LOC-Based Estimation: As an example of LOC and FP problem-based estimation techniques, let us consider a software package to be developed for a computer-aided design application for mechanical components. A review of the System Specification indicates that the software is to execute on an engineering workstation and must interface with various computer graphics peripherals including a mouse, digitizer, high resolution color display and laser printer. Using the System Specification as a guide, a preliminary statement of software scope can be developed:

Example:

image

image

Related questions

Description : Describe the Analytical method of project cost estimation with example.

Last Answer : Analytical estimation techniques derive the required results starting with basic assumptions regarding the project. Thus, unlike empirical and heuristic techniques, analytical techniques do have scientific basis. Halstead's ... the program, * N2 be the total number of operands used in the program.

Description : Name two cost estimation approaches.

Last Answer : * Heuristic Estimation Approach * Analytical Estimation Approach * Empirical Estimation Approach

Description : Problems with using Lines of Code to measure the size of a product include(s) a) The creation of source code is only part of the development effort b) The Lines of Code (LOC) will differ between ... The final size (kLOC) can only be determined once the product is delivered e) All of the above.

Last Answer : e) All of the above.

Description : Which of the following are advantages of using LOC (lines of code) as a sizeoriented metric? (A) LOC is easily computed. (B) LOC is a language dependent measure. (C) LOC is a language independent measure. (D) LOC can be computed before a design is completed.

Last Answer : (A) LOC is easily computed.

Description : While estimating the cost of software, Lines of Code (LOC) and Function Points (FP) are used to measure which one of the following? (A) Length of code (B) Size of software (C) Functionality of software (D) None of the above

Last Answer : (B) Size of software

Description : Explain GANTT chart and its application for project tracking with an example. 

Last Answer : When creating software project schedule, we begin with a set of tasks. If automated tools are used, the work breakdown is input as a task network or task outline. Effort, duration and start date are then ... can also use Gantt charts to get an overview of how things are rolling on the work front. 

Description : Explain the concept of black box testing and white box testing.

Last Answer : Black Box Testing: * It is a way of software testing in which the internal structure or the program or the code is hidden and nothing is known about it. * It also known as ... implementation. * White-box testing is time-consuming, bigger programming applications take the time to test fully.

Description : Explain six function of requirement engineering process.

Last Answer : Requirement Engineering: The broad spectrum of tasks and techniques that lead to an understanding of requirements is called requirements engineering. It starts during the communication activity and ... and track requirements and changes to requirements at any time as the project proceeds.

Description : Explain waterfall process model. State its advantages and disadvantages.

Last Answer : The waterfall model is a traditional method, sometimes called the classic life cycle. This is one of the initial models. As the figure implies stages are cascaded and shall be developed one ... 6. Not suitable for the projects where requirements are at a moderate to high risk of changing.

Description : Draw and explain Level 1 DFD for railway reservation system.

Last Answer : The passenger can initiate either Reservation process or Enquiry process; If a user opts for Reservation process then the system shall proceed with ticket generation process and same needs to ... enquiry module then appropriate request shall be entertain and result to be displayed to the user.

Description : Explain Process framework with a suitable diagram.

Last Answer : A process framework establishes the foundation for a complete software process by identifying a small number of framework activities that are applicable to all software projects; In addition, the ... the customer who evaluates the delivered product and provides feedback based on the evaluation.

Description : Explain four basic principles of software project scheduling.

Last Answer : Basic principles software project scheduling:  Compartmentalization: The project must be compartmentalized into a number of manageable activities and tasks. To accomplish compartmentalization, both the product and ... or part of a work product - Work products are often combined in deliverables 

Description : Explain the notations used for preparing a Data Flow diagram.

Last Answer : Circle: A circle (bubble) shows a process that transforms data inputs into data outputs. Data Flow: A curved line shows the flow of data into or out of a process or data store. Data Store: A ... Sink is an external entity and acts as a source of system inputs or sink of system outputs.

Description : State and explain with examples four categories of software.

Last Answer : Types / Categories of Software  1. System Software  1. System software is a collection of programs written to service other programs. 2. Few examples of system software are compilers, editors, ... database access are only a few of hundreds of applications.  Example: Microsoft word, Excel.

Description : Explain incremental process model using suitable diagram.

Last Answer : 1. Incremental model is also called as iterative enhancement model. 2. In this model the software is built in an incremental fashion. 3. Fig shows the project is divided into ... and it should be noted that the process flow for any increment can incorporate the prototyping paradigm. 

Description : Explain different tasks of regions of spiral model with diagram.

Last Answer : Traditional method or model of software development Also encompasses all the essential development phases: * Requirements analysis * Design * Code * Test * Maintenance  ... appear controllable to the customer, particularly if the customer is more accustomed to the waterfall model.

Description : When publishing an ebook, couldn't they show page rather than "loc"?

Last Answer : But page numbers aren't static. Pages scale depending on your settings, so page 100 on your device will likely be page 175 on someone else's. Additionally, since many books (Amazon at least) ... for determining the audiobook timestamp, so there is a static index needed to keep these in sync.

Last Answer : LOC - Line of Control

Description : Nawaz Sharif proposed a new peace initiative with india starting with implementation of Four measures relating to cease-fire along the LOC, non-use of force or threat to use force, demilitarization ... Creek dispute B. Wuller Barrage C. Withdrawal of forces from Siachin D. Normalisation of trade

Last Answer : ANSWER: C

Description : Nawaz Sharif proposed a new peace initiative with india starting with implementation of Four measures relating to cease-fire along the LOC, non-use of force or threat to use force, demilitarization ... Creek dispute B. Wuller Barrage C. Withdrawal of forces from Siachin D. Normalisation of trade

Last Answer : ANSWER: C

Description : Nawaz Sharif proposed a new peace initiative with india starting with implementation of Four measures relating to cease-fire along the LOC, non-use of force or threat to use force, demilitarization ... Creek dispute B. Wuller Barrage C. Withdrawal of forces from Siachin D. Normalisation of trade

Last Answer : ANSWER: C

Description : Which of the following can estimate size of project directly from problem specification? A. LOC B. Function Point Metric C. Both D. None

Last Answer : B. Function Point Metric

Description : Which of the following technique overcomes drawback related to LOC? A. Project Planning Sheet B. Function Point Metric C. COCOMO D. COCOMO2

Last Answer : B. Function Point Metric

Description : The third type of comment is used by a tool called .................. for automatic generation of documentation. A) Java commenting B) Java generator C) Java doc D) Java loc

Last Answer : C) Java doc

Description : Which is not a size metric? (A) LOC (B) Function count (C) Program length (D) Cyclomatic complexity

Last Answer : (D) Cyclomatic complexity

Description : Which of the following is not a part of Performance Testing? a) Measuring Transaction Rate. b) Measuring Response Time. c) Measuring the LOC. d) None of the above

Last Answer : Ans : c

Description : When two or more successive footnotes refer to the same work which one of the following expressions is used? (A) ibid (B) et.al (C) op.cit : (D) loc.cit. 

Last Answer : Answer: A

Description : The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Java is 50. Estimate the effort (E) required to ... ) 25 person months (B) 75 person months (C) 62.5 person months (D) 72.5 person months

Last Answer : (C) 62.5 person months 

Description : Science bases its estimation of the size of a product on a) Files (Fi), Flows (Fl) and Processes (Pr) b) Lines of Code (kLOC) c) Function Points (FP) d) operands and operators e) Feature Points (FeP).

Last Answer : d) operands and operators

Description : Relationship based on unrelated level of activity and past data of cost is measured with help of A. cost estimation B. price estimation C. unit estimation D. production estimation

Last Answer : A. cost estimation

Description : An expert based test estimation is also known as A. Narrow band Delphi B. Wide band Delphi C. Bespoke Delphi D. Robust Delphi

Last Answer : A. Narrow band Delphi

Description : FP-based estimation techniques require problem decomposition based on (A) information domain values (B) project schedule (C) software functions (D) process activities

Last Answer : (C) software functions

Description : Compare CMMI and ISO for software w.r.to i)scope ii)Approach Iii) Implementation.

Last Answer : Difference between CMMI and ISO based on SCOPE: CMMI is rigid and extends only to businesses developing software intensive systems. ISO is flexible and applicable to all manufacturing industries. CMMI ... in-house teams, or rely on external auditors to see through the implementation process. 

Description : Describe RMMM Strategy.

Last Answer : Risk mitigation, monitoring, and management (RMMM) plan. A risk management strategy can be included in the software project plan or the risk management steps can be organized into a ... associated with implementing them. In essence, the project planner performs a classic cost/benefit analysis.

Description : Enlist core principles of software engineering practice.

Last Answer : 1. Reason it all exists. Provide value to the user 2.Keep it simple stupid 3.Maintain the vision 4. What you reproduce, someone else will have to consume. (implement knowing someone else will have to ... are doing) 5.Be open to the future 6. Plan ahead for reuse Plan ahead for reuse Think!

Description : Describe 4 P’s of management spectrum giving their significance.

Last Answer : The Management Spectrum - 4 Ps and their Significance Effective software project management focuses on these items (in this order) Deals with the cultivation of motivated, highly skilled people ... 1998 survey, 26% of software projects failed outright, 46% experienced cost and schedule overruns.

Description : Name four software quality assurance activities.

Last Answer : These activities are performed (or facilitated) by an independent SQA group that: i. Prepares an SQA plan for a project. ii. Participates in the development of the project's software ... handled according to a documented procedure. vi. Records any noncompliance and reports to senior management.

Description : Define software quality.

Last Answer : 1.Quality means that a product satisfies the demands of its specifications  2. It also means achieving a high level of customer satisfaction with the product  3. In software systems ... (e.g. maintainability or reusability) * Software specifications are often incomplete, inconsistent, or ambiguous

Description : Define proactive and reactive risk strategy.

Last Answer : Reactive risk strategies Reactive risk strategy follows that the risks have to be tackled at the time of their occurrence. No precautions are to be taken as per this strategy. They ... their probability of occurrence, their impact after occurrence, and steps to be followed for its precaution.

Description : Define software requirement specification.

Last Answer : Concept: A software requirements specification (SRS) is a document that is created when a detailed description of all aspects of the software to be built that must be specified before the ... written by Business Analysts who interact with client and gather the requirements to build the software.

Description : State two characteristics of Software.

Last Answer : Characteristics of software : * Software is developed or engineered; it is not manufactured in the classical sense. * Software doesn’t “wear out.” But it does deteriorate! * Although the industry is moving toward component-based construction, most software continues to be custom built.

Description : Define software. Draw the failure curve for software.

Last Answer : Definition of Software  Software is: 1. Instructions (computer programs) that when executed provide desired features, function, and performance; 2. Data structures that enable the programs to adequately ... hard copy and virtual forms that describes the operation and use of the programs.

Description : What is requirement engg. ? What is its need? What are different subtasks included in it?

Last Answer : Requirement Engineering:- Software process perspective, requirements engineering is a major software engineering action that begins during the communication activity and continues into the modeling activity. ... * Elaboration * Negotiation * Specification * Validation * Requirements management

Description : Write difference between cardinality and modaling.

Last Answer : Cardinality Modality Cardinality defines the range of object-to object Relationships Modality indicates whether or not a relationship between objects is mandatory Expected ... maximum numbers occurrences in relationship It gives minimum numbers occurrences in relationship

Description : Write importance of analysis modeling.

Last Answer : * Designing gets easier to the designer * Better understanding of system can be accomplished * System feasibility can be determined * Defines data objects * Describes data attributes  ... * Refines data objects * Creates a functional hierarchy represent behavior at different levels of detail 

Description : State attributes of good software.

Last Answer : 1. Functionality: It refers to the degree of performance of the software against its intended purpose. 2. Reliability: It refers to the ability of the software to provide desired functionality ... degree to which the software can keep on functioning in spite of being provided with invalid data.

Description : Value taken for Poverty line estimation in rural areas is _________________ -Economics 9th

Last Answer : The poverty line had been fixed at Rs 27 in rural areas and Rs 33 in urban areas, levels at which getting two meals may be difficult.

Description : Explain estimation of channel capacitance of CMOS.

Last Answer : Capacitance estimation: The dynamic response i.e. switching speed of MOS system depends on capacitance associated with the MOS devices which are formed by different layers in MOS transistors ... are due to three dimensional, distributed charge voltage relations within the device structure. 

Description : A(n) ____________ is a measure of program size based on the number and  complexity of inputs, outputs, queries, files, and program interfaces.  a. function point  b. line of code  c. project plan  d. standard module  e. workplan

Last Answer : a. function point

Description : In your own estimation how much does how you perceive yourself differ from how others generally tend to perceive you?

Last Answer : answer:I believe Fully well aware and cognizant of the LIE hidden in the middle of any beLIEf That I know myself better than anyone, I believe that I understand myself on a unique level as ... to justify their own feelings about you just because it makes them feel better about their own beLIEf's.