A prerequisite of effective time management is: 

1. Knowing the dictated project completion date 

2. Having the most advanced software package for project planning, scheduling and control 

3. Having a good project WBS which identifies the major project deliverables and tasks, and the 

person responsible for

each of them 

4. Having a well staffed scheduling department

1 Answer

Answer :

1. Knowing the dictated project completion date

Related questions

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : Each project phase is marked by completion of one or more: 1. Tasks.  2. Milestones  3. Deliverables  4. Life cycles

Last Answer : 3. Deliverables

Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan  b. creating the work plan, staffing the project, and controlling ... the deliverables  e. setting the start date, estimating the time, and reading the actual time

Last Answer : b. creating the work plan, staffing the project, and controlling and directing the  project

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : The work plan records and keeps track of all of the tasks that need to be accomplished  over the life of the project, listing each task, along with important information about it,  such as when it needs to be completed, the person assigned to do the work, and any  deliverables that will result.

Last Answer : Ans: True

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Which one of the following statements is true?  a. Independent reviews and quality audits form part of quality assurance to ensure the project  manager delivers on time and to budget. ... planning enables the project manager to manage the trade-off between customer  expectations and budget.

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for  purpose and meet stakeholder expectations.

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which stage of project management life cycle requires the maximum time of  completion  A.Conceptualization  B.Planning  C.Execution  D.Estimation

Last Answer : C.Execution

Description : Configuration management is best described as: a. control in the implementation of changes to project schedules. b. an organization to review proposed changes to the project deliverables ... and documentation. d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : Configuration management is best described as:  a. control in the implementation of changes to project schedules.  b. an organisation to review proposed changes to the project deliverables ... and documentation.  d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : . When estimating project time schedules using industry standards, the estimated  project completion time for a systems project would be _____ person-months if the actual  planning phase were completed in 6 person-months.  a. 30  b. 40  c. 17.14  d. 9  e. 50

Last Answer : b. 40

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project.  Where will Ryan look first to locate the identifiable tasks he will record in his work plan?  a. ... . the project planning software available at the local bookstore  e. the website of his old college professor

Last Answer : c. the company training materials for the company methodology

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description : What should be done by the project manager to ensure that all the work in the  project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.

Last Answer : c. Create a WBS.

Description : Which of the following makes up the project scope baseline?  A. The project scope statement B. The scope management plan and WBS C. The WBS, project scope statement, and WBS dictionary D. The scope management plan, the WBS, and the WBS dictionary

Last Answer : C. The WBS, project scope statement, and WBS dictionary

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : The main aim of a project risk management process should be to:  a. identifies project risks and then manage them appropriately.  b. identify all project risks and transfer them immediately.  ... are threats or opportunities on a project.  d. satisfy the organisation's project management process.

Last Answer : a. identifies project risks and then manage them appropriately.

Description : Which one of the following best defines a benefit? a. A positive result of stakeholder management. b. The successful management of a project. c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : . In project management, the term quality is best defined as: a. inspection, testing and measurement. b. reviews and audits. c. fitness for purpose of deliverables. d. professionally-bound project reports.

Last Answer : c. fitness for purpose of deliverables.

Description : According to the Project Management Institute (PMI), the scope statement should  address all of the following issues EXCEPT: Select one: a. project constraints. b. project assumptions c. project ... d. code of conduct for the team members working on the project. e. project deliverables.

Last Answer : d. code of conduct for the team members working on the project.

Description : Which one of the following best defines a benefit?  a. A positive result of stakeholder management.  b. The successful management of a project.  c. An improvement resulting from project deliverables. d. The successful delivery of project reports and updates.

Last Answer : c. An improvement resulting from project deliverables.

Description : In project management, the term quality is best defined as:  a. inspection, testing and measurement.  b. reviews and audits.  c. fitness for purpose of deliverables.  d. professionally-bound project reports.

Last Answer : c. fitness for purpose of deliverables.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : The methods and regulation used to define goals, plan and monitor tasks and resources, identify and resolve issues, and control costs and budgets for a specific project is known as … a. project management. b. Process Management c. Process d. Activities

Last Answer : a. project management.

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : When planning a systems project, overly optimistic timetables are the cause of project  completion delays.

Last Answer : Ans: True

Description : To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______  level of the WBS 1. Highest  2. Lowest  3. Major work effort  4. Third

Last Answer : 2. Lowest

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : A project management information system consists of: 1. A project management software package operating on appropriate computer facilities  2. Hardware, software, documents, and procedures  3. Automated and ... of  pertinent information for members of a project team  4. All of the above

Last Answer : 4. All of the above

Description : Creating a work plan requires three steps: identify the tasks that need to be  accomplished, estimate the time that it will take to complete the tasks, and record the task  completion time in a Gantt Chart.

Last Answer : Ans: False

Description : A communication management plan identifies the relevant information that should be communicated to: a. the project team. b. the project stakeholders. c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : A communication management plan identifies the relevant information that should be  communicated to:  a. the project team.  b. the project stakeholders.  c. the project board. d. the project sponsor.

Last Answer : b. the project stakeholders.

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed