Which of the following does not affect cash flows from a proposal:

A. Salvage value

B. Depreciation amount

C. Tax rate change

D. Method of project

financing

1 Answer

Answer :

D. Method of project

financing

Related questions

Description : All of the following influence capital budgeting cash flows except . A. choice of depreciation method for tax purposes B. economic length of the project C. projected sales (revenues) for the project

Last Answer : B. economic length of the project

Description : In proper capital budgeting analysis we evaluate incremental cash flows. A. accounting B. operating C. before-tax D. financing

Last Answer : B. operating

Description :  A company has to choose between two projects whose cash flows are as indicated  below; Project 1:  i. Investment - Rs. 15 Lakhs ii. Annual cost savings - Rs. 4 lakhs. iii. Bi-annual ... years xii. Salvage Value- 2 lakhs Which project should the company choose? The annual discount rate is 12

Last Answer : Year Project 1 Project 2 Outgo Saving NPV Outgo Saving NPV 0 15.0 0 =-15.0 14.0 0 = -14 1 0 4.0 = (4 / (1+.12)1 = 3.571 0.2 3.5 = (3.3 / (1+.12)1 = 2.95 2 0.5 4.0 = (3.5 / (1+.12)2 = 2.79 0.2 3.5 ... (1+.12)8 = 3.43 0.2 5.5  (3.5+2) = (5.3 / (1+.12)8 = 2.14 NPV = + 2.301 @12% = + 0.15

Description : Which of the following is least likely to be part of the calculation of the terminal- year incremental net cash flow for an energy-related expansion project? A. An initial working capital ... Disposal/reclamation costs C. Capitalized expenditures D. Salvage value of any sold or disposed assets

Last Answer : D. Salvage value of any sold or disposed assets

Description : Cash inflows from a project include: A. tax shield of depreciation B. after tax operating profits C. raising of funds D. Both (a) and (b)

Last Answer : D. Both (a) and (b)

Description : To the nearest rupee, what is the net present value of a replacement project whose cash flows are -Rs.104,000; Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 0 through 4, respectively? The firm has decided to ... -free rate is 6%. A. Rs.15,115 B. Rs.26,798 C. Rs.33,346 D. Rs.48,121

Last Answer : C. Rs.33,346

Description : Depreciation (A) Costs (on annual basis) are constant when the straight line method is used for its determination (B) Is the unavoidable loss in the value of the plant, equipment and materials with lapse in time ... income tax liability on cash flows from an investment (D) All (A), (B) and (C)

Last Answer : (D) All (A), (B) and (C)

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : Which of the following is not used in capital budgeting? A. B. C. D. Time Value of Money Sensitivity Analysis Net Assets Value Method Cash Flows

Last Answer : Net Assets Value Method

Description : A reactor having a salvage value of Rs. 10000 is estimated to have a service life of 10 years. The annual interest rate is 10%. The original cost of the reactor was Rs. 80000. The book value of the reactor after 5 years ... method will be Rs. (A) 40,096 (B) 43,196 (C) 53,196 (D) 60,196

Last Answer : D) 60,196

Description : A Firm is considering undertaking a project that would yield annual profits (after  depreciation) of Rs 68,000 for 5 years. The initial outlay of the project would be Rs  800,000 and the project's assets would have ... accounting rate of return for this project?  A 16%  B 8.5%  C 8.0%  D 9.1%

Last Answer : A 16%

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return. B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated.

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following statements is correct regarding the internal rate of return (IRR) method? A. Each project has a unique internal rate of return B. As long as you are not dealing with ... of return is rarely used by firms today because of the ease at which net present value is calculated

Last Answer : D. The internal rate of return is rarely used by firms today because of the ease at which net present value is calculated.

Description : Which of the following is not followed in capital budgeting? A. Cash flows principle B. Interest exclusion principle C. Accrual principle D. Post tax principle

Last Answer : C. Accrual principle

Description : The basic capital budgeting principles involved in determining relevant after-tax incremental operating cash flows require us to . A. include sunk costs, but ignore opportunity costs B. include ... C. ignore both opportunity costs and sunk costs D. include both opportunity and sunk costs

Last Answer : B. include opportunity costs, but ignore sunk costs

Description : What is a cash flow table in project management?  A. A table portraying inflow of cash in a project  B. A table portraying outgoing expenses of a project  C. It is the tool that is used ... inflows and  outflows down, usually on a monthly basis  D. A table portraying debts taken for a project

Last Answer : C. It is the tool that is used to study such cash flows by breaking inflows and  outflows down, usually on a monthly basis

Description : The estimated benefits from a capital budgeting project are expected as cash flows rather than income flows because . A. it is more difficult to calculate income flows than cash flows B. it ... is central to the firm's capital budgeting decision C. this is required by the accounting profession

Last Answer : B. it is cash, not accounting income, that is central to the firm's capital budgeting decision

Description : Income tax paid should be shown separately as the cash flows from----------- activities. a) Financing b) Investing c) Operating d) Others

Last Answer : c) Operating

Description :  A sound capital budgeting technique is based on: A. Cash Flows B. Accounting Profit C. Interest rate on borrowings D. Last dividend paid

Last Answer : A. Cash Flows

Description : The depreciation during the year 'n', in diminishing balance method of depreciation calculation, is calculated by multiplying a fixed percentage 'N' to the (A) Initial cost (B) Book value at the end ... ) Depreciation during the (n - 1)th year (D) Difference between initial cost and salvage value

Last Answer : (B) Book value at the end of (n - 1)th year

Description : 'P' is the investment made on an equipment, 'S' is its salvage value and 'n is the life of the equipment in years. The depreciation for Rath year by the sum-of year’s digit method will be (A) (P - S)/n (B) 1 - (P/S)1/m (C) (m/n) (P - S) (D) [2 (n - m + 1)/n(n + 1)]. (P - S)

Last Answer : D) [2 (n - m + 1)/n(n + 1)]. (P - S)

Description : A machine has an initial value of Rs. 5000, service life of 5 years and final salvage value of Rs. 1000. The annual depreciation cost by straight line method is Rs. (A) 300 (B) 600 (C) 800 (D) 1000

Last Answer : (C) 800

Description : A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method ... Rs. 4,75,000 (B) Rs. 5,75,000 (C) Rs. 6,50,000 (D) Rs. 8,50,000

Last Answer : (B) Rs. 5,75,000

Description : The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation ... be (A) Rs. 8,800 (B) Rs. 7,600 (C) Rs. 6,400 (D) Rs. 5,000

Last Answer : (C) Rs. 6,400

Description : Having defined working capital as current assets, it can be further classified according to  . A. financing method and time B. rate of return and financing method C. time and rate of return D. components & time

Last Answer : D. components & time

Description : How can a firm provide a margin of safety if it cannot borrow on short notice to meet its  needs? A. Maintain a low level of current assets (especially cash and marketable securities) ... the level of fixed assets (especially plant and equipment D. Lengthening the maturity schedule of financing

Last Answer : D. Lengthening the maturity schedule of financing

Description : Interest payments, principal payments, and cash dividends are the typical budgeting cash-flow analysis because they are A. included in; financing B. excluded from; financing C. included in; operating D. excluded from; operating

Last Answer : C. included in; operating

Description : The project team documents its charge in the form of a ____, which is based on the  project proposal and business case

Last Answer : Ans. Project charter

Description : The main product is……….. a. project proposal b. Problem Identification c. Problem Definition d. Project Planning

Last Answer : a. project proposal

Description : An annuity is a series of equal payments occuring at equal time intervals, and this amount includes the sum of all payments plus interest, if allowed to accumulate at a definite rate of interest from ... cost (B) Depreciation by sinking fund method (C) Discrete compound interest (D) Cash ratio

Last Answer : (B) Depreciation by sinking fund method

Description : Capital budgeting decisions are based on: A. Incremental profit B. Incremental cash flows C. Incremental assets D. Incremental capital

Last Answer : B. Incremental cash flows

Description : A project has the following cash inflows Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 1 through 4, respectively. The initial cash outflow is Rs.104,000. Which of the following four statements ... than or equal to 14%, but less than 18%. D. The IRR is greater than or equal to 18%.

Last Answer : C. The IRR is greater than or equal to 14%, but less than 18%.

Description : _____________ may be defined as the excess of present value of project cash inflows over that of out flows. A. Net present value technique. B. Average rate of return. C. Benefit-Cost ratio. D. Internal rate of return

Last Answer : A. Net present value technique.

Description : Net Present Value of a machine is  A. PV of cash inflows less cost of investment  B. PV of cash inflows ÷ cost of investment  C. PV of net profit after tax less cost of investment  D.PV of cash inflows less average cost of investment

Last Answer : A. PV of cash inflows less cost of investment

Description : The cash inflows and (outflows) associated with a project are as follows: At start  (120000) , Year1-40000, Year2-50000, Year3-60000, Residual Value(at the end of 3rd  year)-20000. The payback period for this project ... 2 years and 3 months.  B 2 years and 6 months.  C 3 years.  D 2 years.

Last Answer : B 2 years and 6 months.

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : Which of the following is/are true if a firm has a required rate of return equal to the ROE? I. The amount of earnings retained by the firm does not affect market price or the P/E. II. The firm can increase market ... (III) above D. Both (II) and (III) above E. All (I), (II) and (III) above

Last Answer : E. All (I), (II) and (III) above

Description : Which of the following is true?  A. Discounted cash flow analysis is the least precise of the cash flow techniques, because  it does not consider the time value of money. B. NPV is ... least precise of the cash flow analysis techniques, because it assumes  reinvestment at the cost of capital.

Last Answer : C. Payback period is the least precise of the cash flow analysis techniques, because it  does not consider the time value of money.

Description : )The total amount of risk that is calculated for a project is found by 1. Multiplying the sum of each the risk times the amount at stake 2. Calculating the cumulative sum of the probability for ... 3. Cannot be calculated since all risks are not know  4. The amount of project reserves available

Last Answer : 2. Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events

Description : Political unrest, budget overruns, size and complexity of the project  Answer: B  (8)Decision trees are best used for : 1. Determining the interaction of the amount at stake and the expected ... and the associated events  4. A flow chart which determines the standard deviation of the risk event

Last Answer : 3. An illustration of how to see the interactions between decisions and the associated events

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if ... years is 0.069? (A) Rs. 31050 (B) Rs. 34500 (C) Rs. 37950 (D) Rs. 5000

Last Answer : (A) Rs. 31050

Description : The ____ then submits the proposal to get it investigated on its viability, evaluation and  selection

Last Answer : Ans. Client

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : The payback period is the period  A. a project takes to pay back the loan taken to purchase the capital assets  B. equal to the useful life of the machines  C. a project takes to recover its initial cash outflow  D. over which the project will be getting operating cash inflows

Last Answer : C. a project takes to recover its initial cash outflow