Which of the following is incorrect activity for the configuration

management of a system?

(A)Internship management

(B) Change management

(C) Version management

(D) System management

1 Answer

Answer :

(A)Internship management

Related questions

Description : Which of the following is incorrect activity for the configuration management of a software system? a) Internship management b) Change management c) Version management d) System management

Last Answer : a) Internship management

Description : Which of the following is incorrect activity for the configuration management of a software system? a) Internship management b) Change management c) Version management d) System management

Last Answer : a) Internship management

Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of  alternative options. b. ensure ... the  project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the  project.

Description : The main purpose of the Project Management Plan is to:  a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk  of alternative options.  b ... managing the project. d. document the outcome of the risk, change and configuration management processes.

Last Answer : c. document the outcomes of the planning process and provide the reference document for  managing the project.

Description : What combines procedures and tools to manage different versions of configuration objects that are created during the process? a) Change control b) Version control c) SCIs d) None of the mentioned

Last Answer : b) Version control

Description : Which of the following is not a Configuration Management  Activity? a) Configuration item identification b) Risk management c) Release management d) Branch management

Last Answer : b) Risk management

Description : Choose the correct option according to given below  statement. Statement 1: Umbrella activities are independent of any one framework activity and occur throughout the process. Statement 2: quality assurance, ... . c. Only statement 3 is correct. d. Statement 1 and statement 3 are correct

Last Answer : b. Statement 1 and statement 2 are correct.

Description : Following is (are) the tool(s) for changing a process (A)Change Management System (CMS) (B)Configuration Management (CM) (C)Both (A) and (B) (D)None of the above

Last Answer : (C)Both (A) and (B)

Description : Configuration management is best described as: a. control in the implementation of changes to project schedules. b. an organization to review proposed changes to the project deliverables ... and documentation. d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : Which is a configuration management concept that helps us to  control change without seriously impeding justifiable change? a) Baselines b) Source code c) Data model d) None of the mentioned

Last Answer : a) Baselines

Description : Configuration management is best described as:  a. control in the implementation of changes to project schedules.  b. an organisation to review proposed changes to the project deliverables ... and documentation.  d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : What involves preparing for external release and keeping track of the system versions that have been released for customer use? a) System building b) Release management c) Change management d) Version management

Last Answer : b) Release management

Description : Which of the following is the process of assembling program  components, data, and libraries, and then compiling and linking these to  create an executable system? a) System building b) Release management c) Change management d) Version management

Last Answer : a) System building

Description : Your company has asked you to be the project manager for the product introduction  of its new DeskTop Rock media system. You recently published the project scope  statement. Which ... . Constraints  B. Project specifications  C. Requested changes D. Project configuration management requirements

Last Answer : C. Requested changes

Description : The definition and use of configuration management standards is  essential for quality certification in a) ISO 9000 b) CMM c) CMMI d) All of the mentioned

Last Answer : d) All of the mentioned

Description : Configuration Management can be administered in several ways. These include a) A single configuration management team for the whole  organization b) A separate configuration management team for ... c) Configuration Management distributed among the project  members d) All of the mentioned

Last Answer : a) A single configuration management team for the whole  organization

Description : Which of the following software change management activities is most vital to assessing the impact of proposed software modifications? A. Baseline identification B. Configuration auditing C. Change control D. Version control

Last Answer : C. Change control

Description : Identify the incorrect statement in connection with working capital management. A. Long-term funds are more expensive than short-term funds but also riskier B. The objectives of ... fluctuating current assets E. Aggressive financing policies increase profitability at the cost of higher risk

Last Answer : A. Long-term funds are more expensive than short-term funds but also riskier

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Different activity of a project management is A. project planning B. project monitoring C. project control D. All of the above

Last Answer : B. project monitoring

Description : Which of the following is a requirement management activity ? a) Investigation b) Design c) Construction and Test d) All of the mentioned

Last Answer : d) All of the mentioned

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.

Last Answer : a. All variance to the project scope is evaluated.

Description : Which one of the following is least likely to be a success criteria? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : According to a statistical report: over 30% of all projects are cancelled before completion and over 70% of the remainder fail to deliver expected features . What must be the reason for such ... change management b) Poor requirements management c) Poor quality control d) All of the mentioned

Last Answer : b) Poor requirements management

Description : Which one of the following does project change control primarily seek to ensure?  a. All variance to the project scope is evaluated.  b. No reduction in the perceived quality of the project outcome ... project do not increase.  d. Any decrease in the scoped deliverable of the project is rejected

Last Answer : a. All variance to the project scope is evaluated.

Description : Which one of the following is least likely to be a success criterion?  a. A target for the project to receive zero change requests.  b. The date by which the project is to be completed.  c. Delivery of products that meet required specifications.  d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : The system of monitoring and control is more effective when, along with the time- frame, there is the linkage between the physical work to be performed in each activity and  the financial expenditure to be incurred. (True/False)

Last Answer : Ans. True

Description : . A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : Which of the following may generate a milestone list: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder

Last Answer : B. Project Team Members responsible for the work package

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management

Last Answer : C. project monitoring

Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation

Last Answer : B. Project Monitoring and Control

Description : Which of the following activity is undertaken immediately after feasibility study and before  the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling

Last Answer : A. Project Planning

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : Which one of the following is not a fundamental activity for processes in engineering ? a) Verification b) Validation c) design and implementation d) evolution e) specification

Last Answer : a) Verification

Description : quality assurance is an umbrella activity. a. True b. False

Last Answer : a. True

Description : The numbering of the nodes in A-O-A is done  A.From left to right B.From Right to Left  C.Randomly  D.On the basis of the duration of the activity

Last Answer : A.From left to right

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : The particular task performance in CPM is known  A.Dummy  B.Event  C.Activity  D.Contract.

Last Answer : C.Activity