Estimates from the planning stage will need to be refined as the project progresses, 

because it is virtually impossible to develop an exact assessment of the project’s schedule 

before the analysis and design phases are conducted.

1 Answer

Answer :

Ans: True

Related questions

Description : In which of the following project phases is the project schedule developed? 1. Conceptual  2. Planning  3. Implementation  4. Design

Last Answer : 2. Planning

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : In the project planning, which of the following is considered as the most basic parameter  based on which all other estimates are made? A. project size B. project effort C. project duration D. project schedule

Last Answer : A. project size

Description : The life cycle can be said to consist of a series of phases. The  classical model is referred to as the waterfall model. Which phase  may be defined as The concept is explored and refined, ... client's requirements are elicited? (a) Requirements (b) Specification (c) Design d) Implementation

Last Answer : (a) Requirements

Description : Complete the following statement. As the project progresses into the  execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have  been avoided.

Last Answer : a. risks need to be checked off on activities that have been performed.

Description : Following are the phases of Project Management Life Cycle. Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (A) 3-2-1-4

Description : Following are the phases of Project Management Life Cycle.  Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery  (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (D) 4-3-2-1

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : The hurricane model implies that project estimates become more accurate as the  project's product becomes better understood.

Last Answer : Ans: True

Description : One of the greatest weaknesses of systems consulting firms is that they try to apply  estimates and methodologies that they have developed over time and applied to other  projects, most of which are very different from the current project.

Last Answer : Ans: False

Description : A risk is defined as what might happened to the ____________ of the project 1. assessment  2. detriment  3. schedule  4. cost  5. scope

Last Answer : 2. detriment

Description : The ____ of project closeout the assessment is to document the best practices and  lessons learned for use on future projects.

Last Answer : Ans. Primary purpose

Description : When estimating project time schedules using industry standards for a systems project,  the following values are acceptable: 15% for planning, 25% for analysis, 50% for design,  and 10% for implementation.

Last Answer : Ans: False

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : The primary components of the quality management function are : 1. quality planning  2. quality control and assurance  3. quantitative measurement  4. quantitative assessment of the project

Last Answer : 5. a and b

Description : The accuracy of an estimate should: a. decrease as a project progresses through its life cycle. b. increase as a project progresses through its life cycle. c. stay constant throughout the project life cycle. d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.

Description : The accuracy of an estimate should:  a. decrease as a project progresses through its life cycle.  b. increase as a project progresses through its life cycle.  c. stay constant throughout the project life cycle.  d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.

Description : “Risk” is usually _______ as the project progresses. (A) increases (B) reduces (C) remains same (D) becomes negligible

Last Answer : (B) reduces

Description : In the ____ stage, of project identification the project ideas generated above are  screened and a preliminary exercise is conducted to weed out the bad or unviable ideas.

Last Answer : Ans. Screening

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : The phases of a project life cycle are: a. starting, planning, control and closing. b. concept, definition, development, handover and closure. c. initiation, definition, planning, monitoring and operations. d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : The phases of a project life cycle are:  a. starting, planning, control and closing.  b. concept, definition, development, handover and closure.  c. initiation, definition, planning, monitoring and operations.  d. concept, definition, implementation and operations.

Last Answer : b. concept, definition, development, handover and closure.

Description : The project closing process is essential to overall project planning. What is considered one of  the most important steps in closing the project? 1. Insuring that plans are produced to implement ... .  3. Transition the lease of equipment to the owner  4. Satisfying the contractual obligations

Last Answer : 4. Satisfying the contractual obligations

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description : When developing a project's scope statement, which of the following should not be  included? 1. Project justification.  2. Cost/benefit analysis  3. Project deliverables  4. Measurable objectives

Last Answer : 1. Project justification.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : Evaluation process of proposed projects or groups of projects is known as: A. Project Analysis B. Project Compilation C. Project selection D. Project Documentation

Last Answer : C. Project selection

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.

Description : Which one of the following statements best defines an estimate?  a. An approximation of project time and cost targets, refined throughout the project life  cycle.  b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.

Last Answer : a. An approximation of project time and cost targets, refined throughout the project life  cycle.

Description : Traditional Work Breakdown Structures tend to  a. focus on the design of the system as oppose to the needs of the current phase and  iteration  b. force too many levels of detail early on for large ... project and difficult to compare across projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : During which stage of Risk planning are risks prioritized based on probability and impact? a. Identify Risks b. Plan Risk responses c. Perform Qualitative risk analysis d. Perform Quantitative risk analysis

Last Answer : c. Perform Qualitative risk analysis

Description : You are the project manager for a cable service provider. Your team members are  amiable with each other and are careful to make project decisions jointly. Which of the  following statements is true?  ... stage of Develop Project Team. D. They are in the forcing stage of Develop Project Team.

Last Answer : B. They are in the norming stage of Develop Project Team.

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : According to the PMBOK Guide, the project manager is identified and assigned  during which process?  A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process

Last Answer : C. Prior to beginning the Planning processes

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : Feasibility analysis is the first stage in the process of project development. (True/False)

Last Answer : Ans. True

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : Using typical industry standards for estimating project time schedules, the estimated  analysis phase would be 10 person-months for a systems project where the planning phase was completed in 7.5 person-months.

Last Answer : Ans: True

Description : Using typical industry standards for estimating project time schedules, the estimated  analysis phase would be 25 person-months for a systems project where the planning phase was completed in 30 person-months.

Last Answer : Ans: False

Description : The process of assigning values for the time and effort needed to perform a system  project is called _____.  a. analysis  b. estimation  c. identifying  d. planning

Last Answer : b. estimation

Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project.  Where will Ryan look first to locate the identifiable tasks he will record in his work plan?  a. ... . the project planning software available at the local bookstore  e. the website of his old college professor

Last Answer : c. the company training materials for the company methodology

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis