Description : CV = $70,000; AC = 90,000; Budget = $200,000. What percent of the project is complete? Select one: a. 80% b. 53% c. 45% d. 35% e. 75% Answer - a. 80% 39. As a project manager, John ... paid off the project. d. John's boss is happy. e. John and his team are promoted and get salary increases.
Last Answer : c. John’s client has paid off the project.
Description : Complete the following statement. In a weak matrix environment, the project manager, Eric, has to constantly make an effort to influence his project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.
Last Answer : b. Eric has no or little authority.
Description : As a project manager, Tyler is so happy that all expected project deliverable have been accomplished by his project team. What is the next step for his project to proceed in order to verify ... deliverables. e. Invite a few experts to judge the quality of all the completed project deliverables.
Last Answer : d. Ask his client to conduct an inspection on all of the completed project deliverables.
Description : . A project leader or manager is expected to be completely accountable for his team members and meeting the team’s targets. (True/False)
Last Answer : Ans. True
Description : Daniel has just been assigned as the project manager. To motivate his team properly, Daniel’s first step is to award bonuses to team members
Last Answer : Ans: False
Description : Sergei, the project manager, is worried about completing the project on time. To increase the productivity of his 15-person team he should create subteams with no more than 10 people on a sub team.
Last Answer : Ans: True
Description : After the celebration of the successful milestone completion, a project manager will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.
Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.
Description : You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and are in the performing ... will start all over again at the storming stage but quickly progress to the performing stage.
Last Answer : C. The team will start all over again with the forming stage.
Description : What is a key aspect of Project Manger leadership? A. Great management skills B. Negotiation C. Creating a clear vision for the team to follow D. Time management
Last Answer : C. Creating a clear vision for the team to follow
Description : During the project meeting, the project manager had to leave earlier due to a family emergency. Afterwards, a few team members started to argue, so the project meeting took very long without ... team members to take over more responsibilities. e. The project team was not very cooperative.
Last Answer : a. No project team ground rules were set up.
Description : In large organisations, project management shall be of line type function where the project manager shall have ____ and has total formal control over the division he or she heads
Last Answer : Ans. Full line authority
Description : Life cycle of a project manager ____ with the development life cycle.
Last Answer : Ans. Overlaps
Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.
Last Answer : d. Application of processes and methods throughout the project life cycle.
Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.
Last Answer : d. The project manager.
Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.
Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.
Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.
Last Answer : a. It utilizes resources as and when required under direction of a project manager.
Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.
Last Answer : b. to deliver the project objectives to enable benefits to be realised.
Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.
Last Answer : c. The project manager.
Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder
Last Answer : B. Project Team Members responsible for the work package
Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager
Last Answer : b) project
Description : Marco is an investor, and Jon is a project team member. Both have intensive technical background for the project that you are managing. However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company
Last Answer : c. The project team
Description : The project manager works with the project sponsor to identify the necessary resources and team members needed to further develop the key project parameters – Cost, Scope, Schedule, and Quality (CSSQ). (True/False)
Description : Quality planning is the process of developing a quality plan for (A) team (B) project (C) customers (D)project manager
Last Answer : (D)project manager
Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above
Last Answer : c. Track progress
Description : Who creates the project team? A. Factory manager B. Operation manager C. Project manager D.Purchase Manager
Last Answer : C. Project manager
Description : You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following statements is true? ... stage of Develop Project Team. D. They are in the forcing stage of Develop Project Team.
Last Answer : B. They are in the norming stage of Develop Project Team.
Description : .Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder
Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken ... on a project full time. d. Application of processes and methods throughout the project life cycle.
Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the sponsor. b. ... Management Plan is developed by the project manager and team and owned by the project manager.
Description : What is the last item a project manager must do to finalize project close-out? 1. Reassign the team 2. Contract completion 3. Archive the project records 4. Complete lessons learned 5. None of the above.
Last Answer : 2. Contract completion
Description : Expert power is the power that comes from the amount of knowledge a person has obtained in a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of expertise and also manage the project
Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of expertise and also manage the project
Description : As a new project manager, Karen was worried about a statement from her client: your project deliverable is in low quality with low grade . According to PMBOK, how can you help Karen ... quality with high grade is always desirable to your client. e. High quality always represents high grade.
Last Answer : c. Low quality represents a true problem, but low grade might not be the case.
Description : A ____ needs to possess excellent analytical and organizational skills to manage a project team
Last Answer : Ans. Project Manager
Description : Subsequent to preparing ____, the team plans the project schedule and budget
Last Answer : Ans. Work Breakdown Structure
Description : The project team documents its charge in the form of a ____, which is based on the project proposal and business case
Last Answer : Ans. Project charter
Description : A project charter does not include ____ of the project. (A) scope (B) objectives (C) team (D) all above are included
Last Answer : (D) all above are included
Description : Shauna has recently been appointed as a project manager for Project SkyNorth, which is regarded as an important project in her organization. During the project planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization
Last Answer : d. Projectized organization
Description : As a project manager, while Kathy was trying to categorize all potential risks for her new construction project M based on levels of probability and impact on the project, she identified a potential risk, ... b. Risk management plan c. Project management plan d. WBS e. Scope management plan
Last Answer : d. WBS
Description : Christine does not have the skills that her project manager feels are necessary and no money has been budgeted for outside consultants. Mentoring is a good option to improve Christine’s skills in this situation.
Description : In the ____ stage, of project identification the project ideas generated above are screened and a preliminary exercise is conducted to weed out the bad or unviable ideas.
Last Answer : Ans. Screening
Description : ____ is a continuous and repetitive process involving screening, documentation, validation, ranking and approval of viable project ideas for an organization.
Last Answer : Ans. Project identification
Description : Jack is in charge of a project team. Due to an unexpected project change, some issues with the project have come up. Two key team members, Samantha and Felix, are arguing their ... concerns through conflict resolution. e. Delay this issue for now until it becomes a significant conflict.
Last Answer : a. Confront the problem early, and invite both Samantha and Felix to private meetings.
Description : The most successful project manager usually: 1. works their way up from assistants in the project office to full-fledged project managers, supplementing that experience with formal ... . Has considerable experience as a functional manager before moving into the project management arena.
Last Answer : 1. works their way up from assistants in the project office to full-fledged project managers, supplementing that experience
Description : You are the project manager for a top-secret software project for an agency of the United States government. Your mission-should you choose to accept it-is to complete the project using internal resources ... of project ending is this? A. Starvation B. Extinction C. Addition D. Integration
Last Answer : C. Addition
Description : To successfully manage a project, the PM must play both a manager and leadership role. In the manager role the PM will do all but which of the following: 1. Develop procedures 2. Align people 3. Produce results for stakeholder 4. Focus on the organization and its structure 5. Both b and d
Last Answer : 2. Align people
Description : Which one of the following statements best defines teamwork? a. People working collaboratively towards a common goal. b. Developing skills that will enhance project performance. c. Gathering the ... together to work on a project. d. Establishing vision and direction towards a common purpose.
Last Answer : a. People working collaboratively towards a common goal.