Independent float is the amount of time by which:
A. Start of the activity can be delayed without affecting the EST of subsequent
activity
B. reduces the float of subsequent activities
C. completion of an activity can be delayed beyond EFT without affecting EST
D. completion of an activity can be delayed beyond earliest possible finishing time