Description : Complete the following statement. As the project progresses into the execution phase: Select one: a. risks need to be checked off on activities that have been performed. b. the total risk on ... risk breakdown structure needs to be examined to be sure all the risk events have been avoided.
Last Answer : a. risks need to be checked off on activities that have been performed.
Description : The accuracy of an estimate should: a. decrease as a project progresses through its life cycle. b. increase as a project progresses through its life cycle. c. stay constant throughout the project life cycle. d. vary independently of where the project is in its life cycle.
Last Answer : b. increase as a project progresses through its life cycle.
Description : Estimates from the planning stage will need to be refined as the project progresses, because it is virtually impossible to develop an exact assessment of the project’s schedule before the analysis and design phases are conducted.
Last Answer : Ans: True
Description : Once the project is approved and moves into the planning stage, what happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis
Last Answer : d. Risks are identified with each major group of activities.
Description : Fill in the blank. There is _______ correlation between project complexity and project risk. Select one: a. an unknown b. a positive c. no d. a negative e. a general
Last Answer : b. a positive
Description : A Unit Price (UP) contract provides: 1. a reimbursement of allowable costs plus a fixed fee which is paid proportionately as the contract progresses 2. a reimbursement of allowable cost of services ... unit rates and the final price is dependent on the quantities needed to carry out the work.
Last Answer : 4. a fixed price where the supplier agrees to furnish goods and services at unit rates and the final price is dependent on the quantities needed to carry out the work
Description : Resorce requirement in project becomes constant while the project is in its _____ progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%
Last Answer : (D) 80 to 95%
Description : Jack is in charge of a project team. Due to an unexpected project change, some issues with the project have come up. Two key team members, Samantha and Felix, are arguing their ... concerns through conflict resolution. e. Delay this issue for now until it becomes a significant conflict.
Last Answer : a. Confront the problem early, and invite both Samantha and Felix to private meetings.
Description : Resorce requirement in project becomes constant while the project is in its progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%
Description : The hurricane model implies that project estimates become more accurate as the project's product becomes better understood.
Description : All of the following are true regarding the Qualitative Risk Analysis process except which one? A. Probability and impact and expert interview are used to help correct biases that occur in the data ... of this process used to determine which risks need near-term response plans.
Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and impact that usually takes a good deal of time to perform.
Description : The main aim of a project risk management process should be to: a. identify project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. c ... are threats or opportunities on a project. d. satisfy the organization's project management process.
Last Answer : a. identify project risks and then manage them appropriately.
Description : Who has ultimate responsibility for project risk? a. Steering group. b. Risk owner. c. Project sponsor. d. Project manager.
Last Answer : c. Project sponsor.
Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of alternative options. b. ensure ... the project. d. document the outcome of the risk, change and configuration management processes.
Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the project.
Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.
Last Answer : d. allocate work packages to those responsible for project work.
Description : Which one of the following statements about the project risk register is false? a. It facilitates the review and monitoring of risks. b. It facilitates the risk appetite. c. It facilitates the recording of risk responses. d. It facilitates the recording of risks.
Last Answer : b. It facilitates the risk appetite.
Description : The main outcome of risk identification, in a risk management process, is to: a. identify and determine the relative importance of the project risks. b. identify and describe all risks that ... responses to the project risks. d. identify and describe risks that have occurred on previous projects.
Last Answer : b. identify and describe all risks that might occur on the project.
Description : Project risk management is best described as: a. managing responses to threats. b. identifying and acknowledging threats and opportunities. c. planning responses to threats. d. minimising threats and maximising opportunities.
Last Answer : d. minimising threats and maximising opportunities.
Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.
Last Answer : d. Risk Breakdown Structure.
Description : Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities
Last Answer : C. Activity Resource requirements
Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover
Last Answer : c) Testing
Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management
Last Answer : C. project monitoring
Description : An Expected Monetary Value (EMV) of $100000 on a potential project event in the project means which of the following? Select one: a. A number that can be ignored b. An opportunity that ... Actual investment returns on the event e. A threat that must be considered to minimize the project risk
Last Answer : b. An opportunity that must be explored
Description : Which of the following statements about risk is true? Select one: a. Project risk focuses on identifying, assessing, and eliminating the risks on the project. b. Risk management is all ... are no risk-free projects. e. Risk management involves identification, evaluation, and elevation of risk
Last Answer : d. There are no risk-free projects.
Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against the potential benefit of the project’s success in order to decide if the project should be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation
Last Answer : e. initiation
Description : What should be done by the project manager to ensure that all the work in the project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.
Last Answer : c. Create a WBS.
Description : Fill in the blank. Risk represents the likelihood that an event will happen during the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack
Last Answer : b. achievement
Description : What is the most critical aspect in developing a project plan that meets project specifications within the timeframe and at the lowest costs? Select one: a. Assessing risk management b ... business partners e. Developing a project execution plan that matches the complexity level of the project
Last Answer : e. Developing a project execution plan that matches the complexity level of the project
Description : Fill in the blanks. It is during the ______________ phase that the decision should be made regarding whether the project should continue. During this phase, ____________ must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk
Last Answer : e. initiation, risk
Description : As a project manager, while Kathy was trying to categorize all potential risks for her new construction project M based on levels of probability and impact on the project, she identified a potential risk, ... b. Risk management plan c. Project management plan d. WBS e. Scope management plan
Last Answer : d. WBS
Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.
Last Answer : c. Identify potential project risks.
Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above
Last Answer : c. Track progress
Description : Which of the following is not considered as a risk in project management? a. Specification delays b. Product competition c. Testing d. Staff turnover
Last Answer : c. Testing
Description : Which risk is connected to the circumstance outside the project that may influence the scope of work and the performance of the organization? A.Operational Risk B.Financial Risk C.Strategic Risk D.Contextual Risk
Last Answer : D.Contextual Risk
Description : Risk Event Graph is having following on X axis A.Gantt Chart B.Work Break Down Structure C.Project Life Cycle D.Splitting
Last Answer : C.Project Life Cycle
Description : Risk in project management is defined as A.An uncertain event that, if it occurs, has a positive effect on project objectives B.An uncertain event that, if it occurs, has a negative ... effect on project objectives D.An uncertain event that do not have any effect on project objectives
Last Answer : C.An uncertain event that, if it occurs, has a positive or negative effect on project objectives
Description : Monte Carlo analysis can help predict the impact of risks on project deliverables. This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis
Last Answer : B. Quantitative Risk Analysis
Description : All of the following statements are true regarding risk events except which one? Choose the least correct answer. A. Project risks are uncertain events. B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of the risk should be accepted.
Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to plan for them.
Description : The process of assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes ... Risk Analysis B. Risk Identification C. Qualitative Risk Analysis D. Risk Management Planning
Last Answer : C. Qualitative Risk Analysis
Description : Once the logic of a network is laid out, the project manager will conduct a forward pass and a backward pass through the network. This will provide information regarding ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path
Last Answer : A. The total duration of the project, critical path
Description : The main aim of a project risk management process should be to: a. identifies project risks and then manage them appropriately. b. identify all project risks and transfer them immediately. ... are threats or opportunities on a project. d. satisfy the organisation's project management process.
Last Answer : a. identifies project risks and then manage them appropriately.
Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of alternative options. b ... managing the project. d. document the outcome of the risk, change and configuration management processes.
Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. ... response activities to project personnel. d. allocate work packages to those responsible for project work.