Which of the following types of Organizational Charts can be BEST used to track project 

costs :

A. Hierarchical-type Organizational Chart

B. Organizational Breakdown Structure

C. Resource Breakdown Structure

D. Responsibility Assignment Matrix

1 Answer

Answer :

C. Resource Breakdown Structure

Related questions

Description : Which of the following types of Organizational Charts can be BEST used to track project costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.

Last Answer : b. Organizational Breakdown Structure.

Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : Which structure shows the reporting relationships and communications channels for a  project?  a. Work Breakdown Structure.  b. Organisational Breakdown Structure.  c. Product Breakdown Structure.  d. Responsibility assignment structure.

Last Answer : b. Organisational Breakdown Structure.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : An Organisational Breakdown Structure (OBS) is used to identify:  a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : The document that identifies what information needs to be shared, to whom, why, when and  how is called the: a. communication management plan.  b. stakeholder mapping grid.  c. document distribution schedule.  d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : PERT chart can be used to track the tasks of a project when task time estimates are  fairly uncertain.

Last Answer : Ans: True

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : The justification for the investment to be made in a project is documented in the: a. Cost Breakdown Structure. b. procurement strategy. c. business case. d. Project Management Plan.

Last Answer : c. business case.

Description : Which one of the following statements best defines the purpose of a Product Breakdown Structure (PBS)? a. To define the hierarchy of deliverables that are required to be produced on the project. ... . d. To identify the health and safety strategies and procedures to be used on the project

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : The entire process of a project may be considered to be made upon a number of sub- processes placed in different stages called the Work Breakdown Structure. (True/False)

Last Answer : Ans. True

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : The evolutionary Work Breakdown Structure makes it easy to compare the current  project with past project

Last Answer : Ans: True

Description : The traditional Work Breakdown Structure makes it easy to compare the current  project with past projects.

Last Answer : Ans: False

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : The justification for the investment to be made in a project is documented in the:  a. Cost Breakdown Structure.  b. procurement strategy.  c. business case.  d. Project Management Plan

Last Answer : c. business case.

Description : Which one of the following statements best defines the purpose of a Product Breakdown  Structure(PBS)?  a. To define the hierarchy of deliverables that are required to be produced on the project.  b. ... .  d. To identify the health and safety strategies and procedures to be used on the project.

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name  of this identifier? 1. Product ID number  2. Code of accounts  3. Quality inspection identifier  4. Project activity code

Last Answer : 2. Code of accounts

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract

Description : The strategy used to correct resource over-allocations by balancing demand for resources and  the available supply is known as (A) resource assignment (B) resource leveling (C) resource splitting (D) resource scheduling

Last Answer : (B) resource leveling

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Risk Event Graph is having following on X axis  A.Gantt Chart  B.Work Break Down Structure  C.Project Life Cycle  D.Splitting

Last Answer : C.Project Life Cycle

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : If you would like to see a list of resources and the tasks that people are assigned to.  What view best displays this information?  A.Resource Sheet  B. Task Usage  C. Gantt Chart  D.: Resource Usage

Last Answer : C. Gantt Chart

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : A ____ needs to possess excellent analytical and organizational skills to manage a project team

Last Answer : Ans. Project Manager

Description : Constantine suggests four “organizational paradigms” for  engineering teams. The best project team organizational model to use when handling extremely complex problems is  a. Random paradigm b. Open paradigm c. Synchronous paradigm d. Closed paradigm

Last Answer : a. Random paradigm

Description : In corporate costs, cost incurred to finance construction of new equipment are classified as A. treasury costs B. discretionary costs C. human resource management costs D. corporate administration costs

Last Answer : A. treasury costs

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : The evolutionary Work Breakdown Structure approach is very useful when the  requirements of the system are not well understood.

Last Answer : Ans: True