You are the project manager for a top-secret software project for an agency of the
United States government. Your mission—should you choose to accept it—is to complete
the project using internal resources. The reason is that finding contractors with top-secret
clearances takes quite a bit of time, and waiting for clearances would jeopardize the
implementation date. Your programmers are 80 percent of the way through the
programming and testing work when your agency appoints a new executive director.
Slowly but surely your programmers are taken off this project and reassigned to the
executive director’s hot new project. Which of the following type of project ending is
this?
A. Starvation
B. Extinction
C. Addition
D. Integration
United States government. Your mission—should you choose to accept it—is to complete
the project using internal resources. The reason is that finding contractors with top-secret
clearances takes quite a bit of time, and waiting for clearances would jeopardize the
implementation date. Your programmers are 80 percent of the way through the
programming and testing work when your agency appoints a new executive director.
Slowly but surely your programmers are taken off this project and reassigned to the
executive director’s hot new project. Which of the following type of project ending is
this?
A. Starvation
B. Extinction
C. Addition
D. Integration