. When estimating project time schedules using industry standards, the estimated
project completion time for a systems project would be _____ person-months if the actual
planning phase were completed in 6 person-months.
a. 30
b. 40
c. 17.14
d. 9
e. 50
project completion time for a systems project would be _____ person-months if the actual
planning phase were completed in 6 person-months.
a. 30
b. 40
c. 17.14
d. 9
e. 50