What Is Acceptance Testing?

1 Answer

Answer :

Acceptance Testing is performed by the client to see if the system delivers what was requested. It looks similar to system testing but the difference is in the focus. Here, the testing is done by Client from his point of view as he is the one who knows the whole process and requirements of his business.

Related questions

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : The criteria for acceptance of a project on the basis of Profitability Index (PI) is   A.PI=0 B. PI > 0   C. PI < 0   D. PI > 1

Last Answer : D. PI > 1

Description : The outputs of the Close Project process include all of the following except for which one?  A. Administrative closure procedure B. Formal acceptance C. Lessons learned D. Closed contracts

Last Answer : C. Lessons learned

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : From a contract management perspective, the project manager must consider the: 1. acquisition process 2. contract administration  3. ecological environment  4. offer, acceptance, and consideration  5. a and b

Last Answer : 5. a and b

Description : Which of the following is the most efficient means of product quality inspection? 1. Acceptance sampling  2. 100% inspection  3. Variable sampling  4. a and c

Last Answer : 3. Variable sampling

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project B. an independent project C. a dependent project D. None of the above

Last Answer : B. an independent project

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project. D. a contingent project.

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project E. none of the above

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project

Last Answer : C. a dependent project

Description : A project whose acceptance requires the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project E. none of the above

Last Answer : A. a mutually exclusive project.

Description : A project whose acceptance precludes the acceptance of one or more alternative projects is referred to as . A. a mutually exclusive project. B. an independent project. C. a dependent project D. a contingent project

Last Answer : C. a dependent project

Description : Following are the phases of Project Management Life Cycle. Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (A) 3-2-1-4

Description : . In project management, the term quality is best defined as: a. inspection, testing and measurement. b. reviews and audits. c. fitness for purpose of deliverables. d. professionally-bound project reports.

Last Answer : c. fitness for purpose of deliverables.

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : A simple way of looking at the spiral life-cycle model is as a waterfall model with each phase proceeded by a) Build-and-fix b) Freezing c) Synchronization d) Testing e) Risk analysis

Last Answer : e) Risk analysis

Description : In the maintenance phase the product must be tested against  previous test cases. This is known as testing. (a) Unit (b) Integration (c)Regression (d) Module (e) Beta

Last Answer : (c)Regression

Description : The final form of testing COTS is........................testing. a) Unit (b) Integration (c) Alpha (d) Module (e) Beta.

Last Answer : (e) Beta.

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Following are the phases of Project Management Life Cycle.  Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery  (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (D) 4-3-2-1

Description : For the best model suitable for the project, in which of the phase  the developers decide a roadmap for project plan? a. Design b. System Analysis c. Coding d. Testing

Last Answer : b. System Analysis

Description : Which of the following is not considered as a risk in project management? a. Specification delays b. Product competition c. Testing d. Staff turnover

Last Answer : c. Testing

Description : In project management, the term quality is best defined as:  a. inspection, testing and measurement.  b. reviews and audits.  c. fitness for purpose of deliverables.  d. professionally-bound project reports.

Last Answer : c. fitness for purpose of deliverables.

Description : Differentiate Between Sitp And Utp In Testing?

Last Answer :  SITP - System Integration Test Plan - This test is performed in an integrated mode usually by the testing team.  UTP - Unit Test Plan - This test plan is performed at the smallest level or in a standalone mode. It is usually performed by the developers.

Description : What Is V Model In Testing?

Last Answer : The mapping of the type of testing to the stage of development in a given project is done by V model. In this model of testing there is a testing stage for every development stage which means a mapping between the development and a testing.

Description : What's The Difference Between Unit Testing, Assembly Testing And Regression Testing?

Last Answer :  Unit testing ensures that the program unit meets the requirements which are reliable. Unit testing is normally conducted by the programmer who is supervised by the team lead. Testing the individual unit ... . The testers will run all the scripts in order to ensure that nothing has been affected.

Description : What Is Difference Between Sitp And Utp In Testing?

Last Answer :  A test plan that is done at the smallest level or stand alone mode is known as Unit Test Plan. For example, a project is having customer and invoicing modules. So the test on ... normally done by developers and the system testing is normally done by testing professionals in an integrated mode.

Description : What Do You Mean By V-model In Testing?

Last Answer : V-model performs a mapping between the type of test and the stage in project development i.e which test is to be performed at which stage. This has 4 levels of testing the system: 1. ... independent tester. 3. System Testing- performed by system team. 4. Acceptance testing-performed by the client.

Description : What Is System Testing?

Last Answer : System testing is done to see if the system delivers the required features, functional and nonfunctional requirements & outputs. It doesn't check each component individually but the whole system is ... Testing.  Volume Testing.  Stress Testing.  Documentation Testing.  Robustness Testing.

Description : What Is Regression Testing?

Last Answer : Regression testing is performed to see if the system would work well in case of any enhancements or changes in future. Here, all the scripts are run together to see that others are not affected by a change in one module.

Description : What Is Assembly Testing?

Last Answer : Assembly testing moves one step ahead of Unit testing. It checks if two or more modules are able to communicate and produce expected results or not. No Unit in the system can perform stand alone activities ... result. Assembly testing is a way of Black box testing and can be done through the UI.

Description : What Is Unit Testing?

Last Answer : Unit testing, also called Component testing is performed by programmers to test that a specified unit of the program meets the expected output when a particular input is provided. Here, the programmer has ... in the components. A Unit in unit testing means a module self contained and by itself.

Description : What Is Black Box Testing And White Box Testing?

Last Answer : Black box testing is an external perspective of the object that is to be tested to obtain test cases. These tests may be functional or non functional. The valid and invalid inputs are tested ... chosen by the tester to exercise paths through the code to determine the outputs that are appropriate.

Description : What Is White Box Testing?

Last Answer : White box testing is done to test the accuracy of logic and code of the program. It is done by programmers who know the logical flow of the system. It can be done by testing the classes or components in isolation. One of the ways of doing it is Unit Testing.

Description : What Is Black Box Testing?

Last Answer : Black box testing or functional testing means testing the software for the outputs when specified inputs are provided. It is usually performed to see if the software meets the user's requirements. There's ... . An example of this could be manual testing of the system by a tester, assembly testing.

Description : What Is Difference Utp In Testing ?

Last Answer : UTP (Unit Test Plan) are done at smallest unit level or stand alone mode. UTP can be done using NUNIT. Unit testing is done normally by developers.

Description : Does ask-public have separate system integration testing and user acceptance testing environments?

Last Answer : We have a staging environment (of course). We’ve long since abandoned Javascript-based test suites. We had a two javascript bugs that slipped through—one which only affected IE 6 and 7, and another that only affected non-moderators on questions that had new moderations.

Description : Testing helpstoensure_——_—of the program for use within a system. a. Quality, accuracy and except b. Quality, accuracy and acceptance c. Design, assurance and acceptance d. Quality, accuracy and development

Last Answer : b. Quality, accuracy and acceptance

Description : Match every stage of the software Development Life cycle with the Testing Life cycle: i. Hi-level design a Unit tests ii. Code b Acceptance tests iii. Low-level design c System tests iv. Business requirements d Integration tests a) i-d , ii ... i-b , ii-a , iii-d , iv-c d) i-c , ii-a , iii-d , iv-b

Last Answer : d) i-c , ii-a , iii-d , iv-b

Description : Which of the following uses Impact Analysis most? a) Component testing b) Non-functional system testing c) User acceptance testing d) Maintenance testing

Last Answer : d) Maintenance testing

Description : Acceptance testing means A. Testing performed on a single stand - alone module or unit of code B. Testing after changes have been made to ensure that no unwanted changes were introduced C. ... the needs of the organization and end user. D. Users test the application in the developers environment

Last Answer : C. Testing to ensure that the system meets the needs of the organization and end user.

Description : For final software acceptance testing, the system should include A. Delivered software B. All user documents C. Final version of oth

Last Answer : D. All of the above

Description : Testing techniques that can be used in acceptance testing are A. Structural B. Functional C. Usability D. A and B E. B and C

Last Answer : D. A and B

Description : Which of the following is not a type of test under phases in testing life cycle? A. Integration test B. Load test C. User Acceptance test D. Beta test

Last Answer : D. Beta test

Description : Explain acceptance testing and beta testing.

Last Answer : Ans. Acceptance Testing and Beta testing:System tests are designed to validate a fully developed system to assure that it meets its requirements. Acceptance and beta testing are form of system ... testing performed by the cutomer to determine whether he should accept the delivery of the system.

Description : Alpha and Beta Testing are forms of (A) Acceptance testing (B) Integration testing (C) System Testing (D) Unit testing

Last Answer : (A) Acceptance testing

Description : V- model uses -------- test models a) Component testing, integration testing, system testing and acceptance testing b) alpha testing, beta testing , acceptance testing and user testing c) black box testing, white box testing and gray box testing

Last Answer : a

Description : Which of the following is the form of Alpha and Beta Testing? a) Acceptance Testing b) System Testing c) Unit Testing d) Integration Testing

Last Answer : Ans : a