by 8 b. X is divisible by 3. c. X is divisible by 6. a) If the data in statement a is sufficient to answer the question, while ... the question. e) If the data in statement a, b and c together are not sufficient to answer the question.

Last Answer : From (a), we notice that the number is of the form 8n+2, which means it also leaves a remainder 2 on being divided by 4. So, its not divisible by 12. From (b) and (c) together, the number can be any multiple of 6, from which we cant conclusively say if number is divisible by 12. Answer: a)