Petri is working for Nokia in Finland. He has completed 10 months of his 12-month
project, budgeted at $800,000. His earned value analysis shows that variance at
completion is $75,000. What is the estimate at completion value for this project?
Select one:
a. 725,000
b. -725,000
c. -$875,000
d. $875,000
e. $800,000