Description : Which of the following project baselines provides the basis for measurement of the expected cash flow against requirements over time and is often displayed as an S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline
Last Answer : b. Cost performance baseline
Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project performance and progress measurement tool. B. ... approach that combines the scope and cost baseline into a project performance and progress measurement tool.
Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project performance and progress measurement tool.
Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance
Last Answer : D. There is no cost variance
Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance
Description : The Scope Baseline is: 1. the original description of the project's end results 2. a summary description of the project's original content and end product, including basic budgetary and time constraint data 3. the original project budget and schedule 4. a and c
Last Answer : 2. a summary description of the project's original content and end product, including basic budgetary and time constraint data
Description : )Resource leveling attempts to : 1. Reduce resource requirements by smoothing out period-to period resource assignments. 2. Ensure that the budget abnormalities are overcome. 3. Reduce the ... Increase the amount of the project manager's authority so that budget dollars can be appropriated.
Last Answer : 1. Reduce resource requirements by smoothing out period-to period resource assignments.
Description : A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given: Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index? A.0.895 B.0.81 C.0.90 D.1.12
Last Answer : A.0.895
Description : Earned value management integrates scope, cost, and schedule measures to: A. assess project performance and progress. B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.
Last Answer : A. assess project performance and progress.
Description : Complete the following statement. As a project manager, Darrell is excited that he is assigned to be in charge of the most important project this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.
Last Answer : b. start to define and develop the stakeholder needs and requirements
Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance
Last Answer : C. Management Contingency Reserve
Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.
Last Answer : b. to deliver the project objectives to enable benefits to be realised.
Description : Work that continues throughout the project and does not relate to any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.
Last Answer : b) Project function
Description : Which of the following makes up the project scope baseline? A. The project scope statement B. The scope management plan and WBS C. The WBS, project scope statement, and WBS dictionary D. The scope management plan, the WBS, and the WBS dictionary
Last Answer : C. The WBS, project scope statement, and WBS dictionary
Description : In a project schedule, the sequence of activities which cannot be delayed during the course of the project without extending the project end date is referred to as the: A. Action plan B. Critical path C. Schedule baseline D. Slack line
Last Answer : B. Critical path
Description : Following is(are) the responsibility(ies) of the project manager. (A) Budgeting and cost control (B) Allocating resources (C) Tracking project expenditure
Last Answer : (C) Tracking project expenditure
Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.
Last Answer : a. overall project duration.
Description : Following is(are) the responsibility(ies) of the project manager. (A)Budgeting and cost control (B)Allocating resources (C)Tracking project expenditure (D)All of the above
Last Answer : (D)All of the above
Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan.
Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities, uncertainties, and inflation that could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis
Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the investment cost of the project can be measured and managed
Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.
Last Answer : a. All variance to the project scope is evaluated.
Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000
Last Answer : d. $875,000
Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected
Description : Kathryn has little experience estimating the time it will take to complete a systems project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points c. industry standards d. Microsoft Project e. more complex approach
Last Answer : c. industry standards
Description : According to leading experts in software development, the margin of error when estimating project costs is 100% and the margin of error in project scheduling time is 25%.
Last Answer : Ans: True
Description : Using typical industry standards for estimating project time schedules, the estimated analysis phase would be 10 person-months for a systems project where the planning phase was completed in 7.5 person-months.
Description : Using typical industry standards for estimating project time schedules, the estimated analysis phase would be 25 person-months for a systems project where the planning phase was completed in 30 person-months.
Last Answer : Ans: False
Description : When estimating project time schedules using industry standards for a systems project, the following values are acceptable: 15% for planning, 25% for analysis, 50% for design, and 10% for implementation.
Description : . When estimating project time schedules using industry standards, the estimated project completion time for a systems project would be _____ person-months if the actual planning phase were completed in 6 person-months. a. 30 b. 40 c. 17.14 d. 9 e. 50
Last Answer : b. 40
Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan b. creating the work plan, staffing the project, and controlling ... the deliverables e. setting the start date, estimating the time, and reading the actual time
Last Answer : b. creating the work plan, staffing the project, and controlling and directing the project
Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of alternative options. b. ensure ... the project. d. document the outcome of the risk, change and configuration management processes.
Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the project.
Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of alternative options. b ... managing the project. d. document the outcome of the risk, change and configuration management processes.
Description : Which of the following is displayed as an S curve? A. Gantt B. Cost baseline C. Critical path D. Schedule baseline
Last Answer : B. Cost baseline
Description : All of the following influence capital budgeting cash flows except . A. choice of depreciation method for tax purposes B. economic length of the project C. projected sales (revenues) for the project
Last Answer : B. economic length of the project
Description : The estimated benefits from a capital budgeting project are expected as cash flows rather than income flows because . A. it is more difficult to calculate income flows than cash flows B. it ... is central to the firm's capital budgeting decision C. this is required by the accounting profession
Last Answer : B. it is cash, not accounting income, that is central to the firm's capital budgeting decision
Description : The successful project managers spend most of their time: A. Planning with their personnel B. Planning with the top management C. Communication with the project team (Ans.) D. Studying project results
Last Answer : C. Communication with the project team (Ans.)
Description : Approximately what percentage of the project manager's time is spent in some form of communication, such as: conferences, meetings, writing memos, reading and preparing reports, and talking with project team members, upper ... other stalk holders? 1. 10-20% 2. 50-70% 3. 75-90% 4. 21-45%
Last Answer : 3. 75-90%
Description : The successful project managers spend most of their time: 1. Planning with their personnel 2. Planning with the top management 3. Communication with the project team 4. Studying project results.
Last Answer : 3. Communication with the project team
Description : Which of the following represents the estimated value of the work actually accomplished? A. Earned value (EV) B. Planned value (PV) C. Actual cost (AC D. Cost variance (CV)
Last Answer : A. Earned value (EV)
Description : The BCWS = $250, the ACWP = $350, and the BCWP = $200. Calculate the Cost Variance. 1. -$150 2. $150 3. -$50 4. $50
Last Answer : 1. -$150
Description : Cost Variance (CV) is which of the following equations? 1. CV = BCWP - BCWS 2. CV = BCWP - ACWP 3. CV = SV / BCWS 4. A and c
Last Answer : 2. CV = BCWP - ACWP
Description : Which of the following is/are main parameters that you should use when computing the costs of a software development project? a) travel and training costs b) hardware and software costs c) effort costs (the costs of paying software engineers and managers) d) all of the mentioned
Last Answer : d) all of the mentioned
Description : Do it because I said to” is the mantra for project managers who use _____ as the default approach to resolve conflict. Select one: a. collaborating b. compromising c. accommodating d. forcing e. avoiding
Last Answer : d. forcing
Description : Which conflict resolution technique do project managers use most often? A. Smoothing B. Norming C. Confronting D. Forcing
Last Answer : C. Confronting
Description : Two mutually exclusive projects are being considered. Neither project will be repeated again in the future after their current lives are complete. There exists a potential problem though -- ... NPV technique and simply choose the highest IRR since managers are concerned about maximizing returns.
Last Answer : A. Rely on the NPV method and make your choice as it will tell you which one is best.
Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.
Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.
Description : Project managers have to assess the risks that may affect a project. a) True b) False
Last Answer : b) False