Independent float is the amount of time by which: 

A. Start of the activity can be delayed without affecting the EST of subsequent 

activity 

B. reduces the float of subsequent activities 

C. completion of an activity can be delayed beyond EFT without affecting EST 

D. completion of an activity can be delayed beyond earliest possible finishing time

1 Answer

Answer :

A. Start of the activity can be delayed without affecting the EST of subsequent 

activity

Related questions

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : Free float is mainly used to (A) Identify the activities which can be delayed without affecting the total float of preceding activity (B) Identify the activities, which can be delayed ... which can be delayed without affecting the total float of either the preceding or succeeding activities

Last Answer : (B) Identify the activities, which can be delayed without affecting the total float of succeeding activity

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : The latest finish time for an activity: A. Equals the min. of LFT − t for al immediate successors B. Equals the max. of LFT − t for al immediate predecessors. C. Equals the max. of EST + t for all immediate predecessors. D. Equals the min. of EST + t for all immediate successors

Last Answer : A. Equals the min. of LFT − t for al immediate successors

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Choose the correct option according to given below  statement. Statement 1: Umbrella activities are independent of any one framework activity and occur throughout the process. Statement 2: quality assurance, ... . c. Only statement 3 is correct. d. Statement 1 and statement 3 are correct

Last Answer : b. Statement 1 and statement 2 are correct.

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : The independent float affects only (A) Preceding activities (B) Succeeding activities (C) The particular activity involved (D) None of the above

Last Answer : (C) The particular activity involved

Description : EST stands for ____________. A. Earliest Start Time. B. Event Start Time. C. Effective Start Time. D. Essential Start Time.

Last Answer : A. Earliest Start Time.

Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation

Last Answer : B. Project Monitoring and Control

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : Fill in the blank. During the _________ of a project, the project manager focuses on  developing the project infrastructure needed to execute the project and developing  clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Fill in the blank. During the _________ of a project, the project manager  focuses on developing the project infrastructure needed to execute the  project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection

Last Answer : b. start-up

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : Subsequent to preparing ____, the team plans the project schedule and budget

Last Answer : Ans. Work Breakdown Structure

Description : When would you measure the minimum preheat temperature? a) On completion of each pass b) Immediately prior to commencing the first pass and subsequent passes c) When the welding is ... preheat temperature measurement is only required if the heat input is lower than that specified in WPS

Last Answer : b) Immediately prior to commencing the first pass and subsequent passes

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Pick out the true statement pertaining to water treatment. (A) Slow sand filters can remove colour completely (B) Activated carbon can be used for taste & odour control without subsequent filtration ... of water (D) Normally, the turbidity is removed by adding a coagulant prior to sedimentation

Last Answer : (D) Normally, the turbidity is removed by adding a coagulant prior to sedimentation

Description : What are the 5 major processes of project management?  A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)  B. Starting, Closing, Managing, Planning, ... Finishing, Monitoring and Controlling, Executing, Planning D. Starting, Finishing, Executing, Managing, Closing

Last Answer : A. Closing, Executing, Planning, Monitoring and Controlling, Initiating (Ans.)

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : Which of the following may generate a milestone list: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : Which of the following may generate a milestone list: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations

Last Answer : A. Define Activities

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Who orchestrate the completion of the project by inducting the right people at the  right time to address the right issue and make the right decisions?  A.Project Coordinator  B.Project Manager  C.Operations Manager  D.Strategic Business Unit Head

Last Answer : B.Project Manager

Description : Which stage of project management life cycle requires the maximum time of  completion  A.Conceptualization  B.Planning  C.Execution  D.Estimation

Last Answer : C.Execution

Description : Creating a work plan requires three steps: identify the tasks that need to be  accomplished, estimate the time that it will take to complete the tasks, and record the task  completion time in a Gantt Chart.

Last Answer : Ans: False

Description : . When estimating project time schedules using industry standards, the estimated  project completion time for a systems project would be _____ person-months if the actual  planning phase were completed in 6 person-months.  a. 30  b. 40  c. 17.14  d. 9  e. 50

Last Answer : b. 40

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against  the potential benefit of the project’s success in order to decide if the project should  be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation

Last Answer : e. initiation

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk