A firm is about to undertake a project and has computed the NPV of the project using a
variety of discount rates:
Discount Rate used NPV
10% 130
15% 50
20% -50
What is the approximate IRR of this project?
A 20%
B 17.5%
C 15%
D 22.5%
variety of discount rates:
Discount Rate used NPV
10% 130
15% 50
20% -50
What is the approximate IRR of this project?
A 20%
B 17.5%
C 15%
D 22.5%