Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.
Last Answer : a. overall project duration.
Description : Which of the following activity is not the part of project planning? A. project estimation B. project scheduling C. project monitoring D. risk management
Last Answer : C. project monitoring
Description : Which of the following activity is undertaken immediately after feasibility study and before the requirement analysis and specification phase? A. Project Planning B. Project Monitoring C. Project Control D. Project Scheduling
Last Answer : A. Project Planning
Description : In project scheduling, resources are allocated so that project objectives are attained within a ……… a. sensible time span b. lavish time c. excessive d. undue
Last Answer : a. sensible time span
Description : According to leading experts in software development, the margin of error when estimating project costs is 100% and the margin of error in project scheduling time is 25%.
Last Answer : Ans: True
Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan.
Description : A prerequisite of effective time management is: 1. Knowing the dictated project completion date 2. Having the most advanced software package for project planning, scheduling and control 3. ... and the person responsible for each of them 4. Having a well staffed scheduling department
Last Answer : 1. Knowing the dictated project completion date
Description : )Which of the following is NOT one of the primary needs for good project scheduling? 1. Cutting costs and reducing time 2. Decreasing the time required for decision making 3. Eliminating idle time 4. Developing better trouble shooting procedures.
Last Answer : 4. Developing better trouble shooting procedures.
Description : Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement. Which ... . Constraints B. Project specifications C. Requested changes D. Project configuration management requirements
Last Answer : C. Requested changes
Description : )The critical element in a project's communication system is the: 1. Progress report * 2. Project directive 3. Project manager 4. Customer
Last Answer : 3. Project manager
Description : Following is(are) the responsibility(ies) of the project manager. (A) Budgeting and cost control (B) Allocating resources (C) Tracking project expenditure
Last Answer : (C) Tracking project expenditure
Description : Which one of the following best describes project management? a. Using APM's Body of Knowledge 6th edition as a guide to all projects. b. Employing a project manager who has undertaken similar ... on a project full time. d. Application of processes and methods throughout the project life cycle.
Last Answer : d. Application of processes and methods throughout the project life cycle.
Description : Who are project team members primarily accountable to? a. External stakeholders. b. The end users. c. The finance director. d. The project manager.
Last Answer : d. The project manager.
Description : Which one of the following is true for the Project Management Plan (PMP)? a. The Project Management Plan is developed by the project manager and team and owned by the sponsor. b. A ... The Project Management Plan is developed by the project manager and team and owned by the project manager.
Last Answer : d. The Project Management Plan is developed by the project manager and team and owned by the project manager.
Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.
Last Answer : a. It utilizes resources as and when required under direction of a project manager.
Description : Who has ultimate responsibility for project risk? a. Steering group. b. Risk owner. c. Project sponsor. d. Project manager.
Last Answer : c. Project sponsor.
Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.
Last Answer : d. allocate work packages to those responsible for project work.
Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.
Last Answer : b. to deliver the project objectives to enable benefits to be realised.
Description : Who owns the Project Management Plan (PMP)? a. The project team. b. The chief executive. c. The project manager. d. The project support office.
Last Answer : c. The project manager.
Description : Which one of the following statements is true? a. The business case is owned by the sponsor and is created during the concept phase of the project life cycle. b. The business case is ... is owned by the project manager and is created during the definition phase of the project life cycle.
Last Answer : a. The business case is owned by the sponsor and is created during the concept phase of the project life cycle.
Description : Which one of the following best describes a project issue? a. A major problem that requires formal escalation. b. A problem that the project manager has to deal with on a day-to-day basis. c. An uncertain event that may or may not occur. d. An opportunity that occurs through change control.
Last Answer : a. A major problem that requires formal escalation.
Description : Which one of the following statements is true? a. Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget. ... Quality planning enables the project manager to manage the trade-off between customer expectations and budget
Last Answer : c. Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.
Description : Alice is a Project Manager. She is coordinating a bidder conference to allow vendors to get clarification on the work that needs to be performed. Which phase of Project Management is in progress. A. Conduct Procurements B. Plan Procurements C. Control Procurements D. Close Procurements
Last Answer : A. Conduct Procurements
Description : Activity Definition is typically performed by which of the following: A. Project Manager who created the WBS B. Project Team Members responsible for the work package C. Project Officer D. Project Stakeholder
Last Answer : B. Project Team Members responsible for the work package
Description : Andrew has joined as the Project Manager of a project. One of the project documents available to Andrew lists down all the risks in a hierarchical fashion. What is this document called? a. Risk Management Plan. b. List of risks. c. Monte Carlo diagram. d. Risk Breakdown Structure.
Last Answer : d. Risk Breakdown Structure.
Description : Quality planning is the process of developing a quality plan for a) team b) project c) customers d) project manager
Last Answer : b) project
Description : The process each manager follows during the life of a project is known as a) Project Management b) Manager life cycle c) Project Management Life Cycle d) All of the mentioned
Last Answer : c) Project Management Life Cycle
Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above
Last Answer : D. all of the above
Description : Shauna has recently been appointed as a project manager for Project SkyNorth, which is regarded as an important project in her organization. During the project planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization
Last Answer : d. Projectized organization
Description : Which of the following is true about a project manager? Select one: a. Project managers analyze work processes and explore opportunities to make improvements. b. Project managers are focused ... . d. Project managers are goal oriented. e. Project managers standardize the work processes.
Last Answer : d. Project managers are goal oriented.
Description : During a new project planning process to sequence activities, the project manager, Nate, decides to use the precedence diagraming method to show the identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers
Last Answer : b. Start-to-finish
Description : After the celebration of the successful milestone completion, a project manager will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.
Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.
Description : Fill in the blank. During the _________ of a project, the project manager focuses on developing the project infrastructure needed to execute the project and developing clarity around the project charter and scope. ... one: a. completion b. start-up c. execution d. evaluation e. selection
Last Answer : b. start-up
Description : What should be done by the project manager to ensure that all the work in the project is included? Select one: a. Create a contingency plan. b. Create a risk management plan. c. Create a WBS. d. Create a statement of work. e. Create a scope statement.
Last Answer : c. Create a WBS.
Description : During the project meeting, the project manager had to leave earlier due to a family emergency. Afterwards, a few team members started to argue, so the project meeting took very long without ... team members to take over more responsibilities. e. The project team was not very cooperative.
Last Answer : a. No project team ground rules were set up.
Description : CV = $70,000; AC = 90,000; Budget = $200,000. What percent of the project is complete? Select one: a. 80% b. 53% c. 45% d. 35% e. 75% Answer - a. 80% 39. As a project manager, John ... paid off the project. d. John's boss is happy. e. John and his team are promoted and get salary increases.
Last Answer : c. John’s client has paid off the project.
Description : When a project manager starts to plan a new project budget, the cost of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning
Last Answer : d. Closing
Description : Complete the following statement. In a weak matrix environment, the project manager, Eric, has to constantly make an effort to influence his project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.
Last Answer : b. Eric has no or little authority.
Description : As a project manager, while Kathy was trying to categorize all potential risks for her new construction project M based on levels of probability and impact on the project, she identified a potential risk, ... b. Risk management plan c. Project management plan d. WBS e. Scope management plan
Last Answer : d. WBS
Description : Marco is an investor, and Jon is a project team member. Both have intensive technical background for the project that you are managing. However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company
Last Answer : c. The project team
Description : What is considered to be the most useful skill for a project manager who works in a matrix environment in order to achieve project goals? Select one: a. Leadership skill b. Influencing c. Conflict management skill d. Time management e. Planning skill
Last Answer : b. Influencing
Description : Complete the following statement. As a project manager, Darrell is excited that he is assigned to be in charge of the most important project this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.
Last Answer : b. start to define and develop the stakeholder needs and requirements
Description : As a new project manager, Karen was worried about a statement from her client: your project deliverable is in low quality with low grade . According to PMBOK, how can you help Karen ... quality with high grade is always desirable to your client. e. High quality always represents high grade.
Last Answer : c. Low quality represents a true problem, but low grade might not be the case.
Description : As a project manager, Tyler is so happy that all expected project deliverable have been accomplished by his project team. What is the next step for his project to proceed in order to verify ... deliverables. e. Invite a few experts to judge the quality of all the completed project deliverables.
Last Answer : d. Ask his client to conduct an inspection on all of the completed project deliverables.
Description : In ____ style, project manager shares his or her vision with the team but permits them to use their respective ideas to come up with a solution.
Last Answer : Ans. Authoritative
Description : In large organisations, project management shall be of line type function where the project manager shall have ____ and has total formal control over the division he or she heads
Last Answer : Ans. Full line authority
Description : . A project leader or manager is expected to be completely accountable for his team members and meeting the team’s targets. (True/False)
Last Answer : Ans. True