Procedure:
* A trench of minimum 60cm deep is made along with cable route.
* Width of trench depends on number of conduits to be laid.
* Separate pipes are provided for each cable.
* Spacing between 2 cables (conduit) is between 25 cm to 75 cm.
* Diameter of pipe is 2 to 3 cm, greater than cable diameter for easy handling of cable.
* Pipe used may be cement pipe, DWC pipe or ducts of glad stone are used.
* For Maintenance and other cable work, man-holes are provided at suitable distance.
* Size of man-holes should be large enough to allow a person to enter into duct without difficulty.
* Unarmored cables are used in this type.