What characteristic best describes the cost baseline? a. Total budget for the project b. Time phased budget for the project c. Total budget for the project including the contingency budget d. Total budget for the project including the contingency budget and the management reserve. 

1 Answer

Answer :

What characteristic best describes the cost baseline? a. Total budget for the project b. Time phased budget for the project c. Total budget for the project including the contingency budget d. Total budget for the project including the contingency budget and the management reserve. 

Related questions

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Which of the following is displayed as an S curve?  A. Gantt B. Cost baseline C. Critical path D. Schedule baseline

Last Answer : B. Cost baseline

Description :  A time-phased budget that project managers use to measure and monitor cost performance. A. Cost Baseline B. Cost Budgeting C. Cost Estimating D. Cost Variance

Last Answer : A. Cost Baseline

Description : Should individuals acquire baseline medical evaluations? If so, which ones?

Last Answer : If you are male and over 50 get a PSA test done when you have your physical. If your doc says you don’t need it, ask him if he knows his PSA number. If he’s under 60 and says “Yes”, kick him in the balls.

Description : In baseball, what is the second line along the first baseline?

Last Answer : What second line? I don’t see it.

Description : which of the following in the scope baseline is not considered while defining activities?

Last Answer : Need Answer

Description : What of the following is a key benefit of the Integrated Baseline Reviews (IBR)?

Last Answer : Need answer

Description : What is A baseline for an experimental investigation is provided by the?

Last Answer : Control Group

Description : What is the difference between the conventional method of dimensioning and the baseline method of dimensiong?

Last Answer : What is the difference between the conventional method ofdimensioning and the baseline method of dimension

Description : what does the term baseline sugar or sugar baseline mean and how is it determined for a diabetic or just a normal person?

Last Answer : what does the term sugar baseline mean and how is it determined for a person

Description : When conducting a baseline IH survey the industrial hygienist would evaluate:?

Last Answer : Ventilation, processes, noise levels, and ergonomic conditions

Description : If a ball is hit outside the 3rd baseline, what is it called?

Last Answer : home run

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : Which of the following makes up the project scope baseline?  A. The project scope statement B. The scope management plan and WBS C. The WBS, project scope statement, and WBS dictionary D. The scope management plan, the WBS, and the WBS dictionary

Last Answer : C. The WBS, project scope statement, and WBS dictionary

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : Indecodinga digital signal, the receiver calculates a running average of thereceived signal power, called the _______. A) baseline B) base C) line D) none of the above

Last Answer : baseline

Description : In a PIN diode, leakage current in the absence of light is called: a. baseline current b. zero-point current c. dark current d. E-H current

Last Answer : c. dark current

Description : Which of the following software change management activities is most vital to assessing the impact of proposed software modifications? A. Baseline identification B. Configuration auditing C. Change control D. Version control

Last Answer : C. Change control

Description : What is the main purpose of performing pulp test on a recently traumatised tooth? A. Obtain baseline response B. Obtain accurate indication about pulp vitality

Last Answer : A. Obtain baseline response

Description : Which International Telecom Company uses the baseline ‘Intelligence Everywhere’ ?

Last Answer : Motorola

Description : Components of the cell membrane constantly shift. The _____ model describes this characteristic of the cell membrane?

Last Answer : The fluid mosaic model is a model of the cell membrane.

Description : What is a characteristic that best describes United Kingdom's economy?

Last Answer : Traditional

Description : What characteristic best describes what happen during a physical change?

Last Answer : The compsitions stays the same :0

Description : What statement describes a characteristic of the Nazi party?

Last Answer : Sorry, not enough info to give an answer.

Description : What of the following describes a characteristic of the Norths economy?

Last Answer : You need to answer this question question because we don’t dohomework. You have the list that describes the economy.

Description : What characteristic describes a mature river?

Last Answer : What is the answer ?

Description : What of the following describes a characteristic of the Norths economy?

Last Answer : You need to answer this question question because we don’t dohomework. You have the list that describes the economy.

Description : Which sentence best describes a characteristic of a parable?

Last Answer : The story stresses the affects of a good and bad behavior.

Description : Which sentence best describes a characteristic of a parable?

Last Answer : The story stresses the affects of a good and bad behavior.

Description : Pick up the correct statement from the following: (A) Topology describes the geometric characteristic of objects which do not change under transformations and are independent of any coordinate system ... The three elements of topology are adjacency, containment, and connectivity (D) All of these

Last Answer : Answer: Option D

Description : The spectrum of a radar transmitter describes what characteristic of the output pulse?

Last Answer : Frequency distribution