The evolutionary Work Breakdown Structure approach is very useful when the 

requirements of the system are not well understood.

1 Answer

Answer :

Ans: True

Related questions

Description : The traditional Work Breakdown Structure approach is very useful when the  requirements of the system are not well understood.

Last Answer : Ans: False

Description : The evolutionary Work Breakdown Structure makes it easy to compare the current  project with past project

Last Answer : Ans: True

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : Which structure shows the reporting relationships and communications channels for a project? a. Work Breakdown Structure. b. Organizational Breakdown Structure. c. Product Breakdown Structure. d. Responsibility assignment structure.

Last Answer : b. Organizational Breakdown Structure.

Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following statements best defines the purpose of a Product Breakdown Structure (PBS)? a. To define the hierarchy of deliverables that are required to be produced on the project. ... . d. To identify the health and safety strategies and procedures to be used on the project

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work  with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram

Last Answer : a. layered description

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : The entire process of a project may be considered to be made upon a number of sub- processes placed in different stages called the Work Breakdown Structure. (True/False)

Last Answer : Ans. True

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A)Technical key resources (B)Work key structure (C)Work Breakdown Structure (WBS). (D)None of the above

Last Answer : (C)Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : The traditional Work Breakdown Structure makes it easy to compare the current  project with past projects.

Last Answer : Ans: False

Description : Which structure shows the reporting relationships and communications channels for a  project?  a. Work Breakdown Structure.  b. Organisational Breakdown Structure.  c. Product Breakdown Structure.  d. Responsibility assignment structure.

Last Answer : b. Organisational Breakdown Structure.

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : Which one of the following statements best defines the purpose of a Product Breakdown  Structure(PBS)?  a. To define the hierarchy of deliverables that are required to be produced on the project.  b. ... .  d. To identify the health and safety strategies and procedures to be used on the project.

Last Answer : a. To define the hierarchy of deliverables that are required to be produced on the project.

Description : Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name  of this identifier? 1. Product ID number  2. Code of accounts  3. Quality inspection identifier  4. Project activity code

Last Answer : 2. Code of accounts

Description : The Scope Management Plan is included in which of the following documents. 1. Project Plan  2. The Work Breakdown Structure  3. The Scope Statement  4. Project Specifications

Last Answer : 3. The Scope Statement

Description : ) One of the initial project documents, issued by senior management, which outlines the  authority of the project manager, is called Project charter. As a seller, what other document can  be used in this place: 1. Work breakdown structure  2. Project scope  3. Contract  4. Internal memo

Last Answer : 3. Contract

Description : What Is A Work Breakdown Structure (wbs)?

Last Answer : The work breakdown structure defines the total project. A work breakdown structure is a product oriented, family tree composed of hardware elements, software elements, and service elements. The work ... the end product. The work breakdown structure is not an organization chart of company personnel.

Description : For a well understood data processing application it is best to use (A) The waterfall model (B) prototyping model (C) the evolutionary model (D) the spiral model

Last Answer : (A) The waterfall model

Description : An Organizational Breakdown Structure (OBS) is used to identify: a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of communication ... . d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : The justification for the investment to be made in a project is documented in the: a. Cost Breakdown Structure. b. procurement strategy. c. business case. d. Project Management Plan.

Last Answer : c. business case.

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Which of the following types of Organizational Charts can be BEST used to track project costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Andrew has joined as the Project Manager of a project. One of the project documents  available to Andrew lists down all the risks in a hierarchical fashion. What is this document  called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Which of the following types of Organizational Charts can be BEST used to track project  costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : An Organisational Breakdown Structure (OBS) is used to identify:  a. the reporting structure and current availability of all individuals in the project. b. technical ability and line of ... project. d. the reporting structure and lines of communication for all individuals in the projects.

Last Answer : d. the reporting structure and lines of communication for all individuals in the projects.

Description : The justification for the investment to be made in a project is documented in the:  a. Cost Breakdown Structure.  b. procurement strategy.  c. business case.  d. Project Management Plan

Last Answer : c. business case.

Description : The Prototyping model of software development is: (1) a reasonable approach when requirements are well-defined. (2) a useful approach when a customer cannot define requirements clearly. (3) the ... projects with large development teams. (4) a risky model that rarely produces a meaningful product.

Last Answer : 1

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following statements is most correct? A. For small companies, long-term debt is the principal source of external financing. B. Current assets of the typical manufacturing firm account ... the financial manager to make a decision and not address the issue again for several months.

Last Answer : B. Current assets of the typical manufacturing firm account for over half of its total assets.

Description : The hurricane model implies that project estimates become more accurate as the  project's product becomes better understood.

Last Answer : Ans: True

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : WBS is produced by identifying the key elements, breaking each element down into  component parts and continuing to breakdown until manageable work packages have been identified. (True/False)

Last Answer : Ans. True

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : Kathryn has little experience estimating the time it will take to complete a systems  project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points  c. industry standards  d. Microsoft Project  e. more complex approach

Last Answer : c. industry standards

Description : Which model is used during early stages of the system  design afterthe requirements have been established? a) An application-composition model b) A post-architecture model c) A reuse model d) An early design model

Last Answer : d) An early design model

Description : Project managers can develop task lists for a project with the help of _____.  a. established methodologies  b. system proposals  c. system requests  d. user application hardware  e. user requirements

Last Answer : a. established methodologies

Description : Quality control in the final analysis is : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements  2. a production system  3. an inspection system  4. fitness for purpose

Last Answer : 1. using the technical procedures of monitoring project results to decide if the outputs meet  the requirements

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.