Describe RMMM Strategy.

1 Answer

Answer :

Risk mitigation, monitoring, and management (RMMM) plan. A risk management strategy can be included in the software project plan or the risk management steps can be organized into a separate Risk Mitigation, Monitoring and Management Plan. The RMMM plan documents all work performed as part of risk analysis and is used by the project manager as part of the overall project plan. Once RMMM has been documented and the project has begun, risk mitigation and monitoring steps commence. Risk mitigation is a problem avoidance activity. 

Risk monitoring is a project tracking activity with three primary objectives: 

(1) To assess whether predicted risks do, in fact, occur; (2) To ensure that risk aversion steps defined for the risk are being properly applied; and (3) To collect information that can be used for future risk analysis. 

In many cases, the problems that occur during a project can be traced to more than one risk. Another job of risk monitoring is to attempt to allocate origin (what risk(s) caused which problems throughout the project).

An effective strategy must consider three issues:

• Risk avoidance

• Risk monitoring

• Risk management and contingency planning. 

If a software team adopts a proactive approach to risk, avoidance is always the best strategy. This is achieved by developing a plan for risk mitigation. To mitigate this risk, project management must develop a strategy for reducing turnover. Among the possible steps to be taken are 

• Meet with current staff to determine causes for turnover (e.g., poor working conditions, low pay, and competitive job market).

• Mitigate those causes that are under our control before the project starts.

• Once the project commences, assume turnover will occur and develop techniques to ensure continuity when people leave.

• Organize project teams so that information about each development activity is widely dispersed.

• Define documentation standards and establish mechanisms to be sure that documents are developed in a timely manner.

• Conduct peer reviews of all work (so that more than one person is "up to speed).

• Assign a backup staff member for every critical technologist. As the project proceeds, risk monitoring activities commence. The project manager monitors factors that may provide an indication of whether the risk is becoming more or less likely. In the case of high staff turnover, the following factors can be monitored:

• General attitude of team members based on project pressures.

• The degree to which the team has jelled.

• Interpersonal relationships among team members.

• Potential problems with compensation and benefits.

• The availability of jobs within the company and outside it. 

In addition to monitoring these factors, the project manager should monitor the effectiveness of risk mitigation steps. RMMM steps incur additional project cost. Part of risk management, therefore, is to evaluate when the benefits accrued by the RMMM steps are outweighed by the costs associated with implementing them. In essence, the project planner performs a classic cost/benefit analysis.

Related questions

Description : Define proactive and reactive risk strategy.

Last Answer : Reactive risk strategies Reactive risk strategy follows that the risks have to be tackled at the time of their occurrence. No precautions are to be taken as per this strategy. They ... their probability of occurrence, their impact after occurrence, and steps to be followed for its precaution.

Description : Describe the Analytical method of project cost estimation with example.

Last Answer : Analytical estimation techniques derive the required results starting with basic assumptions regarding the project. Thus, unlike empirical and heuristic techniques, analytical techniques do have scientific basis. Halstead's ... the program, * N2 be the total number of operands used in the program.

Description : Describe 4 P’s of management spectrum giving their significance.

Last Answer : The Management Spectrum - 4 Ps and their Significance Effective software project management focuses on these items (in this order) Deals with the cultivation of motivated, highly skilled people ... 1998 survey, 26% of software projects failed outright, 46% experienced cost and schedule overruns.

Description : Explain the concept of black box testing and white box testing.

Last Answer : Black Box Testing: * It is a way of software testing in which the internal structure or the program or the code is hidden and nothing is known about it. * It also known as ... implementation. * White-box testing is time-consuming, bigger programming applications take the time to test fully.

Description : Compare CMMI and ISO for software w.r.to i)scope ii)Approach Iii) Implementation.

Last Answer : Difference between CMMI and ISO based on SCOPE: CMMI is rigid and extends only to businesses developing software intensive systems. ISO is flexible and applicable to all manufacturing industries. CMMI ... in-house teams, or rely on external auditors to see through the implementation process. 

Description : Explain six function of requirement engineering process.

Last Answer : Requirement Engineering: The broad spectrum of tasks and techniques that lead to an understanding of requirements is called requirements engineering. It starts during the communication activity and ... and track requirements and changes to requirements at any time as the project proceeds.

Description : Explain GANTT chart and its application for project tracking with an example. 

Last Answer : When creating software project schedule, we begin with a set of tasks. If automated tools are used, the work breakdown is input as a task network or task outline. Effort, duration and start date are then ... can also use Gantt charts to get an overview of how things are rolling on the work front. 

Description : Enlist core principles of software engineering practice.

Last Answer : 1. Reason it all exists. Provide value to the user 2.Keep it simple stupid 3.Maintain the vision 4. What you reproduce, someone else will have to consume. (implement knowing someone else will have to ... are doing) 5.Be open to the future 6. Plan ahead for reuse Plan ahead for reuse Think!

Description : Explain waterfall process model. State its advantages and disadvantages.

Last Answer : The waterfall model is a traditional method, sometimes called the classic life cycle. This is one of the initial models. As the figure implies stages are cascaded and shall be developed one ... 6. Not suitable for the projects where requirements are at a moderate to high risk of changing.

Description : With an example, explain Line of Code (LOC) based estimation.

Last Answer : LOC-Based Estimation: As an example of LOC and FP problem-based estimation techniques, let us consider a software package to be developed for a computer-aided design application for mechanical components. A ... guide, a preliminary statement of software scope can be developed: Example:

Description : Draw and explain Level 1 DFD for railway reservation system.

Last Answer : The passenger can initiate either Reservation process or Enquiry process; If a user opts for Reservation process then the system shall proceed with ticket generation process and same needs to ... enquiry module then appropriate request shall be entertain and result to be displayed to the user.

Description : Explain Process framework with a suitable diagram.

Last Answer : A process framework establishes the foundation for a complete software process by identifying a small number of framework activities that are applicable to all software projects; In addition, the ... the customer who evaluates the delivered product and provides feedback based on the evaluation.

Description : Explain four basic principles of software project scheduling.

Last Answer : Basic principles software project scheduling:  Compartmentalization: The project must be compartmentalized into a number of manageable activities and tasks. To accomplish compartmentalization, both the product and ... or part of a work product - Work products are often combined in deliverables 

Description : Explain the notations used for preparing a Data Flow diagram.

Last Answer : Circle: A circle (bubble) shows a process that transforms data inputs into data outputs. Data Flow: A curved line shows the flow of data into or out of a process or data store. Data Store: A ... Sink is an external entity and acts as a source of system inputs or sink of system outputs.

Description : State and explain with examples four categories of software.

Last Answer : Types / Categories of Software  1. System Software  1. System software is a collection of programs written to service other programs. 2. Few examples of system software are compilers, editors, ... database access are only a few of hundreds of applications.  Example: Microsoft word, Excel.

Description : Name four software quality assurance activities.

Last Answer : These activities are performed (or facilitated) by an independent SQA group that: i. Prepares an SQA plan for a project. ii. Participates in the development of the project's software ... handled according to a documented procedure. vi. Records any noncompliance and reports to senior management.

Description : Define software quality.

Last Answer : 1.Quality means that a product satisfies the demands of its specifications  2. It also means achieving a high level of customer satisfaction with the product  3. In software systems ... (e.g. maintainability or reusability) * Software specifications are often incomplete, inconsistent, or ambiguous

Description : Name two cost estimation approaches.

Last Answer : * Heuristic Estimation Approach * Analytical Estimation Approach * Empirical Estimation Approach

Description : Define software requirement specification.

Last Answer : Concept: A software requirements specification (SRS) is a document that is created when a detailed description of all aspects of the software to be built that must be specified before the ... written by Business Analysts who interact with client and gather the requirements to build the software.

Description : State two characteristics of Software.

Last Answer : Characteristics of software : * Software is developed or engineered; it is not manufactured in the classical sense. * Software doesn’t “wear out.” But it does deteriorate! * Although the industry is moving toward component-based construction, most software continues to be custom built.

Description : Define software. Draw the failure curve for software.

Last Answer : Definition of Software  Software is: 1. Instructions (computer programs) that when executed provide desired features, function, and performance; 2. Data structures that enable the programs to adequately ... hard copy and virtual forms that describes the operation and use of the programs.

Description : What is requirement engg. ? What is its need? What are different subtasks included in it?

Last Answer : Requirement Engineering:- Software process perspective, requirements engineering is a major software engineering action that begins during the communication activity and continues into the modeling activity. ... * Elaboration * Negotiation * Specification * Validation * Requirements management

Description : Write difference between cardinality and modaling.

Last Answer : Cardinality Modality Cardinality defines the range of object-to object Relationships Modality indicates whether or not a relationship between objects is mandatory Expected ... maximum numbers occurrences in relationship It gives minimum numbers occurrences in relationship

Description : Explain incremental process model using suitable diagram.

Last Answer : 1. Incremental model is also called as iterative enhancement model. 2. In this model the software is built in an incremental fashion. 3. Fig shows the project is divided into ... and it should be noted that the process flow for any increment can incorporate the prototyping paradigm. 

Description : Write importance of analysis modeling.

Last Answer : * Designing gets easier to the designer * Better understanding of system can be accomplished * System feasibility can be determined * Defines data objects * Describes data attributes  ... * Refines data objects * Creates a functional hierarchy represent behavior at different levels of detail 

Description : Explain different tasks of regions of spiral model with diagram.

Last Answer : Traditional method or model of software development Also encompasses all the essential development phases: * Requirements analysis * Design * Code * Test * Maintenance  ... appear controllable to the customer, particularly if the customer is more accustomed to the waterfall model.

Description : State attributes of good software.

Last Answer : 1. Functionality: It refers to the degree of performance of the software against its intended purpose. 2. Reliability: It refers to the ability of the software to provide desired functionality ... degree to which the software can keep on functioning in spite of being provided with invalid data.

Description : Describe a general strategy for creating a setup project that terminates installation if a specific file is not already installed on the target machine.

Last Answer : First, create a file search to search the file system for the specific file. Then create a launch condition to evaluate the results of the search. You can connect the launch condition to ... in the search's Property property in the expression specified by the launch condition's Condition property. 

Description : What does Strategy describe? A. The general direction in which an organization plans to move to attain its goals B. Framework for managerial decisions C. Leveraging strengths to gain competitive advantage D. All of these options

Last Answer : All of these options

Description : What does Strategy describe? A. The general direction in which an organization plans to move to attain its goals B. Framework for managerial decisions C. Leveraging strengths to gain competitive advantage D. All of these options

Last Answer : All of these options

Description : If selected for this position, can you describe your strategy for the first 90 days?

Last Answer : This depends on the job role. Make sure you break it down into

Description : _________must be developed to describe when and how testing will occur. A. Test Strategy B. Test Plan C. Test Design D. High Level document

Last Answer : B. Test Plan

Description : The following describe the strategy of Differentiation with Product Lifecycle Focus, except: a. develops an R&D competency to keep designs fresh and exciting. b. concentrates on the High End, Traditional ... . products maintains pace with the market. e. capacity is expanded as demand is increased.

Last Answer : c. prices are below average.