A critical path network diagram does NOT:

A. Help determine the amount of float

B. Identify the particularly important activities

C. Calculate earned value

D. Calculate the duration of the whole

project

1 Answer

Answer :

C. Calculate earned value

Related questions

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : To crash a schedule you should: 1. Increase the time allowed on those tasks that have float.  2. Try to increase expenditures of time only those tasks that are behind schedule.  3. Replace those ... to par with the busy.  4. Increase work efforts on those tasks that are on the critical path.

Last Answer : 4. Increase work efforts on those tasks that are on the critical path.

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : What would be the critical path if the duration of activity C increased to 10? A. ABCF B. ABCEF C. ABGHIF D. ABGHIF & ABDEF

Last Answer : A. ABCF

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : The network diagram is the best tool for demonstrating:  A. Schedule variances B. Resource requirements C. The sequence of project activities  D. Schedule performance over time

Last Answer : C. The sequence of project activities

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : Feasibility study determines -----------------  A.Whether the project is possible with resources  B.Comparing the project with world class manufacturing norms C.Calculate the cost crashing each unit  D.Add duration to each unit

Last Answer : A.Whether the project is possible with resources

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.

Last Answer : a. overall project duration.

Description : Scheduling can best be defined as the process used to determine:  a. overall project duration.  b. project cost estimating.  c. the project management plan.

Last Answer : a. overall project duration.

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : What is the critical path through the network above? A. ABGHIF B. ABDEF C. ABGHIF& ABDEF D. AB CEF

Last Answer : B. ABDEF

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at  completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000

Last Answer : d. $875,000

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : A critical success factor for project management is to _____.  a. create a work plan  b. follow the three steps of project management  c. identify most project tasks  d. manage the hundreds of tasks

Last Answer : e. start with a realistic assessment of the work

Description : Amount of work completed to date compared with planned in the Earned Value  Management method is  A. Schedule Performance Index  B. Cost Performance Index  C. Percentage Complete  D .Percentage Spent

Last Answer : C. Percentage Complete

Description : ....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis

Last Answer : d. Network analysis

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Which one of the following is a responsibility of the project steering group/board? a. To identify potential problems for the project team to solve. b. To provide strategic direction and guidance ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : The methods and regulation used to define goals, plan and monitor tasks and resources, identify and resolve issues, and control costs and budgets for a specific project is known as … a. project management. b. Process Management c. Process d. Activities

Last Answer : a. project management.

Description : Which one of the following is a responsibility of the project steering group/board?  a. To identify potential problems for the project team to solve.  b. To provide strategic direction and ... project team in all daily activities. d. To receive and consider daily reports from team members.

Last Answer : b. To provide strategic direction and guidance to the sponsor.

Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.

Description : The main outcome of risk identification, in a risk management process, is to:  a. identify and determine the relative importance of the project risks.  b. identify and describe all risks that ... to the project risks.  d. identify and describe risks that have occurred on previous projects.

Last Answer : b. identify and describe all risks that might occur on the project.