Which of the following project baselines provides the basis for measurement of
the expected cash flow against requirements over time and is often displayed as an
S curve?
Select one:
a. Schedule baseline
b. Cost performance baseline
c. Scope baseline
d. Plan baseline
e. Initiation baseline