Christine does not have the skills that her project manager feels are necessary and no 

money has been budgeted for outside consultants. Mentoring is a good option to improve 

Christine’s skills in this situation.

1 Answer

Answer :

Ans: True

Related questions

Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at  completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000

Last Answer : d. $875,000

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description :  A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given:  Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index?  A.0.895  B.0.81  C.0.90  D.1.12

Last Answer : A.0.895

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : Who among the following are less able to influence a project? (A) Consultants (B) Contractors (C) Stakeholders (D) Project team

Last Answer : (B) Contractors

Description : Project Human Resource Management ensures that the most appropriate manpower with necessary skills is deployed for effective execution of the desired project. (True/False)

Last Answer : Ans. True

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Lauren, a systems analyst, has excellent interpersonal skills. To take advantage of her  skills, the functional lead of the project should assign her to program in Java and C++

Last Answer : Ans: False

Description : As a new project manager, Karen was worried about a statement from  her client: your project deliverable is in low quality with low grade .  According to PMBOK, how can you help Karen ... quality with high grade is always desirable to your client. e. High quality always  represents high grade.

Last Answer : c. Low quality represents a true problem, but low grade might not be the case.

Description : In ____ style, project manager shares his or her vision with the team but permits them to  use their respective ideas to come up with a solution.

Last Answer : Ans. Authoritative

Description : Project Manager must ensure that it develops appropriate trade off/s as  A. Time, cost and performance  B. Time, value and performance  C.Men, Materials and Machines  D.Money, Cost and Return on Investment

Last Answer : A. Time, cost and performance

Description : What are the key components in the "Triple constraint Triangle"?  A. Scope, Schedule, Cost, Project Manager B. Scope, Time, Cost, Project (Ans.) C. Time, Money, Scope, Project D. Project Manager, Time, Scope, Money

Last Answer : B. Scope, Time, Cost, Project (Ans.)

Description : Daniel has just been assigned as the project manager. To motivate his team properly,  Daniel’s first step is to award bonuses to team members

Last Answer : Ans: False

Description : You are a project manager for Cinema Snicker Productions. Your company  specializes in producing comedy films for the big screen. Your latest project has just been  cancelled because of budget cuts ... elsewhere. D. This project ended due to integration because the funding was cut off.

Last Answer : A. This project ended due to starvation because the funding was cut off.

Description : Complete the following statement. In a weak matrix environment, the  project manager, Eric, has to constantly make an effort to influence his  project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.

Last Answer : b. Eric has no or little authority.

Description : Sergei, the project manager, is worried about completing the project on time. To  increase the productivity of his 15-person team he should create subteams with no more  than 10 people on a sub team.

Last Answer : Ans: True

Description : Which one of the following statements best defines teamwork? a. People working collaboratively towards a common goal. b. Developing skills that will enhance project performance. c. Gathering the ... together to work on a project. d. Establishing vision and direction towards a common purpose.

Last Answer : a. People working collaboratively towards a common goal.

Description : According to the Project Management Institute (PMI), project  management is defined as the application of knowledge, _____, _____, and  techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories

Last Answer : d. skills, tools

Description : A ____ needs to possess excellent analytical and organizational skills to manage a project team

Last Answer : Ans. Project Manager

Description : Project leader role will require an individual with strong management skills. (True/False)

Last Answer : ns. True

Description : Matching people’s skills with the needs of the project, motivating employees, and  minimizing personnel conflict are all part of the staffing process.

Last Answer : Ans: True

Description : What is a key aspect of Project Manger leadership?  A. Great management skills  B. Negotiation  C. Creating a clear vision for the team to follow  D. Time management

Last Answer : C. Creating a clear vision for the team to follow

Description : Which one of the following statements best defines teamwork?  a. People working collaboratively towards a common goal .b. Developing skills that will enhance project performance.  c. Gathering the ... together to work on a project.  d. Establishing vision and direction towards a common purpose

Last Answer : a. People working collaboratively towards a common goal.

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : Following is(are) the responsibility(ies) of the project manager. (A) Budgeting and cost control (B) Allocating resources (C) Tracking project expenditure

Last Answer : (C) Tracking project expenditure

Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.

Last Answer : d. Application of processes and methods throughout the project life cycle.

Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.

Last Answer : d. The project manager.

Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the  sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.

Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Who has ultimate responsibility for project risk? a. Steering group. b. Risk owner. c. Project sponsor. d. Project manager.

Last Answer : c. Project sponsor.

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.

Last Answer : c. The project manager.

Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle. b. The business case is ... is owned by the project manager and is created during the definition phase of the  project life cycle.

Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the project life  cycle.

Description : Which one of the following best describes a project issue? a. A major problem that requires formal escalation. b. A problem that the project manager has to deal with on a day-to-day basis. c. An uncertain event that may or may not occur. d. An opportunity that occurs through change control.

Last Answer : a. A major problem that requires formal escalation.

Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations  and budget

Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and  meet stakeholder expectations.

Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements

Last Answer : A. Conduct Procurements

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.

Last Answer : d. Risk Breakdown Structure.

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description : The process each manager follows during the life of a project is known as a) Project Management b) Manager life cycle c) Project Management Life Cycle d) All of the mentioned

Last Answer : c) Project Management Life Cycle

Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above

Last Answer : D. all of the above

Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager

Last Answer : b) project

Description :  The process each manager follows during the life of a project is known as a) Project Management b) Manager life cycle c) Project Management Life Cycle d) All of the mentioned

Last Answer : c) Project Management Life Cycle